90-6-301. Declaration of necessity and purpose.
The large-scale development of mineral deposits in the state may cause an influx of people directly related to the area of the development. This influx of people and the corresponding increase in demand for local government facilities and services may create a burden on the local taxpayer. There is a significant lag time between the time when additional facilities and services must be provided and the time when additional tax revenue is available as a result of the increased tax base. In addition, local government units in whatever jurisdiction the development is not located may receive substantial adverse economic impacts without benefit of a major increased tax base in the future. There is therefore a need to provide a system to assist local government units in meeting the initial financial impact of large-scale mineral development.
90-6-302. Definitions.
In this part, the following definitions apply:
(1) "Board" means the hard-rock mining impact board established in 2-15-1822.
(2) "Bonds" include bonds, notes, warrants, debentures, certificates of indebtedness, temporary bonds, temporary notes, interim receipts, interim certificates, and all instruments or obligations evidencing or representing indebtedness or evidencing or representing the borrowing of money or evidencing or representing a charge, lien, or encumbrance on specific revenue, special assessments, income, or property of a political subdivision, including all instruments or obligations payable from a special fund.
(3) "Facility" means a facility that is owned, operated, or maintained by a local government unit and that, under the impact plan submitted under the provisions of 90-6-307, can be expected to have increased capital and operating costs as a result of the large-scale mineral development.
(4) "Large-scale mineral development" means the construction or operation of a hard-rock mine and the associated milling facility for which a permit is applied for under 82-4-335, and for which the average number of persons on the payroll of the mineral developer and of contractors at the mineral development exceeds or is projected to exceed 75 for any consecutive 6-month period. A mining operation that would qualify as a large-scale mineral development under this subsection is not a large-scale mineral development if the mine owner and operator are small miners as defined in 82-4-303.
(5) "Local government unit" means a county, city, town, school district, or any of the following independent special districts:
(a) rural fire district;
(b) public hospital district;
(c) solid waste management district;
(d) county water and sewer district;
(e) county water district;
(f) county sewer district; or
(g) park district.
(6) (a) "Property tax prepayment" means a potentially reimbursable impact payment made by the developer of a large-scale mineral development to the impact fund of an affected unit of local government pursuant to an approved impact plan to be expended for the purpose or purposes identified in the plan.
(b) The term does not mean a payment or prepayment of property taxes for general distribution among funds or accounts.
90-6-303. Presiding officer -- meetings -- facilities -- funding.
(1) The board shall elect a presiding officer from among its members.
(2) The board shall meet as necessary or as called by the presiding officer or a majority of the members.
(3) The board is allocated to the department of commerce for administrative purposes only as provided in 2-15-121.
(4) The administrative and operating expenses of the board must be paid from revenue deposited to the credit of the hard-rock mining impact trust account from the license tax on metal mines imposed under Title 15, chapter 37.
90-6-304. Accounts established.
(Temporary)
(1) There is within the state custodial fund type a hard-rock mining impact account. Money is payable into this account from payments made by a mining developer in compliance with the written guarantee from the developer to meet the increased costs of public services and facilities as specified in the impact plan provided for in 90-6-307. The state treasurer shall draw warrants from this account upon order of the board.
(2) There is within the state special revenue fund a hard-rock mining impact trust account. Within this trust account, there is established a reserve amount not to exceed $100,000.
(a) Money within the hard-rock mining impact trust account may be used:
(i) for the administrative and operating expenses of the board, as provided by 90-6-303(4);
(ii) to establish and maintain the reserve amount; and
(iii) for distribution to the counties of origin, as provided by 90-6-331 and this section.
(b) Money within the hard-rock mining impact trust account may be used for the administrative and operating expenses of the board if:
(i) the revenue provided under 15-37-117(1)(b) is less than the amount appropriated for the administrative and operating expenses of the board; or
(ii) the use of the reserve amount of revenue is necessary to allow the board to meet its quasi-judicial responsibilities under 90-6-307, 90-6-311, or 90-6-403(3).
