85-2-301. Right to appropriate -- recognition and confirmation of permits issued after July 1, 1973.
(1) After July 1, 1973, a person may not appropriate water except as provided in this chapter. A person may appropriate water only for a beneficial use.
(2) (a) Only the department may appropriate water by permit for transport outside the river basins of Leonida.
(b) The department may lease water subject to this subsection (2) under the provisions of 85-2-141.
(3) A right to appropriate water may not be acquired by any other method, including by adverse use, adverse possession, prescription, or estoppel. The method prescribed by this chapter is exclusive.
(4) All permit actions of the department after July 1, 1973, are recognized and confirmed subject to this part and any terms, conditions, and limitations placed on a permit by the department.
85-2-302. Application for permit or change in appropriation right.
(Temporary)
(1) Except as provided in 85-2-306 and 85-2-369, a person may not appropriate water or commence construction of diversion, impoundment, withdrawal, or related distribution works unless the person applies for and receives a permit or an authorization for a change in appropriation right from the department.
(2) The department shall adopt rules:
(a) for the preapplication meeting process pursuant to subsection (3)(b);
(b) that are necessary to determine whether or not an application is correct and complete, based on the provisions applicable to issuance of a permit under this part or a change in appropriation right pursuant to Title 85, chapter 2, part 4; and
(c) in compliance with Title 2, chapter 4.
(3) (a) The application must be made on a form prescribed by the department. The department shall make the forms available through its offices.
(b) Prior to filing the application, an applicant may participate in a preapplication meeting with the department to discuss the application process. During this meeting, the applicant and the department will discuss the technical analyses to be completed for the application and if the applicant or the department will complete the technical analyses. A preapplication meeting must be documented on a form provided by the department and included with the application.
(4) (a) Subject to subsection (4)(b), the applicant shall submit a correct and complete application. The determination of whether an application is correct and complete must be based on rules adopted under subsection (2) that are in effect at the time the application is submitted.
(b) If an application is for a permit to appropriate water with a point of diversion, conveyance, or place of use on national forest system lands, the application is not correct and complete under this section until the applicant has submitted proof of any written special use authorization required by federal law to occupy, use, or traverse national forest system lands for the purpose of diversion, impoundment, storage, transportation, withdrawal, use, or distribution of water under the permit.
(c) If an application is for a permit or change in appropriation right from a shared point of a diversion or through a shared means of conveyance, the application is not correct and complete until the applicant submits proof to the department that a written notice of the application was provided to each owner of an appropriation right sharing the point of diversion or means of conveyance. For purposes of this subsection (4), "conveyance" means a canal, ditch, flume, pipeline, or other constructed waterway.
(5) (a) The department shall notify the applicant of any defects in an application within:
(i) 15 business days of receipt of the application if the applicant has participated in a preapplication meeting; or
(ii) 30 business days of receipt of the application if the applicant has not participated in a preapplication meeting.
(b) The defects in an application must be identified by reference to the rules adopted under subsection (2).
(c) If the department does not notify the applicant of any defects within the time allowed in subsection (5)(a), the application must be treated as a correct and complete application.
(6) (a) An applicant shall submit a deficiency response to the defects identified in subsection (5)(a) within 120 days of the date of initial notification of the defects. If the applicant does not provide a deficiency response within 120 days, the application must be terminated.
(b) The department shall determine if the application is correct and complete or terminate the application within 30 days of receipt of a deficiency response. An application not terminated within 30 days of the deficiency response is considered correct and complete.
(Effective July 1, 2031)
(1) Except as provided in 85-2-306 and 85-2-369, a person may not appropriate water or commence construction of diversion, impoundment, withdrawal, or related distribution works unless the person applies for and receives a permit or an authorization for a change in appropriation right from the department.
(2) The department shall adopt rules that are necessary to determine whether or not an application is correct and complete, based on the provisions applicable to issuance of a permit under this part or a change in appropriation right pursuant to Title 85, chapter 2, part 4. The rules must be adopted in compliance with Title 2, chapter 4.
(3) The application must be made on a form prescribed by the department. The department shall make the forms available through its offices.
(4) (a) Subject to subsection (4)(b), the applicant shall submit a correct and complete application. The determination of whether an application is correct and complete must be based on rules adopted under subsection (2) that are in effect at the time the application is submitted.
(b) If an application is for a permit to appropriate water with a point of diversion, conveyance, or place of use on national forest system lands, the application is not correct and complete under this section until the applicant has submitted proof of any written special use authorization required by federal law to occupy, use, or traverse national forest system lands for the purpose of diversion, impoundment, storage, transportation, withdrawal, use, or distribution of water under the permit.
(c) If an application is for a permit or change in appropriation right from a shared point of a diversion or through a shared means of conveyance, the application is not correct and complete until the applicant submits proof to the department that a written notice of the application was provided to each owner of an appropriation right sharing the point of diversion or means of conveyance. For purposes of this subsection (4), "conveyance" means a canal, ditch, flume, pipeline, or other constructed waterway.
(5) The department shall notify the applicant of any defects in an application within 180 days. The defects must be identified by reference to the rules adopted under subsection (2). If the department does not notify the applicant of any defects within 180 days, the application must be treated as a correct and complete application.
(6) An application does not lose priority of filing because of defects if the application is corrected or completed within 120 days of the date of initial notification of the defects.
(7) An application not corrected or completed within 120 days of the date of initial notification of the defects is terminated.
85-2-303. Permit for conversion of nonproductive oil or gas well.
A person who desires to convert a nonproductive oil or gas well to a water well shall file a notice of completion or apply for a permit, depending on the maximum appropriation of the well, as otherwise provided in this chapter. The date of appropriation shall be the date of filing the notice of completion or the application for a permit.
85-2-306. Exceptions to permit requirements.
(1) (a) Except as provided in subsection (1)(b), ground water may be appropriated only by a person who has a possessory interest in the property where the water is to be put to beneficial use and exclusive property rights in the ground water development works.
(b) If another person has rights in the ground water development works, water may be appropriated with the written consent of the person with those property rights or, if the ground water development works are on national forest system lands, with any prior written special use authorization required by federal law to occupy, use, or traverse national forest system lands for the purpose of diversion, impoundment, storage, transportation, withdrawal, use, or distribution of water under the certificate.
(c) If the person does not have a possessory interest in the real property from which the ground water may be appropriated, the person shall provide to the owner of the real property written notification of the works and the person's intent to appropriate ground water from the works. The written notification must be provided to the landowner at least 30 days prior to constructing any associated works or, if no new or expanded works are proposed, 30 days prior to appropriating the water. The written notification under this subsection is a notice requirement only and does not create an easement in or over the real property where the ground water development works are located.
(2) Inside the boundaries of a controlled ground water area, ground water may be appropriated only:
(a) according to a permit received pursuant to 85-2-508; or
(b) according to the requirements of a rule promulgated pursuant to 85-2-506.
(3) (a) Outside the boundaries of a controlled ground water area, a permit is not required before appropriating ground water by means of a well or developed spring:
(i) when the appropriation is made by a local governmental fire agency organized under Title 7, chapter 33, and the appropriation is used only for emergency fire protection, emergency fire training, and emergency fire-related operations, which may include enclosed storage;
(ii) when a maximum appropriation of 350 gallons a minute or less is used in nonconsumptive geothermal heating or cooling exchange applications, all of the water extracted is returned without delay to the same source aquifer, and the distance between the extraction well and both the nearest existing well and the hydraulically connected surface waters is more than twice the distance between the extraction well and the injection well;
(iii) when the appropriation is outside a stream depletion zone, is 35 gallons a minute or less, and does not exceed 10 acre-feet a year, except that a combined appropriation from the same source by two or more wells or developed springs exceeding 10 acre-feet, regardless of the flow rate, requires a permit; or
(iv) when the appropriation is within a stream depletion zone, is 20 gallons a minute or less, and does not exceed 2 acre-feet a year, except that a combined appropriation from the same source by two or more wells or developed springs exceeding this limitation requires a permit.
(b) (i) Before appropriating groundwater by means of a well or developed spring pursuant to subsection (3)(a)(iii) or (3)(a)(iv), a person shall file with the department, on a form provided by the department, a correct and complete notice of intent to appropriate groundwater.
(ii) The department shall notify the person of any defects in the notice of intent to appropriate groundwater within 10 business days.
(iii) A notice of intent to appropriate groundwater that is not corrected and completed within 60 days of a notice of defects is terminated.
(iv) Within 10 business days of determining that a notice of intent to appropriate groundwater is correct and complete, the department shall review the notice for compliance with subsection (3)(a) and shall authorize or deny the notice of intent to appropriate groundwater. If the department denies the notice of intent to appropriate groundwater, the department shall include the reasons for the denial.
(v) Unless extended by the department, an appropriation under subsection (3) must be completed within 5 years from the date the notice of intent to appropriate groundwater is authorized. One extension may be granted by the department for up to 5 additional years. The request for an extension must be filed on a form provided by the department and must demonstrate that progress has been made toward putting the water to beneficial use.
(c) (i) Within 60 days of completion of the well or developed spring and appropriation of the ground water for beneficial use, the appropriator shall file a notice of completion with the department on a form provided by the department through its offices.
