85-15-207. Dams and reservoirs -- how constructed.
No person may fill or procure to be filled with water any dam or reservoir that is not so thoroughly and substantially constructed as to safely hold any water that may be turned therein.
Use Open PDF for a printable PDF in a new tab.
No person may fill or procure to be filled with water any dam or reservoir that is not so thoroughly and substantially constructed as to safely hold any water that may be turned therein.
No person may construct or cause to be constructed a dam or reservoir for the purpose of accumulating, storing, appropriating, or diverting any of the waters of this state, except in a thorough, secure, and substantial manner.
A person proposing to construct a dam or reservoir with an impounding capacity of 50 acre-feet or more measured at the maximum normal operating pool shall make application to the department for a determination of whether the dam or reservoir is a high-hazard dam. The application must include the information required by the department. The department shall make the determination required by this section within 60 calendar days after a complete application is received by the department.
(1) A person may not begin construction of a high-hazard dam as determined under 85-15-209 without first obtaining a construction permit from the department.
(2) An application for a construction permit must be submitted to the department and must contain:
(a) plans and specifications for the proposed construction, prepared by or under the direction of an engineer experienced in dam design and construction; and
(b) other data and information required by the department.
(3) Within 60 calendar days after receipt of the application and any additional information requested by the department, the department shall:
(a) issue a construction permit or deny the application, as filed; or
(b) issue a construction permit upon terms, conditions, or modifications the department considers appropriate.
(1) An engineer must be in charge of and responsible for inspections during construction of any high-hazard dam.
(2) Inspections during construction must be performed at intervals necessary to ensure conformity with the permit. The engineer in charge or a qualified designee shall perform the inspections.
(3) The department shall set procedures and requirements for reporting information obtained from, during, or as the result of an inspection. The engineer in charge shall certify all reports to the department.
(4) The department may also inspect the high-hazard dam during construction to ensure conformity with the construction permit.
(5) If the department finds that construction of the high-hazard dam does not conform with the construction permit, it may order that construction be stopped until changes are made in conformity with the permit.
(1) An operation plan must be prepared by the owner and approved by the department prior to operation of the high-hazard dam or reservoir. The operation plan must set forth at a minimum:
(a) a reservoir operation procedure;
(b) a maintenance procedure for the high-hazard dam and appurtenant works; and
(c) emergency procedures and warning plans.
(2) When construction is complete and if the high-hazard dam or reservoir conforms to the construction permit and when an operation plan has been approved, the department shall issue a permit to operate the high-hazard dam or reservoir, containing conditions on the safe operation of the high-hazard dam as it considers necessary.
(1) (a) A high-hazard dam, whether or not previously permitted by the department, must be inspected as often as considered necessary by the department, but at least once every 5 years, in order to ensure the continued safe operation of the high-hazard dam.
(b) The department determination that an inspection is necessary more often than once every 5 years, as provided in subsection (1)(a), must be based on substantive evidence, and the reasons for that determination must be stated in writing.
(2) Periodic inspections required by this section must be performed by a qualified engineer, who shall make a report of the inspection to the department. If the department finds that the high-hazard dam conforms to current safety standards, it shall issue or reissue, as the case may be, a permit to continue operation of the high-hazard dam, containing conditions on the safe operation of the high-hazard dam as it considers necessary.
(3) The owner is responsible for inspections required under this section.
(1) At its discretion or upon receipt of an affidavit complaining that the person or property of the complainant is endangered by the construction, maintenance, or operation of any dam or reservoir, the department may order an inspection of the dam or reservoir unless the data, records, and inspection reports on file are adequate to determine that the complaint is not meritorious.
(2) If the complainant continues to request an inspection even though the department has determined under subsection (1) that the complaint is not meritorious, the department may make the inspection upon requiring the complainant to deposit with the department money sufficient to cover the costs of the inspection.
(3) If the dam or reservoir is found to be defective, the department may require the person who owns the dam or reservoir to pay all or part of the expenses of inspection. If the department requires such payment, it shall present a bill of costs to the owner. The costs shall constitute a lien upon the dam, reservoir, and other property of the owner and may be collected by appropriate action in a court of competent jurisdiction.
(4) If the dam or reservoir is not found to be defective after an inspection made under subsection (2), any money deposited by the complainant therefor must be paid to the general fund.
(5) If the inspection discloses defects in the dam or reservoir that, in the judgment of the department, constitute an immediate hazard to life or property, the department may order:
(a) the draining of the dam or reservoir;
(b) the limitation or cessation of use of the dam or reservoir or any defective appurtenant works; or
(c) any other steps to eliminate the hazard until the dam, reservoir, or appurtenant works have been made safe and approved by the department.
(1) In case of an emergency, the department may take any action necessary to safeguard life and property. This action must be commenced immediately by the owner, or by the department at the owner's expense if the owner fails to act. The department must be notified immediately of any proposed emergency repairs or breaching to be instituted by the owner.
(2) All costs incurred by the department during an emergency must be paid by the owner on receipt of a bill of costs from the department. The costs are a lien upon the dam, reservoir, and other property of the owner and may be collected by appropriate action in a court of competent jurisdiction.
Failure to comply with the provisions of 85-15-209 through 85-15-212 or 85-15-214 subjects the permit to cancellation at any time during the progress of construction or the operation of the high-hazard dam. The department is authorized to cancel any permit if the provisions of 85-15-209 through 85-15-212 or 85-15-214 have not been or are not being complied with, and the cancellation operates as a forfeiture of all rights acquired under and by virtue of any permit approved by the department.