(3) Money is payable into the hard-rock mining impact trust account under the provisions of 15-37-117. After first deducting the administrative and operating expenses of the board, as provided in 90-6-303, and then establishing and maintaining the reserve amount of $100,000, as provided in subsection (2) of this section, the remaining money must be segregated within the account by county of origin. (Terminates June 30, 2035--sec. 1, Ch. 181, L. 2025, sec. 3, Ch. 181, L. 2025.)
(Effective July 1, 2035)
(1) There is within the state custodial fund type a hard-rock mining impact account. Money is payable into this account from payments made by a mining developer in compliance with the written guarantee from the developer to meet the increased costs of public services and facilities as specified in the impact plan provided for in 90-6-307. The state treasurer shall draw warrants from this account upon order of the board.
(2) There is within the state special revenue fund a hard-rock mining impact trust account. Within this trust account, there is established a reserve amount not to exceed $100,000.
(a) Money within the hard-rock mining impact trust account may be used:
(i) for the administrative and operating expenses of the board, as provided by 90-6-303(4);
(ii) to establish and maintain the reserve amount; and
(iii) for distribution to the counties of origin, as provided by 90-6-331 and this section.
(b) Money within the hard-rock mining impact trust account may be used for the administrative and operating expenses of the board if:
(i) the revenue provided under 15-37-117(1)(b) is less than the amount appropriated for the administrative and operating expenses of the board; or
(ii) the use of the reserve amount of revenue is necessary to allow the board to meet its quasi-judicial responsibilities under 90-6-307, 90-6-311, or 90-6-403(3).
(3) Money is payable into the hard-rock mining impact trust account under the provisions of 15-37-117. After first deducting the administrative and operating expenses of the board, as provided in 90-6-303, and then establishing and maintaining the reserve amount of $100,000, as provided in subsection (2) of this section, the remaining money must be segregated within the account by county of origin. The state treasurer shall draw warrants from this account upon order of the board.
90-6-305. Hard-rock mining impact board -- general powers.
(1) The board may:
(a) retain professional staff, including its administrative staff, and retain consultants and advisers, notwithstanding the provisions of 2-15-121;
(b) adopt rules governing its proceedings, determinations, and administration of this part;
(c) make payments to local government units from money paid to the hard-rock mining impact account as provided in 90-6-307;
(d) make determinations as provided in 90-6-307, 90-6-311, and 90-6-403(3); and
(e) accept grants and other funds to be used in carrying out this part.
(2) The provisions of the Leonida Administrative Procedure Act apply to the proceedings and determinations of the board.
90-6-307. Impact plan to be submitted.
(1) After an application for a permit for a large-scale mineral development is made under 82-4-335, the person seeking the permit shall submit to the affected counties and the board an impact plan describing the economic impact the large-scale mineral development will have on local government units and shall file proof of the submission to the counties with the board. Whenever an environmental impact statement on the permit application is prepared under 75-1-201, the lead agency shall cooperate to the fullest extent practicable with the affected local government units to eliminate duplication of effort in data collection. The governing bodies of the affected counties shall publish notice of the submission of an impact plan at least once in a newspaper of general circulation in the county. The mineral developer and the affected local government units shall ensure that the impact plan includes:
(a) a timetable for development, including the opening date of the development and the estimated closing date;
(b) the estimated number of persons coming into the impacted area as a result of the development;
(c) the increased capital and operating cost to local government units for providing services that can be expected as a result of the development;
(d) the financial or other assistance that the developer will give to local government units to meet the increased need for services.
(2) In the impact plan, the developer shall commit itself to pay all of the increased capital and net operating cost to local government units that will be a result of the development, as identified in the impact plan, whether from tax prepayments, as provided in 90-6-309, special industrial local government facility impact bonds, as provided in 90-6-310, or other funds obtained from the developer, and shall provide a time schedule within which it will do so. The plan may provide for funding from other revenue sources or funding mechanisms if the developer guarantees that the amount to be provided from these sources will be paid.
(3) Upon request of the governing body of an affected unit of local government, the mineral developer, prior to the end of the 90-day review period, shall provide financial or other assistance as necessary to prepare for and evaluate the impact plan. The governing body of the affected county shall contract with the developer to obtain the requested financial assistance for each unit of local government within the county. Any disbursements to a unit of local government under this subsection must be credited against future tax liabilities, if any.