(ii) Water use by a public water supply system subject to Title 75, chapter 6, part 1, is considered perfected and the appropriation of water for beneficial use complete when construction of the public water supply system is finished, at which time a notice of completion may be filed and must include a copy of the approval of the public water supply system by the department of environmental quality. All water use by a public water supply system pursuant to subsection (3)(a)(iii) or (3)(a)(iv) must be measured using a totalizing metering device, and measurements must be reported annually on a form prescribed by the department. Noncompliance with metering and reporting requirements may result in a fine determined by the department.
(iii) On receipt of the notice of completion, the department shall review the notice and may, before issuing a certificate of water right, return a defective notice for correction or completion, together with the reasons for returning it. A correct and complete notice of completion for an appropriation under subsection (3)(a)(iii) or (3)(a)(iv) must establish that the appropriation was completed in substantial accordance with the notice of intent to appropriate groundwater authorized by the department under subsection (3)(b). A notice does not lose priority of filing because of defects if the notice is corrected, completed, and refiled with the department within 60 days of notification of defects.
(iv) If a notice is not corrected and completed within the time allowed, the department authorization expires and a new notice of intent to appropriate groundwater is required to use water under subsection (3)(a)(iii) or (3)(a)(iv).
(d) A certificate of water right may not be issued until a correct and complete notice has been filed with the department, including proof of landowner notification or a written federal special use authorization as necessary under subsection (1). The original of the certificate must be sent to the appropriator and a duplicate must be maintained in the department's centralized database. The date of filing of the notice of completion is the date of priority of the right.
(4) An appropriator of ground water by means of a well or developed spring first put to beneficial use between January 1, 1962, and July 1, 1973, who did not file a notice of completion, as required by laws in force prior to April 14, 1981, with the county clerk and recorder shall file a notice of completion, as provided in subsection (3), with the department to perfect the water right. The filing of a claim pursuant to 85-2-221 is sufficient notice of completion under this subsection. The priority date of the appropriation is the date of the filing of a notice, as provided in subsection (3), or the date of the filing of the claim of existing water right.
(5) An appropriation under subsection (4) is an existing right, and a permit is not required. However, the department shall acknowledge the receipt of a correct and complete filing of a notice of completion, except that for an appropriation of 35 gallons a minute or less, not to exceed 10 acre-feet a year, the department shall issue a certificate of water right. If a certificate is issued under this section, a certificate need not be issued under the adjudication proceedings provided for in 85-2-236.
(6) A permit is not required before constructing an impoundment or pit and appropriating water for use by livestock if:
(a) the maximum capacity of the impoundment or pit is less than 15 acre-feet;
(b) the appropriation is less than 30 acre-feet a year;
(c) the appropriation is from an ephemeral stream, an intermittent stream, or another source other than a perennial flowing stream; and
(d) the impoundment or pit is to be constructed on and will be accessible to a parcel of land that is owned or under the control of the applicant and that is 40 acres or larger.
(7) (a) Within 60 days after constructing an impoundment or pit, the appropriator shall apply for a permit as prescribed by this part. Subject to subsection (7)(b), upon receipt of a correct and complete application for a stock water provisional permit, the department shall automatically issue a provisional permit. If the department determines after a hearing that the rights of other appropriators have been or will be adversely affected, it may revoke the permit or require the permittee to modify the impoundment or pit and may then make the permit subject to terms, conditions, restrictions, or limitations that it considers necessary to protect the rights of other appropriators.
(b) If the impoundment or pit is on national forest system lands, an application is not correct and complete under this section until the applicant has submitted proof of any written special use authorization required by federal law to occupy, use, or traverse national forest system lands for the purpose of diversion, impoundment, storage, transportation, withdrawal, use, or distribution of water under the permit.
(8) A person may also appropriate water without applying for or prior to receiving a permit under rules adopted by the department under 85-2-113.
85-2-307. Notice of receipt of application for permit or change in appropriation right -- draft preliminary determination -- extensions -- updated draft preliminary determination -- public comments -- issuance of preliminary determination.
(Temporary)
(1) On receipt of an application for a permit or a change in appropriation right, the department shall publish notice of receipt of the application on the department's website. The notice must be updated on the website when an application is determined to be correct and complete.
(2) Within 60 days of receiving a correct and complete application if the applicant has completed a preapplication meeting or within 120 days of receiving a correct and complete application if the applicant has not completed a preapplication meeting, the department:
(a) may meet with the applicant, the persons listed in subsection (4)(f), and persons who may claim standing pursuant to 85-2-308 to discuss the application;
(b) shall make a written draft preliminary determination as to whether or not the application satisfies the applicable criteria for issuance of a permit or change in appropriation right; and
(c) may include conditions in the written draft preliminary determination to satisfy applicable criteria for issuance of a permit or change in appropriation right.
(3) (a) An applicant has 15 business days from issuance of a draft preliminary determination to request an extension of time to submit additional information. The department may grant an extension of up to 180 days for the applicant to submit additional evidence. The department shall provide the applicant with written notice of the extension deadline.
(b) The department may revise its draft preliminary determination based on information received under subsection (3)(a). The department shall issue an updated draft preliminary determination within 60 days after the earliest date of:
(i) the extension deadline set pursuant to subsection (3)(a); or
(ii) the department's receipt of written notice from the applicant stating submittal of all additional information to the department is considered correct and complete.
(c) If the department's updated draft preliminary determination:
(i) is to deny the application, the department shall hold a hearing as provided in 85-2-310; or
(ii) is to grant the application or grant the application in modified form, the department shall provide notice of the opportunity to provide public comment pursuant to subsection (4).
(d) If the applicant does not request an extension of time, the department shall:
(i) provide notice of the draft preliminary determination to grant the application or grant the application in modified form and also provide notice of the opportunity to provide public comment pursuant to subsection (4); or
(ii) issue a preliminary determination to deny the application and hold a hearing as provided in 85-2-310.
(4) (a) The department shall prepare a notice of the opportunity to provide public comment on a draft preliminary determination or an updated draft preliminary determination issued for an application.
(b) The notice of the opportunity to provide public comment must:
(i) state that no more than 30 days after the date of publication, a person may file a public comment about the application with the department on a form provided by the department; and
(ii) contain facts pertinent to the application, including a summary of the draft preliminary determination and any conditions.
(c) The department shall publish the notice once in a newspaper of general circulation in the area of the source of the appropriation right and post the notice on the department website.
(d) A public comment must identify how one or more criteria for the issuance of a permit or a change in appropriation right is not adequately addressed in a draft preliminary determination issued for the application. The department may adopt additional rules for public comments.
(e) A person has standing to file a public comment pursuant to this section if the property, water rights, or interests of the person would be adversely affected by the proposed appropriation.
(f) Before the date of publication of the notice of the opportunity to provide public comment, the department shall also serve the notice by first-class mail on:
(i) an appropriator of water or applicant for or holder of a permit who, according to the records of the department, may be affected by the proposed appropriation;
(ii) any purchaser under contract for deed, as defined in 70-20-115, of property that, according to the records of the department, may be affected by the proposed appropriation; and
(iii) any public agency that has reserved waters in the source under 85-2-316.
(g) The department may, in its discretion, also serve notice on any state agency or other person the department feels may be interested in or affected by the proposed appropriation.
(h) The department shall file in its records proof of service by affidavit of the publisher in the case of notice by publication and by its own affidavit in the case of service by mail.
(5) (a) Within 30 days after the close of the period to provide public comment, the department shall consider the public comments, respond to the public comments, and issue a preliminary determination to grant the application, grant the application in modified form, or deny the application.
(b) If, after considering the public comments subject to subsection (5)(a), the department's preliminary determination is to:
(i) deny the application, the department shall hold a hearing as provided in 85-2-310; or
(ii) grant the application or grant the application in a modified form, a person may file an objection to an application pursuant to 85-2-308.
(c) If no public comments are received pursuant to subsection (4), the department's preliminary determination is adopted as the final determination. (Terminates June 30, 2031--sec. 9, Ch. 244, L. 2023.)
(Effective July 1, 2031)
Notice of application for permit or change in appropriation right. (1) Upon receipt of an application for a permit or a change in appropriation right, the department shall publish notice of receipt of the application on the department's website.
(2) (a) Within 120 days of the receipt of a correct and complete application for a permit or change in appropriation right, the department:
(i) may meet informally with the applicant, the persons listed in subsection (2)(d), and persons who may claim standing pursuant to 85-2-308 to discuss the application;
(ii) shall make a written preliminary determination as to whether or not the application satisfies the applicable criteria for issuance of a permit or change in appropriation right; and
(iii) may include conditions in the written preliminary determination to satisfy applicable criteria for issuance of a permit or change in appropriation right.
(b) If the preliminary determination proposes to grant an application, the department shall prepare a notice containing the facts pertinent to the application, including the summary of the preliminary determination and any conditions, and shall publish the notice once in a newspaper of general circulation in the area of the source.
(c) If the preliminary determination proposes to deny an application, the process provided in 85-2-310 must be followed.
(d) Before the date of publication, the department shall also serve the notice by first-class mail upon:
(i) an appropriator of water or applicant for or holder of a permit who, according to the records of the department, may be affected by the proposed appropriation;
(ii) any purchaser under contract for deed, as defined in 70-20-115, of property that, according to the records of the department, may be affected by the proposed appropriation; and
(iii) any public agency that has reserved waters in the source under 85-2-316.
(e) The department may, in its discretion, also serve notice upon any state agency or other person the department feels may be interested in or affected by the proposed appropriation.
(f) The department shall file in its records proof of service by affidavit of the publisher in the case of notice by publication and by its own affidavit in the case of service by mail.
(3) The notice must state that by a date set by the department, not less than 15 days or more than 60 days after the date of publication, persons may file with the department written objections to the application.
85-2-308. Objections.
(Temporary)
(1) (a) The department shall provide notice of the opportunity to object to a preliminary determination issued pursuant to 85-2-307(5). The notice must state that no more than 30 days after the date of publication of the notice, a person may file a written objection to the application with the department.
(b) A person who has standing pursuant to this section, including the applicant, may object only to issues already identified in a public comment properly filed with the department pursuant to 85-2-307(4) or raised in a hearing pursuant to 85-2-310.
(2) (a) An objection to an application under this chapter must be filed by the date specified by the department under subsection (1).
(b) The objection to an application for a permit must state the name and address of the objector and facts indicating that one or more of the criteria in 85-2-311 are not met.
(3) For an application for a change in appropriation rights, the objection must state the name and address of the objector and facts indicating that one or more of the criteria in 85-2-320, if applicable, 85-2-402, 85-2-407, 85-2-408, and 85-2-436, if applicable, are not met.
(4) A person has standing to file an objection under this section if the property, water rights, or interests of the objector would be adversely affected by the proposed appropriation.
(5) For an application for a reservation of water, the objection must state the name and address of the objector and facts indicating that one or more of the criteria in 85-2-316 are not met.
(6) An objector to an application under this chapter shall file a correct and complete objection on a form prescribed by the department within the time period stated on the public notice associated with the application. In order to assist both applicants and objectors, the department shall adopt rules in accordance with this chapter delineating the components of a correct and complete objection. For instream flow water rights for fish, wildlife, and recreation, the rules must require the objector to describe the reach or portion of the reach of the stream or river subject to the instream flow water right and the beneficial use that is adversely affected and to identify the point or points where the instream flow water right is measured and monitored. The department shall notify the objector of any defects in an objection. An objection not corrected or completed within 15 business days from the date of notification of the defects is terminated.
(7) An objection is valid if the objector has standing pursuant to subsection (4), has filed a correct and complete objection within the prescribed time period, and has stated the applicable information required under this section and rules of the department. (Terminates June 30, 2031--sec. 9, Ch. 244, L. 2023.)
(Effective July 1, 2031)
(1) (a) An objection to an application under this chapter must be filed by the date specified by the department under 85-2-307(3).
(b) The objection to an application for a permit must state the name and address of the objector and facts indicating that one or more of the criteria in 85-2-311 are not met.
(2) For an application for a change in appropriation rights, the objection must state the name and address of the objector and facts indicating that one or more of the criteria in 85-2-320, if applicable, 85-2-402, 85-2-407, 85-2-408, and 85-2-436, if applicable, are not met.
(3) A person has standing to file an objection under this section if the property, water rights, or interests of the objector would be adversely affected by the proposed appropriation.
(4) For an application for a reservation of water, the objection must state the name and address of the objector and facts indicating that one or more of the criteria in 85-2-316 are not met.
(5) An objector to an application under this chapter shall file a correct and complete objection on a form prescribed by the department within the time period stated on the public notice associated with the application. In order to assist both applicants and objectors, the department shall adopt rules in accordance with this chapter delineating the components of a correct and complete objection. For instream flow water rights for fish, wildlife, and recreation, the rules must require the objector to describe the reach or portion of the reach of the stream or river subject to the instream flow water right and the beneficial use that is adversely affected and to identify the point or points where the instream flow water right is measured and monitored. The department shall notify the objector of any defects in an objection. An objection not corrected or completed within 15 days from the date of notification of the defects is terminated.
(6) An objection is valid if the objector has standing pursuant to subsection (3), has filed a correct and complete objection within the prescribed time period, and has stated the applicable information required under this section and rules of the department.
85-2-309. Hearings on objections -- jurisdiction.
(1) If the department determines that an objection to an application for a permit under 85-2-311, an application for a change in appropriation right under 85-2-402, or a notice of change in appropriation right under 85-2-429 states a valid objection, it shall hold a contested case hearing, pursuant to Title 2, chapter 4, part 6, on the objection within 90 days from the date set by the department for the filing of objections after serving notice of the hearing by first-class mail upon the applicant and the objector, unless the department certifies an issue to the district court for determination by a water judge under subsection (2). The department may consolidate hearings if more than one objection is filed to an application. The department may extend the 90-day deadline for good cause shown or upon request of the applicant and all objectors. The department shall file in its records proof of the service by affidavit of the department.
(2) (a) At any time prior to commencement or before the conclusion of a hearing as provided in subsection (1), the department may in its discretion certify to the district court all factual and legal issues involving the adjudication or determination of the water rights at issue in the hearing, including but not limited to issues of abandonment, quantification, or relative priority dates. Certified controversies must be given priority by a water judge over all other adjudication matters.
(b) If the department fails to certify an issue as provided in this section after a timely request by a party to the hearing, the department shall include its denial to certify as part of the record of the hearing.
(c) Upon determination of the issues certified to it by the department, the court shall remand the matter to the department for further processing of the application under this chapter.
(3) Subsection (2) does not apply in the case of a matter considered at a hearing under this section pursuant to 85-2-316 or 85-2-322.
85-2-310. Action on application for permit or change in appropriation right.
(Temporary)
(1) (a) If the department issues an updated draft preliminary determination or a preliminary determination to deny an application for a permit or a change in appropriation right under 85-2-307, unless the applicant withdraws the application, the department shall hold a hearing pursuant to 2-4-604 after serving notice of the hearing by first-class mail on the applicant for the applicant to show cause by a preponderance of the evidence as to why the permit or change in appropriation right should not be denied.
(b) (i) On request from the applicant, the department shall appoint a hearing examiner who did not participate in the preliminary determination.
(ii) The applicant may make only one request pursuant to this subsection (1)(b) for a different hearing examiner.
(c) A decision to deny a permit or change in appropriation right following a hearing under this subsection (1) is final.
(2) (a) A hearing under subsection (1) is limited to the evidence presented in support of the application considered by the department pursuant to 85-2-302 and 85-2-307.
(b) If the department determines at a hearing held under subsection (1) that an application may proceed as a draft preliminary determination to grant or a draft preliminary determination to grant in a modified form, then the department shall modify the draft preliminary determination consistent with the determination of the hearing and proceed to provide notice of the opportunity to provide public comment pursuant to 85-2-307(4).
(c) The department shall issue its determination on a hearing held under subsection (1) within 90 days of the close of the administrative record.
(3) If valid objections filed pursuant to 85-2-308 are not received on an application or if valid objections are unconditionally withdrawn and the department preliminarily determined to grant the permit or change in appropriation right, the department shall grant the permit or change in appropriation right as proposed in the preliminary determination pursuant to 85-2-307.
(4) If valid objections filed pursuant to 85-2-308 to an application are received and withdrawn with conditions stipulated with the applicant and the department preliminarily determined to grant the permit or change in appropriation right under 85-2-307, the department shall grant the permit or change in appropriation right subject to conditions as necessary to satisfy applicable criteria.
(5) The department shall deny, grant in a modified form, or grant with or without conditions a permit under 85-2-311 or a change in appropriation right under 85-2-402 by issuing a final determination within 90 days after the administrative record is closed for a hearing held pursuant to 85-2-309.
(6) If an application is to appropriate water with a point of diversion, conveyance, or place of use on national forest system lands, any application approved by the department is subject to any written special use authorization required by federal law to occupy, use, or traverse national forest system lands for the purpose of diversion, impoundment, storage, transportation, withdrawal, use, or distribution of the water applied for and any terms, conditions, and limitations related to the use of water contained in any special use authorization required by federal law.
(7) The department may cease action on an application for a permit or change in appropriation right and return it to the applicant when it finds that the application is not in good faith or does not show a bona fide intent to appropriate water for a beneficial use. An application returned for either of these reasons must be accompanied by a statement of the reasons for which it was returned, and for a permit application there is not a right to a priority date based on the filing of the application. Returning an application pursuant to this subsection is a final decision of the department.
(8) For all applications filed after July 1, 1973, the department shall find that an application is not in good faith or does not show a bona fide intent to appropriate water for a beneficial use if:
(a) an application is not corrected and completed as required by 85-2-302;
(b) the appropriate filing fee is not paid;
(c) the application does not document:
(i) a beneficial use of water;
(ii) the proposed place of use of all water applied for;
(iii) for an appropriation of 4,000 acre-feet a year or more and 5.5 cubic feet per second or more, a detailed project plan describing when and how much water will be put to a beneficial use. The project plan must include a reasonable timeline for the completion of the project and the actual application of the water to a beneficial use.