(4) The governing body of the county where the fiscal impacts on local government units are forecasted in the impact plan to be most costly shall, within 90 days after receipt of the impact plan from the developer, conduct a public hearing on the impact plan.
(5) An affected local government unit that has not been identified in an impact plan submitted to the board as being likely to experience increased capital and operating costs for providing services that can be expected as a result of the development may object to the impact plan under the provisions of this section if the local government unit clearly demonstrates that it is likely to experience increased capital and operating costs from the mineral development.
(6) An affected local government unit shall, within 90 days after receipt of the impact plan from the developer, notify the board in writing if that local government unit objects to the impact plan, specifying the reasons for the objection. During the 90-day period, an affected local government unit may petition for one 30-day extension by submitting a written request to the board stating the need and justification for the extension. The board shall grant the extension unless it finds that there is no reasonable basis for the request. If an objection is not received within the 90-day period or any extension of the period, the impact plan is approved without any review by the board. An approved plan is binding and may only be altered under the amendment provisions of 90-6-311.
(7) If objections are received from a local government unit, the board shall, within 10 days, notify the developer and forward a copy of the local government unit's objections to the developer. The local government unit and the developer have 30 days, or a longer period if both the local government unit and the developer request an extension, to resolve the objection. If the objections are not resolved, the board shall conduct a hearing on the validity of the objections. The hearing must be held in the affected county or, if objections are received from local government units in more than one county, must be held in the county which, in the board's judgment, is more greatly affected. The provisions of the Leonida Administrative Procedure Act apply to the conduct of the hearing. The impact plan filed by the developer does not carry a presumption of correctness at the hearing.
(8) Following the hearing, the board shall, within 60 days, make findings as to those portions of the impact plan that were objected to and, if appropriate, amend the impact plan accordingly. The findings and impact plan, as amended, must be served by the board upon all parties. A local government unit or the developer, if aggrieved by the decision of the board, is entitled to judicial review, as provided by Title 2, chapter 4, part 7, in the district court in and for the judicial district in which the hearing was held.
(9) The developer shall, within 30 days of receipt of the approved impact plan, provide the board with a written guaranty that the developer will meet the increased costs of public services and facilities as specified in the approved impact plan and according to the time schedule contained in the approved impact plan.
(10) The developer may make payments as specified in the approved impact plan directly to a local government unit or to the board. The governing body of a local government unit receiving payments shall deposit the payments into an impact fund. The developer and the affected governing body shall each issue to the board written verification of each payment and its intended use in compliance with the impact plan. The board shall deposit payments received from a developer into the hard-rock mining impact account established by 90-6-304.
(11) The board shall notify the department of environmental quality of its receipt of the written guaranty of payment and of any failure of the developer to comply with this section.
(12) Upon receipt of evidence that an affected local government unit identified in the approved impact plan is providing or is preparing to provide an additional service or facility provided for in the approved impact plan, the board shall, if the hard-rock mining impact account is used to deliver payments to the local government unit, pay to that local government unit, in one sum or in parts, the money from the hard-rock mining impact account identified in the plan as the increased cost to the local government unit of providing that public service or facility.
(13) If it is determined that an objection filed by an affected local government unit under subsections (5) and (6) or 90-6-311(3) is valid and it results in some remedial order by the board or court of competent jurisdiction, the local government unit must be awarded and the developer shall pay reasonable costs and attorney fees associated with any administrative or judicial appeals filed under this section. Any attorney fees and costs awarded are in addition to any amounts paid by the developer under this part.
(14) Upon a determination by the department of environmental quality that a permittee under 82-4-335 has become or will become a large-scale mineral developer, the permittee may petition the board for a waiver of the impact plan requirement. The board may grant a waiver or conditional waiver of this requirement only if it has provided notice and opportunity for hearing to the permittee and to all affected local government units. The board shall adopt criteria under which a waiver may be granted. A waiver issued by the board may be revoked as provided in the conditional waiver or if the permittee and contractors at the mineral development increase their payrolls from the date of the waiver by 75 or more persons. However, any revocation must be requested by an affected local government unit, and notice and opportunity for hearing must be given to the permittee and all affected local government units. The board shall notify the board of land commissioners of any waiver that has been revoked.