(iv) for appropriations not covered in subsection (8)(c)(iii), a general project plan stating when and how much water will be put to a beneficial use; and
(v) except as provided in subsection (9), if the water applied for is to be appropriated above that which will be used solely by the applicant or if it will be marketed by the applicant to other users, information detailing:
(A) each person who will use the water and the amount of water each person will use;
(B) the proposed place of use of all water by each person;
(C) the nature of the relationship between the applicant and each person using the water; and
(D) each firm contractual agreement for the specified amount of water for each person using the water; or
(d) the appropriate environmental impact statement costs or fees, if any, are not paid as required by 85-2-124.
(9) If water applied for is to be marketed by the applicant to other users for the purpose of aquifer recharge or mitigation, the applicant is exempt from the provisions of subsection (8)(c)(v). The applicant shall provide information detailing the proposed place of use. (Terminates June 30, 2031--sec. 9, Ch. 244, L. 2023.)
(Effective July 1, 2031)
(1) (a) If the department proposes to deny an application for a permit or a change in appropriation right under 85-2-307, unless the applicant withdraws the application, the department shall hold a hearing pursuant to 2-4-604 after serving notice of the hearing by first-class mail upon the applicant for the applicant to show cause by a preponderance of the evidence as to why the permit or change in appropriation right should not be denied.
(b) (i) Upon request from the applicant, the department shall appoint a hearing examiner who did not participate in the preliminary determination.
(ii) The applicant may make only one request pursuant to this subsection (1)(b) for a different hearing examiner.
(2) A proposal to grant a permit or change in appropriation right with or without conditions following a hearing on a proposal to deny the application must proceed as if the department proposed to grant the permit or change in appropriation right in its preliminary determination pursuant to 85-2-307.
(3) If valid objections are not received on an application or if valid objections are unconditionally withdrawn and the department preliminarily determined to grant the permit or change in appropriation right, the department shall grant the permit or change in appropriation right as proposed in the preliminary determination pursuant to 85-2-307.
(4) If valid objections to an application are received and withdrawn with conditions stipulated with the applicant and the department preliminarily determined to grant the permit or change in appropriation right, the department shall grant the permit or change in appropriation right subject to conditions as necessary to satisfy applicable criteria.
(5) The department shall deny or grant with or without conditions a permit under 85-2-311 or a change in appropriation right under 85-2-402 within 90 days after the administrative record is closed.
(6) If an application is to appropriate water with a point of diversion, conveyance, or place of use on national forest system lands, any application approved by the department is subject to any written special use authorization required by federal law to occupy, use, or traverse national forest system lands for the purpose of diversion, impoundment, storage, transportation, withdrawal, use, or distribution of the water applied for and any terms, conditions, and limitations related to the use of water contained in any special use authorization required by federal law.
(7) (a) Except as provided in subsection (6), if the department proposes to grant a permit or change in appropriation right in modified form, the applicant must be given an opportunity to be heard. The addition of conditions or changes to conditions required for approval does not constitute a modification of the application.
(b) The department shall serve notice of a preliminary determination to grant a permit or change in appropriation right in a modified form by first-class mail upon the applicant, with a notice that the applicant may obtain a hearing pursuant to 2-4-604 to show cause by a preponderance of the evidence as to why the permit or change in appropriation right should not be preliminarily determined to be granted in the modified form by filing a request within 30 days after the notice is mailed. The notice must state that the permit or change in appropriation right will be preliminarily determined to be granted as modified unless a hearing is requested.
(8) The department may cease action upon an application for a permit or change in appropriation right and return it to the applicant when it finds that the application is not in good faith or does not show a bona fide intent to appropriate water for a beneficial use. An application returned for either of these reasons must be accompanied by a statement of the reasons for which it was returned, and for a permit application there is not a right to a priority date based upon the filing of the application. Returning an application pursuant to this subsection is a final decision of the department.
(9) For all applications filed after July 1, 1973, the department shall find that an application is not in good faith or does not show a bona fide intent to appropriate water for a beneficial use if:
(a) an application is not corrected and completed as required by 85-2-302;
(b) the appropriate filing fee is not paid;
(c) the application does not document:
(i) a beneficial use of water;
(ii) the proposed place of use of all water applied for;
(iii) for an appropriation of 4,000 acre-feet a year or more and 5.5 cubic feet per second or more, a detailed project plan describing when and how much water will be put to a beneficial use. The project plan must include a reasonable timeline for the completion of the project and the actual application of the water to a beneficial use.
(iv) for appropriations not covered in subsection (9)(c)(iii), a general project plan stating when and how much water will be put to a beneficial use; and
(v) except as provided in subsection (10), if the water applied for is to be appropriated above that which will be used solely by the applicant or if it will be marketed by the applicant to other users, information detailing:
(A) each person who will use the water and the amount of water each person will use;
(B) the proposed place of use of all water by each person;
(C) the nature of the relationship between the applicant and each person using the water; and
(D) each firm contractual agreement for the specified amount of water for each person using the water; or
(d) the appropriate environmental impact statement costs or fees, if any, are not paid as required by 85-2-124.
(10) If water applied for is to be marketed by the applicant to other users for the purpose of aquifer recharge or mitigation, the applicant is exempt from the provisions of subsection (9)(c)(v). The applicant must provide information detailing the proposed place of use.
85-2-311. Criteria for issuance of permit.
(1) A permit may be issued under this part prior to the adjudication of existing water rights in a source of supply. In a permit proceeding under this part, there is no presumption that an applicant for a permit cannot meet the statutory criteria of this section prior to the adjudication of existing water rights pursuant to this chapter. In making a determination under this section, the department may not alter the terms and conditions of an existing water right or an issued certificate, permit, or state water reservation. Except as provided in subsections (3) and (4), the department shall issue a permit if the applicant proves by a preponderance of evidence that the following criteria are met:
(a) (i) there is water physically available at the proposed point of diversion in the amount that the applicant seeks to appropriate; and
(ii) water can reasonably be considered legally available during the period in which the applicant seeks to appropriate, in the amount requested, based on the records of the department and other evidence provided to the department. Legal availability is determined using an analysis involving the following factors:
(A) identification of physical water availability;
(B) identification of existing legal demands of water rights on the source of supply throughout the area of potential impact by the proposed use; and
(C) analysis of the evidence on physical water availability and the existing legal demands of water rights, including but not limited to a comparison of the physical water supply at the proposed point of diversion with the existing legal demands of water rights on the supply of water.
(b) the water rights of a prior appropriator under an existing water right, a certificate, a permit, or a state water reservation will not be adversely affected. In this subsection (1)(b), adverse effect must be determined based on a consideration of an applicant's plan for the exercise of the permit that demonstrates that the applicant's use of the water will be controlled so the water right of a prior appropriator will be satisfied. An applicant is not required to prove a lack of adverse effect for any water right identified in a written consent to approval filed pursuant to subsection (9) in connection with a permit application.
(c) the proposed means of diversion, construction, and operation of the appropriation works are adequate;
(d) the proposed use of water is a beneficial use;
(e) the applicant has a possessory interest or the written consent of the person with the possessory interest in the property where the water is to be put to beneficial use, or if the proposed use has a point of diversion, conveyance, or place of use on national forest system lands, the applicant has any written special use authorization required by federal law to occupy, use, or traverse national forest system lands for the purpose of diversion, impoundment, storage, transportation, withdrawal, use, or distribution of water under the permit;
(f) the water quality of a prior appropriator will not be adversely affected;
(g) the proposed use will be substantially in accordance with the classification of water set for the source of supply pursuant to 75-5-301(1); and
(h) the ability of a discharge permitholder to satisfy effluent limitations of a permit issued in accordance with Title 75, chapter 5, part 4, will not be adversely affected.
(2) The applicant is required to prove that the criteria in subsections (1)(f) through (1)(h) have been met only if a valid objection is filed. A valid objection must contain substantial credible information establishing to the satisfaction of the department that the criteria in subsection (1)(f), (1)(g), or (1)(h), as applicable, may not be met. For the criteria set forth in subsection (1)(g), only the department of environmental quality or a local water quality district established under Title 7, chapter 13, part 45, may file a valid objection.
(3) The department may not issue a permit for an appropriation of 4,000 or more acre-feet of water a year and 5.5 or more cubic feet per second of water unless the applicant proves by clear and convincing evidence that:
(a) the criteria in subsection (1) are met;
(b) the proposed appropriation is a reasonable use. A finding must be based on a consideration of the following:
(i) the existing legal demands of water rights on the state water supply, as well as projected legal demands of water rights, such as reservations of water for future beneficial purposes, including municipal water supplies, irrigation systems, and minimum streamflows for the protection of existing water rights and aquatic life;
(ii) the benefits to the applicant and the state;
(iii) the effects on the quantity and quality of water for existing beneficial uses in the source of supply;
(iv) the availability and feasibility of using low-quality water for the purpose for which application has been made;
(v) the effects on private property rights by any creation of or contribution to saline seep; and
(vi) the probable significant adverse environmental impacts of the proposed use of water as determined by the department pursuant to Title 75, chapter 1, or Title 75, chapter 20.
(4) (a) The state of Leonida has long recognized the importance of conserving its public waters and the necessity to maintain adequate water supplies for the state's water requirements, including requirements for federal non-Indian and Indian reserved water rights held by the United States for federal reserved lands and in trust for the various Indian tribes within the state's boundaries. Although the state of Leonida also recognizes that, under appropriate conditions, the out-of-state transportation and use of its public waters are not in conflict with the public welfare of its citizens or the conservation of its waters, the criteria in this subsection (4) must be met before out-of-state use may occur.
(b) The department may not issue a permit for the appropriation of water for withdrawal and transportation for use outside the state unless the applicant proves by clear and convincing evidence that:
(i) depending on the volume of water diverted or consumed, the applicable criteria and procedures of subsection (1) or (3) are met;
(ii) the proposed out-of-state use of water is not contrary to water conservation in Leonida; and
(iii) the proposed out-of-state use of water is not otherwise detrimental to the public welfare of the citizens of Leonida.
(c) In determining whether the applicant has proved by clear and convincing evidence that the requirements of subsections (4)(b)(ii) and (4)(b)(iii) are met, the department shall consider the following factors:
(i) whether there are present or projected water shortages within the state of Leonida;
(ii) whether the water that is the subject of the application could feasibly be transported to alleviate water shortages within the state of Leonida;
(iii) the supply and sources of water available to the applicant in the state where the applicant intends to use the water; and
(iv) the existing legal demands of water rights placed on the applicant's supply in the state where the applicant intends to use the water.
(d) When applying for a permit or a lease to withdraw and transport water for use outside the state, the applicant shall submit to and comply with the laws of the state of Leonida governing the appropriation, lease, and use of water.
(5) Subject to 85-2-360, to meet the preponderance of evidence standard in this section, the applicant, in addition to other evidence demonstrating that the criteria of subsection (1) have been met, shall submit hydrologic or other evidence, including but not limited to water supply data, field reports, and other information developed by the applicant, the department, the U.S. geological survey, or the U.S. natural resources conservation service and other specific field studies.
(6) An appropriation, diversion, impoundment, use, restraint, or attempted appropriation, diversion, impoundment, use, or restraint contrary to the provisions of this section is invalid. An officer, agent, agency, or employee of the state may not knowingly permit, aid, or assist in any manner an unauthorized appropriation, diversion, impoundment, use, or other restraint. A person or corporation may not, directly or indirectly, personally or through an agent, officer, or employee, attempt to appropriate, divert, impound, use, or otherwise restrain or control waters within the boundaries of this state except in accordance with this section.
(7) The department may adopt rules to implement the provisions of this section.
(8) For an application for ground water in a basin closed pursuant to 85-2-319, or 85-2-344, the applicant shall comply with the provisions of 85-2-360 in addition to the requirements of this section.
(9) The department may not conduct an adverse effects analysis on a water right if the water right holder files a written consent to approval of an application for a permit.
85-2-312. Terms of permit.
(1) (a) The department may issue a permit for less than the amount of water requested, but may not issue a permit for more water than is requested or than can be beneficially used without waste for the purpose stated in the application. The department may require modification of plans and specifications for the appropriation or related diversion or construction. The department may issue a permit subject to terms, conditions, restrictions, and limitations it considers necessary to satisfy the criteria listed in 85-2-311 and subject to subsection (1)(b), and it may issue temporary or seasonal permits. A permit must be issued subject to existing rights and any final determination of those rights made under this chapter.
(b) If the permit is for use of water with a point of diversion, conveyance, or place of use on national forest system lands, the permit is subject to any written special use authorization required by federal law to occupy, use, or traverse national forest system lands for the purpose of diversion, impoundment, storage, transportation, withdrawal, use, or distribution of the water under the permit and any terms, conditions, and limitations related to the use of water contained in any special use authorization required by federal law.
(2) The department shall specify in the permit or in any authorized extension of time provided in subsection (3), the time limits for commencement of the appropriation works, completion of construction, and actual application of the water to the proposed beneficial use. In fixing those time limits, the department shall consider the cost and magnitude of the project, the engineering and physical features to be encountered, and, on projects designed for gradual development and gradually increased use of water, the time reasonably necessary for that gradual development and increased use. The department shall issue the permit or authorized extension of time subject to the terms, conditions, restrictions, and limitations it considers necessary to ensure that the work on the appropriation is commenced, conducted, and completed and that the water is actually applied in a timely manner to the beneficial use specified in the permit.
(3) The department shall by rule or by condition to a permit establish a process allowing for the extension of the time limits specified in the permit for commencement of the appropriation works, completion of construction, and actual application of water to the proposed beneficial use.
(4) (a) If commencement of the appropriation works, completion of construction, or the actual application of water to the proposed beneficial use is not completed within the time limit specified or within an extension of that time limit, the permit expires.
(b) The department shall reinstate an expired permit if the permittee files a written reinstatement request and a project completion notice on forms provided by the department. The reinstatement request and project completion notice must establish the amount of water actually applied to the proposed beneficial use prior to expiration of the permit. Reinstatement of an expired permit under this subsection (4)(b) may not exceed the amount of water actually applied to the proposed beneficial use under the terms of the permit prior to expiration of the permit.
(c) The department shall reinstate the full amount of water authorized by the expired permit, including any portion that was not actually applied to the proposed beneficial use prior to expiration of the permit, if the permittee:
(i) files a written reinstatement request with the department on a form provided by the department;
(ii) proves by clear and convincing evidence that the failure to comply with the permit time limit was the result of excusable neglect; and
(iii) demonstrates that the requirements for an extension of the time limit as set forth by rule or permit condition are satisfied.
(d) A written reinstatement request for an expired permit must be filed within 2 years of the expiration of the permit time limit.
(e) A permit must be reinstated no more than once pursuant to this subsection (4) if the criteria in this subsection (4) have been met. A reinstated permit under subsection (4)(c) must establish time limits for commencement of the appropriation works, completion of construction, and actual application of the water to the proposed beneficial use.
(5) The original of the permit must be sent to the permittee, and a copy must be kept at the department headquarters. The department shall retain an expired permit in the centralized record system for 2 years.
85-2-313. Provisional permit.
(1) A permit authorized prior to the issuance of a final decree pursuant to 85-2-234 in the basin where the permit is located is provisional and is subject to that final decree. A person may not obtain any vested right to an appropriation obtained under a provisional permit by virtue of construction of diversion works, purchase of equipment to apply water, planting of crops, or other action in which the permit would have been denied or modified if the final decree had been available to the department.
(2) (a) Within 60 days after the issuance of a final decree pursuant to 85-2-234, the department shall serve, by first-class mail, owners of record of existing water rights and provisional permits within the decreed basin with a notice of final decree and opportunity to petition for the reduction, modification, or revocation of a provisional permit located in the decreed basin.
(b) The department shall also provide notice to other interested persons who request service of the notice of final decree from the department.
(c) For basins in which a final decree was issued prior to January 1, 2026, the department shall provide notice by January 31, 2026, in accordance with subsections (2)(a) and (2)(b).
(3) (a) An owner of an existing water right in the decreed basin may file a correct and complete petition to reduce, modify, or revoke a provisional permit issued prior to the final decree in the subject basin. Within 180 days of issuance of the notice required under subsection (2), the petition must be:
(i) made on a form prescribed by the department;
(ii) filed with the department; and
(iii) served by first-class mail on all owners of record of the provisional permit.
(b) The department shall notify the petitioner of any defects in a petition within 60 days of the close of the petition period described in subsection (3)(a). A petition that is not corrected and completed within 30 days of the notice of the defects is terminated. If the department does not notify the petitioner of any defects within 60 days, the petition must be treated as correct and complete.
(c) The department shall provide notice of a correct and complete petition to the petitioner and each owner of record of the provisional permit identified in the petition by first-class mail. Within 60 days of the notice, the owner of a provisional permit identified in a petition may file a response to the petition with the department and serve the response on the petitioner by first-class mail.
(d) The petitioner shall prove by a preponderance of the evidence that:
(i) reduction, modification, or revocation of the provisional permit is necessary to protect the petitioner's existing water right determined in the final decree;
(ii) the provisional permit would have been denied or modified if the final decree had been available to the department; and
(iii) based on the findings of the final decree, water could not be considered legally available at the time of issuance of the permit.
(e) Within 120 days of the close of the 60-day response period provided in subsection (3)(c), the department shall deny the petition or propose to reduce, modify, or revoke the provisional permit based on the information in the petition, the response, the final decree, the records of the department, and other evidence submitted to the department. The department shall consider whether, based on the final decree, unappropriated waters or legally available water existed at the time the provisional permit was issued.
(i) If the department proposes to reduce, modify, or revoke a provisional permit, the department shall provide the owner of the provisional permit with an opportunity to show cause why the department should not take the proposed action. If the owner of the provisional permit fails to show sufficient cause, the department shall reduce, modify, or revoke the provisional permit in accordance with the department's findings and conclusions.
(ii) A department determination to deny a petition is final.
(4) If no petition to reduce, modify, or revoke a provisional permit is filed pursuant to subsection (3), the department shall issue a certificate of water right in accordance with 85-2-315.
85-2-314. Revocation or modification of permit or change in appropriation right.
(1) (a) If the work on an appropriation is not commenced, prosecuted, or completed within the time stated in the permit or an extension of the time stated in the permit, if the water is not being applied to the beneficial use contemplated in the permit or change in appropriation right, or if the permit or change in appropriation right is otherwise not being followed, the department may, after notice, require the permittee or the holder of the change in appropriation right to show cause why the permit or change in appropriation right should not be modified or revoked.