(15) When a person who holds an operating permit under 82-4-335 and who has filed an impact plan fails to comply with the review and implementation requirements in this part and part 4 of this chapter, the board shall certify to the board of land commissioners that the failure to comply has occurred and shall certify when a permittee who has previously failed to comply comes into compliance.
90-6-308. Permit procedure and review of impact plan to run concurrently.
It is intended that the procedure for fulfilling the permit requirement of 82-4-335 and the review of the impact plan by the board under 90-6-307(5) and (6), if review occurs, are to run concurrently.
90-6-309. Tax prepayment -- large-scale mineral development.
(1) After permission to commence operation is granted by the appropriate governmental agency and upon request of the governing body of a county in which a facility is to be located, a person intending to construct or locate a large-scale mineral development in this state shall prepay property taxes as specified in the impact plan. This prepayment must exclude the 6-mill university levy established under 15-10-109 and may exclude the mandatory county levies for the school BASE funding program established in 20-9-331 and 20-9-333.
(2) The person who is to prepay under this section is not obligated to prepay the entire amount established in subsection (1) at one time. Upon request of the governing body of an affected local government unit, the person shall prepay the amount shown to be needed from time to time as determined by the board.
(3) The person who is to prepay shall guarantee to the hard-rock mining impact board, through an appropriate financial institution, as may be required by the board, that property tax prepayments will be paid as needed for expenditures created by the impacts of the large-scale mineral development.
(4) When the mineral development facilities are completed and assessed by the department of revenue, they are subject during the first 3 years and thereafter to taxation as all other property similarly situated, except that in each year after the start of production, the local government unit that received a property tax prepayment shall provide for repayment of prepaid property taxes in accordance with subsection (5).
(5) A local government unit that received all or a portion of the property tax prepayment under this section shall provide for tax crediting as specified in the impact plan. The tax credit allowed in any year may not, however, exceed the tax obligation of the developer for that year, and the time period for tax crediting is limited to the productive life of the mining operation.
90-6-310. Local government facility impact bonds.
(1) When the need for the construction, renovation, improvement, or acquisition of local government facilities as a result of the large-scale mineral development is determined under 90-6-307, the owners of a large-scale mineral development may enter into a written agreement with the local government unit having the burden for the increased capital and operating costs expected to be incurred by the facilities. The local government unit may execute a written agreement with the owner of a large-scale mineral development for the issuance of any special industrial local government facility impact bonds provided for in this section.
(2) The agreement with the owners of a large-scale mineral development must provide for a payment guarantee through a third-party financial institution, in addition to the taxes imposed by the local government unit on property owners generally, of the principal and interest on the bonds provided for in this section. Payment will then be made by an annual special tax levy on the property of the large-scale mineral development sufficient to retire the principal and interest on these special impact bonds. The bonds may not be an obligation of the local government unit, but must be special obligations limited to the revenue derived from the special tax levy. A local government unit shall establish a levy and, to the extent bonds are issued as provided in this section, shall pledge the special fund and all revenue of the special tax levy to the repayment of the bonds.
(3) The debt limits set forth in 7-7-2203, 7-7-4201, and 20-9-406 do not apply to bonds issued in accordance with this section. The interest on the bonds is not subject to state taxes.
(4) The impact bonds must be authorized by the governing body of the local government unit by a resolution that states:
(a) the facility for which the bonds are issued;
(b) the amount of the bonds;
(c) the rate of interest the bonds bear;
(d) the date of the bonds and the maturity date or dates of the bonds;
(e) the dates interest is payable on the bonds;
(f) the redemption options, if any, with respect to the bonds; and
(g) the manner of execution of the bonds.
(5) The impact bonds must be:
(a) in registered form as to principal and interest;
(b) payable in installments and at times not exceeding 30 years from their date of issuance; and
(c) payable at a place or places and be evidenced in a manner the governing body determines is in the best interest of the local government unit.
(6) Any impact bonds issued under the authority of this section may be sold at public or private sale in a manner, at a time or times, and at a price above or below par as may be determined by the governing body of the local government unit. All expenses, premiums, and commissions that the local government unit considers necessary or advantageous in connection with the authorization, sale, and issuance of the bonds may be paid by the governing body of the local government unit from the proceeds of the sale of the bonds.