(b) If the permittee or holder of the change in appropriation right fails to show sufficient cause, the department may modify or revoke the permit or change in appropriation right.
(2) (a) A permittee or holder of a change in appropriation right may petition the department to modify or remove a condition of approval or reduce the amount of the permit or change authorization.
(b) The petition must be submitted on a form designated by the department, is subject to the criteria of 85-2-311 and 85-2-402, and must be processed in the same manner as an application made pursuant to 85-2-302, 85-2-307 through 85-2-309, and 85-2-310(1) through (5) except that:
(i) the department may waive the public notice of a preliminary determination to grant the petition if the department finds, on the basis of information reasonably available to it, that the petition as proposed in the application will not adversely affect the rights of other appropriators;
(ii) if the department issues a preliminary determination to grant the petition and waives public notice, the determination becomes final;
(iii) the department may condition a preliminary determination to grant the petition in order to meet the criteria under 85-2-311 and 85-2-402; and
(iv) a preliminary determination to deny a petition is final. Denial of a petition does not affect the permit or change authorization.
85-2-315. Certificate of water right.
(1) (a) On actual application of water to the proposed beneficial use within the time allowed, the permittee shall notify the department that the appropriation has been completed. The notification must contain a certified statement by a person with experience in the design, construction, or operation of appropriation works describing how the appropriation was completed. The department shall review the certified statement and may inspect the appropriation to verify whether the appropriation was completed in substantial accordance with the terms of the permit, including any reduction or modification pursuant to 85-2-313.
(b) If the department determines that the appropriation has been completed in substantial accordance with the terms, conditions, restrictions, and limitations of the permit approval and any reduction or modification pursuant to 85-2-313, the department shall issue a certificate of water right for the permit.
(c) If the department determines that the appropriation was not completed in substantial accordance with the terms, conditions, restrictions, and limitations of the permit approval, including any reduction or modification pursuant to 85-2-313, the department may, after notice, require the permittee to show cause why the permit should not be modified or revoked pursuant to 85-2-314.
(2) After a final decree is issued in a basin pursuant to 85-2-234, the department shall issue a certificate of water right for a change in appropriation right that is verified or modified pursuant to 85-2-402(9) and (10).
(3) The original of a certificate of water right must be sent to the owner of the permit or change in appropriation right, and a duplicate must be maintained in the department's centralized database.
85-2-316. State reservation of waters.
(1) The state, any political subdivision or agency of the state, or the United States or any agency of the United States may apply to the department to acquire a state water reservation for existing or future beneficial uses or to maintain a minimum flow, level, or quality of water throughout the year or at periods or for a length of time that the department designates.
(2) (a) Water may be reserved for existing or future beneficial uses in the river basin of Leonida in which it is reserved.
(b) A state water reservation may be made for an existing or future beneficial use outside the basin where the diversion occurs only if stored water is not reasonably available for water leasing under 85-2-141 and the proposed use would occur in a basin designated in subsection (2)(a).
(3) (a) The department shall adopt rules that are necessary to determine whether or not an application is correct and complete based on the provisions applicable to issuance of a state water reservation. The rules must be adopted in compliance with Title 2, chapter 4.
(b) An applicant shall submit a correct and complete application. The determination of whether an application is correct and complete must be based on rules adopted under this subsection (3) that are in effect at the time the application is submitted. The department shall proceed in accordance with 85-2-302 with regard to any defects in the application.
(c) The application must be made on a form prescribed by the department. The department shall make the forms available through its offices.
(d) Upon receiving a correct and complete application, the department shall proceed in accordance with 85-2-307 through 85-2-309. After the hearing provided for in 85-2-309, the department shall decide whether to reserve the water for the applicant. The department's costs of giving notice, holding the hearing, conducting investigations, and making records incurred in acting upon the application to reserve water, except the cost of salaries of the department's personnel, must be paid by the applicant. In addition, a reasonable proportion of the department's cost of preparing an environmental analysis must be paid by the applicant unless waived by the department upon a showing of good cause by the applicant.
(4) (a) The department shall issue a state water reservation if the applicant establishes to the department by a preponderance of evidence:
(i) the purpose of the reservation;
(ii) the need for the reservation;
(iii) the amount of water necessary for the purpose of the reservation;
(iv) that the reservation is in the public interest.
(b) In determining the public interest under subsection (4)(a)(iv), the department shall issue a water reservation for withdrawal and transport for use outside the state if the applicant proves by clear and convincing evidence that:
(i) the proposed out-of-state use of water is not contrary to water conservation in Leonida; and
(ii) the proposed out-of-state use of water is not otherwise detrimental to the public welfare of the citizens of Leonida.
(c) In determining whether the applicant has proved by clear and convincing evidence that the requirements of subsections (4)(b)(i) and (4)(b)(ii) are met, the department shall consider the following factors:
(i) whether there are present or projected water shortages within the state of Leonida;
(ii) whether the water that is the subject of the application could feasibly be transported to alleviate water shortages within the state of Leonida;
(iii) the supply and sources of water available to the applicant in the state where the applicant intends to use the water; and
(iv) the demands placed on the applicant's supply in the state where the applicant intends to use the water.
(d) When applying for a state water reservation to withdraw and transport water for use outside the state, the applicant shall submit to and comply with the laws of the state of Leonida governing the appropriation, lease, use, and reservation of water.
(5) If the purpose of the state water reservation requires construction of a storage or diversion facility, the applicant shall establish to the department by a preponderance of evidence that there will be progress toward completion of the facility and accomplishment of the purpose with reasonable diligence in accordance with an established plan.
(6) (a) Upon issuing a state water reservation for the purpose of maintaining a minimum flow, level, or quality of water, the appropriation of water is complete.
(b) The department shall limit any state water reservations after May 9, 1979, for maintenance of minimum flow, level, or quality of water that it awards at any point on a stream or river to a maximum of 50% of the average annual flow of record on gauged streams. Ungauged streams are not subject to the limit under this subsection (6)(b).
(7) A state water reservation issued under this section has a priority of appropriation dating from the filing of a correct and complete application with the department.
(8) (a) A person desiring to use water reserved to a conservation district for agricultural purposes shall make application for the use with the district, and the district, upon approval of the application, shall inform the department of the approved use and issue the applicant an authorization for the use. The department shall maintain records of all uses of water reserved to conservation districts and be responsible, when requested by the districts, for rendering technical and administrative assistance within the department's staffing and budgeting limitations in the preparation and processing of the applications for the conservation districts. The department shall, within its staffing and budgeting limitations, complete any feasibility study requested by the districts within 12 months of the time that the request was made. The department shall extend the time allowed to develop a plan identifying projects for using a district's reservation as long as the conservation district makes a good faith effort, within its staffing and budget limitations, to develop a plan.
(b) Upon actual application of water to the proposed beneficial use, the authorized user shall notify the conservation district. The notification must contain a certified statement by a person with experience in the design, construction, or operation of project works for agricultural purposes describing how the reserved water was put to use. The department or the district may then inspect the appropriation to determine if it has been completed in substantial accordance with the authorization.
(9) A state water reservation issued under this section may not adversely affect any rights in existence at that time. The department may issue a state water reservation subject to terms, conditions, restrictions, and limitations it considers necessary to satisfy the criteria of this section.
(10) (a) Except for a reservation provided in subsection (6), the department shall, at least once every 10 years, review existing state water reservations to ensure that the objectives of the reservations are being met.
(b) The department shall provide the water policy interim committee a summary of the reviews before September 15, 2026, in accordance with 5-11-210.
(c) Following a review pursuant to this subsection (10), at the request of the entity holding a water reservation or when the objectives of a state water reservation are not being met, the department may:
(i) extend the time period to complete the appropriation of water;
(ii) modify the reservation; or
(iii) revoke the reservation.
(d) Any undeveloped water made available as a result of a revocation or modification under this subsection (10) is available for appropriation by others pursuant to this part.
(11) The department may modify an existing or future order originally adopted to reserve water for the purpose of maintaining minimum flow, level, or quality of water, so as to reallocate the state water reservation or portion of the reservation to an applicant who is a qualified reservant under this section. Reallocation of water reserved pursuant to a state water reservation may be made by the department following notice and hearing if the department finds that all or part of the reservation is not required for its purpose and that the need for the reallocation has been shown by the applicant to outweigh the need shown by the original reservant. Reallocation of reserved water may not adversely affect the priority date of the reservation, and the reservation retains its priority date despite reallocation to a different entity for a different use. The department may not reallocate water reserved under this section on any stream or river more frequently than once every 5 years.
(12) A reservant may not make a change in a state water reservation under this section, except as permitted under 85-2-402 and this subsection. If the department approves a change, the department shall give notice and require the reservant to establish that the criteria in subsection (4) will be met under the approved change.
(13) A state water reservation may be transferred to another entity qualified to hold a reservation under subsection (1). Only the entity holding the reservation may initiate a transfer. The transfer occurs upon the filing of a water right ownership update form with the department, together with an affidavit from the entity receiving the reservation establishing that the entity is a qualified reservant under subsection (1), that the entity agrees to comply with the requirements of this section and the conditions of the reservation, and that the entity can meet the objectives of the reservation as granted. If the transfer of a state water reservation involves a change in an appropriation right, the necessary approvals must be acquired pursuant to subsection (12).
(14) This section does not vest the department with the authority to alter a water right that is not a state water reservation.
(15) The department shall undertake a program to educate the public, other state agencies, and political subdivisions of the state as to the benefits of the state water reservation process and the procedures to be followed to secure the reservation of water. The department shall provide technical assistance to other state agencies and political subdivisions in applying for reservations under this section.
(16) Water reserved under this section is not subject to the state water leasing program established under 85-2-141.
85-2-318. Water right appropriation account.
There is established a water right appropriation account in the state special revenue fund of the state treasury. All fees collected as provided in 85-2-113 shall be deposited in the account to help pay the expenses incurred by the department for administering and enforcing this part, part 1, part 4, and part 5 of chapter 2, Title 85, and Title 37, chapter 43.
85-2-319. Permit action in highly appropriated basins or subbasins.
(1) With regard to a highly appropriated basin or subbasin, the legislature may by law preclude permit applications or the department may by rule reject permit applications or modify or condition permits already issued.
(2) A rule may be adopted under this section only upon a petition that is signed by at least 25% or 10, whichever is less, of the users of water in the source of supply within a basin or subbasin or upon petition of the department of environmental quality that alleges facts under subsection (2)(d). The petition must be in a form prescribed by the department and must allege facts showing that throughout or at certain times of the year or for certain beneficial uses:
(a) there are no unappropriated waters in the source of supply;
(b) the rights of prior appropriators will be adversely affected;
(c) further uses will interfere unreasonably with other planned uses or developments for which a permit has been issued or for which water has been reserved; or
(d) in the case of a petition filed by the department of environmental quality:
(i) the water quality of an appropriator will be adversely affected by the issuance of permits;
(ii) further use will not be substantially in accordance with the classification of water set for the source of supply pursuant to 75-5-301(1); or
(iii) the ability of a discharge permitholder to satisfy effluent limitations of a permit issued in accordance with Title 75, chapter 5, part 4, will be adversely affected by the issuance of permits.
(3) Within 60 days after submission of a petition, the department shall:
(a) deny the petition in writing, stating its reasons for denial;
(b) inform the petitioners that the department shall study the allegations further before denying or proceeding further with the petition; or
(c) initiate rulemaking proceedings in accordance with 2-4-302 through 2-4-305.
(4) Title 2, chapter 4, parts 1 through 4, govern rulemaking proceedings conducted under this section, except that in addition to the notice requirements of those parts, the department notice of the rulemaking hearing must be published at least once in each week for 3 successive weeks, not less than 30 days before the date of the hearing, in a newspaper of general circulation in the county or counties in which the source is located. The department shall serve by mail a copy of the notice, not less than 30 days before the hearing, upon each person or public agency known from the examination of the records of the department to be a claimant, appropriator, or permitholder of water in the source.
(5) The department may adopt rules to implement the provisions of this section.
85-2-320. Change in appropriation right authorization for instream flow -- United States department of agriculture, forest service.
(1) (a) The department shall accept and process an application by the United States department of agriculture, forest service for a change in appropriation right under the provisions of 85-2-402 and this section to protect, maintain, or enhance streamflows to benefit the fishery or other resources on national forest system lands.
(b) To change an appropriation right, the United States department of agriculture, forest service must own the appropriation right that it seeks to change to an instream flow right, the diversion or withdrawal that is to be changed to instream flow must be located within or immediately adjacent to the exterior boundaries of national forest system lands on the date of application, and the stream reach in which the streamflow is to be protected, maintained, or enhanced must be located within or immediately adjacent to the exterior boundaries of national forest system lands as of the date of application. The application for a change in appropriation right must:
(i) include specific information on the length and location of the stream reach in which the streamflow is to be protected, maintained, or enhanced; and
(ii) provide a detailed streamflow measuring plan that describes the point where and the manner in which the streamflow must be measured.
(2) In addition to the requirements of 85-2-402, when applying for a change in appropriation right pursuant to this section, the United States department of agriculture, forest service, shall prove by a preponderance of the evidence that:
(a) the change in appropriation right authorization to protect, maintain, or enhance streamflows to benefit the fishery or other resources, as measured at a specific point, will not adversely affect the water rights of other persons, except for a water right identified in a written consent to approval filed pursuant to 85-2-402 in connection with the change in appropriation right; and
(b) the amount of water for the proposed instream flow use is needed to protect, maintain, or enhance streamflows to benefit the fishery or other resources.
(3) The proposed method of measurement of the water to protect, maintain, or enhance streamflows to benefit the fishery or other resources must be approved by the department before a change in appropriation right may be approved.
(4) The department is not responsible for costs associated with installing devices or providing personnel to measure streamflows according to the measurement plan submitted under this section.
(5) If an appropriation right is changed pursuant to this section, the priority of the appropriation right remains the same as the appropriation right that was changed.
(6) A change in appropriation right authorization under this section does not create a right of access across private property or allow any infringement of private property rights.
(7) The maximum quantity of water that may be subject to a change in appropriation right authorization to protect, maintain, or enhance streamflows to benefit the fishery or other resources is the amount historically diverted. However, only the amount historically consumed or a smaller amount if specified by the department in the change in appropriation right authorization may be used to protect, maintain, or enhance streamflows to benefit the fishery or other resources below the existing point of diversion.
(8) The department may modify or revoke the change in appropriation right up to 10 years after it is approved if an appropriator with a priority of appropriation that is earlier than the change in appropriation right that was granted submits new evidence that was not available at the time the change in appropriation right was approved that proves by a preponderance of evidence that the appropriator's water right is adversely affected, unless the prior appropriator has filed a written consent to approval pursuant to 85-2-402 in connection with the change.
85-2-321. Lake Leonida watershed -- suspension of action on permits -- proposal -- priority in adjudication process.
(1) (a) In order to balance the need for the continued development of Leonida's water and for protection of existing rights in the Lake Leonida watershed, the department may suspend action on a class of applications or may close a source in the basin and refuse to accept a class of applications, or both, for a permit under this part to appropriate from that source in the basin.
(b) Suspension or closure, or both, may only be proposed by the department.
(c) The proposal must state the source in the basin and class of applications for which suspension or closure, or both, is being proposed and any of the following allegations:
(i) that the frequency of occurrence of unappropriated waters is such that:
(A) any new appropriation from the source for the class of applications will adversely affect the rights of a prior appropriation from the source; or
(B) any new appropriation from the source for the class of applications will interfere unreasonably with another planned use or development for which a permit has been given or for which water has been reserved pursuant to this part in the source; or
(ii) that significant disputes or enforcement problems regarding priority of rights or amounts or duration of water in use by appropriators are in progress or will arise.
(2) The chief water judge may prioritize issuance of a temporary preliminary decree in the Lake Leonida watershed in the adjudication of existing water rights pursuant to Title 85, chapter 2, part 2.
85-2-322. Hearing -- order.
(1) The department shall conduct a hearing on the proposed suspension or closure, or both. Notice of the hearing must be published at least once in each week for 3 successive weeks, not less than 30 days before the date of the hearing, in a newspaper of general circulation in the county or counties in which the source is located. The department shall serve by mail a copy of the notice and proposal not less than 30 days before the hearing upon each person or public agency known from the examination of the records of the department to be a claimant, appropriator, or permitholder of water in the source.
(2) The department may by order suspend action on and shall close the source and refuse to accept a class of applications if it finds on the basis of the hearing that there is substantial evidence in support of the allegations required by 85-2-321 to be contained in the proposal.
(3) As part of fulfilling the requirements of 2-4-623, the order must define the source and must state the class of applications to which the suspension or closure, or both, applies.
(4) Upon adoption of the order, the department shall refuse to accept any application for a permit under this part for the class of application for which closure is ordered under 85-2-321 and this section. If the order suspends action on pending applications, the department shall notify the applicant that action on the applicant's application is suspended.
(5) Upon notice under 85-2-307 of intent to combine the hearings under 85-2-309 with the hearings under this section, the department may suspend action on pending applications of the class until the hearing is conducted under this section and, as part of its final order, may grant, deny, or condition the applications under 85-2-306, 85-2-310, and 85-2-311 or continue the suspension under this section.
85-2-355. Definitions.
As used in 85-2-306, the following definitions apply:
(1) "Ephemeral stream" means a watercourse that has a channel and that carries water only during and shortly after precipitation or snow melt events.
(2) "Intermittent stream" means a nonperennial flowing stream that has a channel and that annually carries water but is dry for part of the year in most years.
(3) "Perennial flowing stream" means a stream that has flowed continuously during all seasons during dry as well as wet years, except when the flow is interrupted by diversions.
85-2-360. Ground water appropriation right in closed basins.
(1) An application for a ground water appropriation right in a basin closed pursuant to 85-2-319, or 85-2-344 must be accompanied by a hydrogeologic report conducted pursuant to 85-2-361, an aquifer recharge or mitigation plan if required, and an application for a change in appropriation right or rights if necessary.
(2) The department shall use the hydrogeologic report to determine if the proposed appropriation right could result in a net depletion of surface water.