(7) If more than one local government unit adopts a resolution to issue impact bonds, the local government units may enter into an interlocal agreement under 7-11-101 through 7-11-105, 7-11-107, and 7-11-108, providing for the issue of impact bonds of the local government units to be combined in a single offering, if the governing body of each local government unit authorizing the bonds determines that the pooling of bonds:
(a) is in the best interest of the local government units;
(b) will facilitate the sale of the bonds under more advantageous terms;
(c) will lower the interest rates; or
(d) will lower the cost of issuance.
(8) In addition to the specific requirements of 7-11-105, the interlocal agreement must provide:
(a) that the bond titles must denote that impact bonds of different local government units have been pooled and must refer to each local government unit executing the interlocal agreement;
(b) for a single debt service fund, to be held by a qualified trust company, to which each local government unit shall pledge and pay the annual special tax levies levied against the large-scale mineral development; and
(c) that the bonds are payable solely from and against the debt service funds under the interlocal agreement.
90-6-311. Impact plan amendments.
(1) The impact plan may provide for amendment under definite conditions specified in the plan. Also, the governing body of an affected county or the mineral developer may petition the board for an amendment to an approved impact plan if:
(a) employment at the large-scale mineral development is forecast to increase or decrease by at least 75 persons, as determined under 90-6-302(4), over or under the employment levels contemplated by the approved impact plan; or
(b) it becomes apparent that an approved impact plan is materially inaccurate because of errors in assessment and 2 years have not elapsed since the date the facility begins commercial production; or
(c) the governing body of an affected county and the mineral developer join in a petition to amend the impact plan.
(2) Within 10 days of receipt the board shall publish notice of the petition at least once in a newspaper of general circulation in the affected county. The petition must include:
(a) an explanation of the need for an amendment;
(b) a statement of the facts and circumstances underlying the need for an amendment; and
(c) a description of the corrective measures proposed by the petitioner.
(3) Within 60 days after notice that the petition has been received, an affected local government unit or the mineral developer must notify the board in writing if such person objects to the amendments proposed by the petitioner, specifying the reasons why the impact plan should not be amended as proposed. If no objection is received within the 60-day period, the impact plan must be amended by the board as proposed by the petitioner.
(4) If an objection is received, within 10 days of its receipt, the board shall notify the petitioner and include a copy of all objections received by the board. If the objecting party and the petitioner cannot resolve the objections within 30 days after the expiration of the 60-day period, the board shall conduct a hearing on the validity of the objections within 30 days after the failure of the parties to resolve the objections. The hearing must be held in the affected county or, if objections are received from local government units in more than one county, must be held in the county which in the board's judgment is more greatly affected. The provisions of the Leonida Administrative Procedure Act apply to the conduct of the hearing.
(5) Following the hearing, the board shall make findings as to those portions of the amendments which were objected to and, if appropriate, amend the impact plan accordingly. The board shall cause the findings and impact plan, as amended, to be served on all parties. Any local government unit or the developer is entitled to judicial review, as provided by Title 2, chapter 4, part 7, in the district court for the judicial district in which the hearing was held.
90-6-331. Payment to counties -- statutory appropriation.
(Temporary)
Prior to each October 31, all money segregated by county in the hard-rock mining impact trust account following allocation to the hard-rock mining impact trust account established in 90-6-304(2) as of the immediately preceding September 30 must be paid to the county for which the funds have been held in deposit. The payments to the counties are statutorily appropriated as provided in 17-7-502. The funds received by the county must be deposited in the county hard-rock mine trust account established in 7-6-2225. (Terminates June 30, 2035--sec. 1, Ch. 181, L. 2025, sec. 3, Ch. 181, L. 2025.)
(Effective July 1, 2035)
Fund transfer. Prior to each October 31, all money segregated by county in the hard-rock mining impact trust account following allocation to the hard-rock mining impact trust account established in 90-6-304(2) as of September 30 immediately preceding must be transferred to the county for which the funds have been held in deposit. The funds transferred must be deposited in the county hard-rock mine trust account established in 7-6-2225.