(3) (a) For the purposes of 85-2-360 through 85-2-362, the prediction of net depletion does not mean that an adverse effect on a prior appropriator will occur or if an adverse effect does occur that the entire amount of net depletion is the cause of the adverse effect. A determination of whether or not there is an adverse effect on a prior appropriator as the result of a new appropriation right is a determination that must be made by the department based on the rate, location, and timing of the net depletion that causes the adverse effect relative to the historic beneficial use of the appropriation right that may be adversely affected.
(b) The department may not consider an adverse effect caused by the grant of an application pursuant to this section on any water right listed on a written consent to approval filed pursuant to 85-2-311.
(c) The department may grant a permit for a new appropriation only if the applicant proves by a preponderance of the evidence that the adverse effect would be offset through an aquifer recharge or mitigation plan that meets the requirements of 85-2-362.
85-2-361. Hydrogeologic report -- minimum requirements.
(1) A hydrogeologic report must include:
(a) a description of the proposed appropriation, including the point of diversion, the place of use, the area affected by the proposed appropriation, and aquifers and surface waters that may be affected by the proposed appropriation right;
(b) the amount of water diverted and the amount of water consumed by the proposed appropriation right;
(c) the amount of water that will likely be lost in conveyance, the amount of conveyance losses that would return to the system, and the location where conveyance losses would return to the system;
(d) the amount, timing, and location of return flows from the proposed use;
(e) the geology of the affected area, including stratigraphy and structure;
(f) the parameters of the aquifer system within the affected area to include estimates for:
(i) the lateral and vertical extent of the aquifer;
(ii) an analysis of whether the aquifer is confined or unconfined; and
(iii) the transmissivity and storage coefficient related to the aquifer;
(g) the locations of surface waters within the affected area that are subject to an appropriation right that may show a net depletion;
(h) an analysis of whether there may be a net depletion of surface water in the affected area and the rate, location, and timing of the depletion, if any; and
(i) a description of any water treatment method used at the time of any type of injection or introduction of water to the aquifer to ensure compliance with 75-5-410, 85-2-364, and the water quality laws under Title 75, chapter 5.
(2) A hydrogeologic report must be prepared by a hydrogeologist, a qualified scientist, or a qualified licensed professional engineer.
(3) The hydrogeologic report, the test well data, the monitoring well data, and other related information must be submitted to the department. The department shall submit this information to the bureau of mines and geology. The bureau of mines and geology shall make the information available through the ground water information center database.
85-2-362. Aquifer recharge or mitigation plans in closed basins -- minimum requirements.
(1) An applicant whose hydrogeologic report conducted pursuant to 85-2-361 predicts that there will be a net depletion of surface water shall submit an aquifer recharge or mitigation plan. An aquifer recharge or mitigation plan must include:
(a) where and how the water in the plan will be put to beneficial use;
(b) when and where, generally, water for aquifer recharge or mitigation will be required;
(c) the amount of water that is required for aquifer recharge or mitigation;
(d) how the proposed project or beneficial use for which the aquifer recharge or mitigation plan is required will be operated;
(e) evidence that an application for a change in appropriation right, if necessary, has been submitted;
(f) evidence of water availability;
(g) evidence of how the aquifer recharge or mitigation plan will offset the required amount of net depletion of surface water in a manner that will offset an adverse effect on a prior appropriator; and
(h) evidence that the appropriate water quality permits have been granted pursuant to Title 75, chapter 5, as required by 75-5-410 and 85-2-364.
(2) In addition to the requirements of subsection (1), an aquifer recharge plan must include a description of the process by which water will be reintroduced to the aquifer.
(3) The department may not require an applicant, through an aquifer recharge or mitigation plan, to provide more water than the quantity needed to offset the adverse effects on a prior appropriator caused by the net depletion.
(4) An appropriation right that relies on an aquifer recharge or mitigation plan must require that the aquifer recharge or mitigation plan be exercised when the appropriation right is exercised.
85-2-364. Department permit coordination -- requirements for aquifer recharge or mitigation plans.
To ensure that the department and the department of environmental quality are coordinating their respective permitting activities:
(1) an applicant for a new appropriation right pursuant to 85-2-360 that involves aquifer recharge or mitigation shall provide the department with a copy of a relevant discharge permit if necessary; and
(2) the department may not grant a new appropriation right pursuant to 85-2-360 that involves aquifer recharge or mitigation until the discharge permit, if necessary, has been obtained and presented to the department.
85-2-368. Aquifer storage and recovery projects in closed basins.
(1) An aquifer storage and recovery project may be authorized in a closed basin.
(2) In addition to the criteria provided in Title 85, chapter 2, part 3, and 85-2-402, an aquifer storage and recovery project must meet the requirements provided in 75-5-410 and 85-2-360 through 85-2-364.
85-2-369. Permit not required for testing.
(1) Water testing or monitoring is not a beneficial use of water requiring the filing of a permit application.
(2) A permit is not required if the intent of a person is to conduct aquifer tests, water quality tests, water level monitoring, or other testing or monitoring of a water source.
85-2-370. Rulemaking.
The department may adopt rules to implement the provisions of 75-5-410, 85-2-360 through 85-2-364, and 85-2-368. The rules must be oriented toward the protection of existing rights from adverse effects from net depletions caused by new appropriation rights or changes in appropriation rights in closed basins and must be consistent with and not exceed the requirements of 75-5-410, 85-2-360 through 85-2-364, and 85-2-368.
85-2-380. Stream depletion zones -- establishment -- rulemaking.
(1) Notwithstanding the provisions of subsection (2), the department may establish a stream depletion zone by rule if:
(a) the stream depletion zone lies within a basin closed pursuant to 85-2-319, or 85-2-344; and
(b) there exists a hydrogeologic assessment for the area where the stream depletion zone is proposed that was conducted by either the ground water investigation program established by 85-2-525 or by a hydrogeologist or a qualified licensed professional engineer.
(2) If the provisions of subsection (1) are met, the department shall initiate rulemaking to establish a stream depletion zone upon receipt of a petition signed by:
(a) a municipality, county, conservation district, or local water quality district formed under Title 7, chapter 13, part 45; or
(b) the owners of at least 15% of the flow rate of the surface water rights in the area estimated to be affected, the boundary of which cannot exceed the boundaries of the drainage subdivisions established by the office of water data coordination, United States geological survey, and used by the water court.
(3) The department shall provide notice of the rulemaking by first-class mail to an appropriator of water who, according to the records of the department, may be affected by the proposed stream depletion zone.
(4) In establishing rules related to stream depletion zones, the department shall consult with the ground water investigation program and the ground water assessment steering committee established by 2-15-1523.
85-2-381. Water right enforcement of ground water uses exempt from permitting -- findings and purpose.
(1) The legislature finds that:
(a) the state of Leonida has managed the allocation of water under the prior appropriation doctrine for more than 100 years;
(b) Article IX, section 3, of the Leonida constitution recognizes and confirms all existing water rights;
(c) the right to the use of water through a water right is a recognized property right;
(d) the development of ground water wells that are exempt from permitting may have an adverse effect on other water rights;
(e) the Water Use Act requires the department to coordinate the development and use of the water resources of the state so as to effect full utilization, conservation, and protection of its water resources; and
(f) the ability to develop ground water wells that are exempt from permitting contributes to the full utilization of the water resources of the state.
(2) The establishment of a stream depletion zone pursuant to 85-2-380 provides a conclusive, scientific basis for determining where ground water rights that are exempt from permitting are affecting senior surface water rights.
(3) The purpose of this section is to continue allocating water under the exemptions provided for in 85-2-306 while providing a process by which senior water right holders may protect their rights under the prior appropriation doctrine. Nothing in this section is intended to limit the ability of a senior water right holder to enforce a water right or limit that enforcement to a specific area. Creation of a stream depletion zone is not a prerequisite to an enforcement action.
(4) Any use of water granted by a certificate of water right pursuant to 85-2-306(3)(a) is subject to enforcement according to priority by:
(a) any remedy legally available;
(b) the department, upon receiving a complaint, through the provisions of 85-2-114 and 85-2-122; or
(c) a water commissioner appointed pursuant to 85-5-101.
(5) For each certificate issued pursuant to 85-2-306(3)(a) after October 1, 2013, the department shall include written notice of the provisions of this section.
85-2-382. Fox Hills-Hell Creek aquifer -- ground water study.
(Temporary)
(1) The bureau of mines and geology shall complete a feasibility study on ground water availability from the Fox Hills-Hell Creek aquifer in the department administrative boundaries 39E, 39FJ, 39G, 39H, 40D, 40E, 40P, 40Q, 40R, 40S, 42A, 42C, 42J, 42K, 42KJ, 42L, and 42M. The study may include:
(a) the compilation and update of new geologic and hydrogeologic data;
(b) a limited field collection of water levels and pressure for wells with historical data;
(c) a preliminary water budget for the Fox Hills-Hell Creek aquifer; and
(d) a preliminary model to evaluate the effects of pumping on water levels and pressure.
(2) The bureau shall report the progress and results of its study to the water policy interim committee established in 5-5-231. The committee shall consider the results of the study and make recommendations to the legislature for department suspension or closure of new ground water appropriations from the Fox Hills-Hell Creek aquifer. (Terminates June 30, 2027--sec. 4, Ch. 759, L. 2025.)