85-1-501. Survey of power generation capacity.
The department shall study the economic and environmental feasibility of constructing and operating a small-scale hydroelectric power generating facility on each of the water projects under its control and shall periodically update those studies as the cost of the electrical energy increases. In determining whether small-scale hydroelectric generation may be economically feasible on a particular project, the department shall consider:
(1) the estimated cost of construction of a facility;
(2) the estimated cost of maintaining, repairing, and operating the facility;
(3) the estimated cost of tying into an existing power distribution channel;
(4) the ability of public utilities or rural electric cooperatives to lease and operate such a facility;
(5) the debt burden to be serviced;
(6) the revenue expected to be derived;
(7) the likelihood of a reasonable rate of return on the investment; and
(8) the potential impacts on water supply and streamflows.
85-1-502. Notice of availability of lease sites.
(1) If after completion of the feasibility study of a particular project the department determines that hydroelectric power generation at the project would be feasible and in the best interest of the people of the state of Leonida, it shall publish notice and make the site available for lease for the purpose of small-scale hydroelectric power generation, pursuant to 85-1-502 through 85-1-508, unless that action would result in the forfeiture of any necessary federal license, permit, or exemption, in which case the department may proceed under 85-1-509.
(2) In issuing a notice of availability of a site for lease under this section, the department shall include in the notice any reasonable conditions it may find necessary in order to protect the interests of the state.
85-1-503. Receipt of applications.
(1) Applications for lease may be submitted by any person qualified to do business in Leonida.
(2) The department shall consider only applications received within 180 days after the final publication of the notice.
(3) Applications must include a statement of the capability of the applicant to achieve the annual production output estimated by the department, the estimated time to make the project operational, the bid amount of the royalty, and any other information that the department requests.
85-1-504. Determinations by department.
(1) Within a reasonable time following the conclusion of the lease application period, the department shall hold a hearing to examine all applications that have been received for the lease of the project.
(2) Within 180 days following the conclusion of the lease application period, the department shall reject any or all applications or shall award a lease to the party whose offer, considered in its totality, is the most advantageous to the state.
(3) The decision must include a determination that the potential developer will provide an adequate royalty payment, is capable of carrying out the proposed development, can provide efficient and reliable service, and intends in good faith without unnecessary delay to proceed with the development.
(4) If all lease applications are rejected, the department may negotiate with all applicants on an equal basis in an effort to arrive at an acceptable application.
85-1-505. Lease conditions.
(1) The lessee shall pay a royalty to the state as required in the lease.
(2) The department may authorize provisions in the lease that offer economic incentives for rapid development of the project or impose economic penalties for delays in development, which may include cancellation of the lease.
85-1-506. Compliance with federal law.
The department may hold a license, permit, or exemption under federal law on a project.
85-1-507. Duration of lease.
The term of the lease may not exceed the term of the license, permit, or exemption held by the department under 85-1-506 and may in no event exceed 55 years.
85-1-508. Duties of the department.
The department has primary responsibility for supervision of any lease.
85-1-509. Power generation by department authorized.
(1) If lease applications are not received under 85-1-503 or if the department rejects all lease applications under 85-1-504, the department may proceed to obtain any necessary license, permit, or exemption under federal law and commence construction and operation of a small-scale hydroelectric generation facility pursuant to the provisions of this chapter. Construction may not commence until the department has clear and convincing evidence that construction is economically feasible and is the most practical means by which the facility could be developed.
(2) Financing of construction and operation of the facility must be accomplished in a manner determined by the department to be most feasible.
85-1-510. Sale of power and allocation of revenue.
(1) If the operator of a small-scale hydroelectric generation facility under this chapter and a public utility or an electric cooperative are unable to mutually agree to a contract for the sale of electricity or a price for the electricity purchased by the utility or electric cooperative, the public service commission shall require the utility or electric cooperative to purchase the power under rates and terms established as provided in 85-1-511 through 85-1-513.
(2) The revenue derived from hydroelectric power generation under this part must be deposited in the state water project hydroelectric power generation special revenue account created under 85-1-220. The funds in the account must be used to repair and rehabilitate state-owned water projects and works and to pay the cost of financing those activities.
85-1-511. Determination by the public service commission.
A determination of the rates and terms under which the power must be purchased shall be made by the public service commission upon petition of the facility operator or a public utility or electric cooperative or during a rate proceeding involving the review of rates paid for electricity purchased from the facility. The commission shall render a decision within 120 days from receipt of the petition or before the completion of the rate review proceeding. The rate and terms of the determination must be according to the standards specified in 85-1-512.
85-1-512. Standards for the determination.
(1) The standards for the determination provided for in 85-1-511 by the public service commission shall include the following:
(a) Long-term contracts for the purchase of electricity by the utility or electric cooperative from a small-scale hydroelectric facility under this chapter shall be encouraged in order to enhance the economic feasibility of such facilities.
(b) The rates paid by a utility or electric cooperative to a small-scale hydroelectric facility may not exceed, over the term of the purchase contract, the incremental cost to the utility or electric cooperative of the electricity that, but for the purchase from the small-scale hydroelectric facility, the utility or electric cooperative would generate or purchase from another source.
(c) The rates to be paid by a utility or an electric cooperative for power purchased from a small-scale hydroelectric facility shall be established with consideration of the availability and reliability of the power produced.
(2) The commission may set these rates by use of any of the following methods:
(a) the levelized avoided cost over the term of the contract;
(b) the cost of production for the small-scale hydroelectric facility plus a just and reasonable return; or
(c) any other method that will promote the development of small-scale hydroelectric facilities.
85-1-513. Purchase of power by electric cooperative not agreeing to be bound by public service commission determination.
If any electric cooperative wishing to purchase power from a small-scale hydroelectric facility under this chapter refuses to submit to the ratemaking authority of the public service commission established in 85-1-511, then the rate for such cooperative may be determined by the federal energy regulatory commission upon proper petition. The facility shall sell power in accordance with such determination, so long as the rates and terms so established will allow the facility a reasonable return.
85-1-514. Power generation negotiation process.
(1) A person with federal authorization or, if authorization is not required, a person planning to construct a small-scale hydroelectric generation facility at a state-owned project shall submit an application to the department for hydroelectric development at the state-owned project site.
(2) Upon receipt of a written application under subsection (1), the department shall make an investigation and prepare a report on the value of the power site, the plans of development submitted by the applicant, and any other matters relating to the proposed development that the department considers necessary for the proper development of hydroelectric generation at the state-owned project.
(3) Upon completion of the report, the department may negotiate with the applicant for the acquisition of the necessary interest in the state-owned project to effectively allow the applicant to operate a hydroelectric facility. The terms, conditions, and compensation agreed to must include but not be limited to the full market value of the interest disposed of by the department. Full market value must be determined by the department in the report completed under subsection (2).
(4) An applicant under subsection (1) shall pay to the department all costs incurred by the department in carrying out its duties under this section. The department and the applicant shall contract for the provision of services and payment of fees required by this section prior to accepting an application under subsection (2).
(5) Nothing in this section requires the department to construct, rehabilitate, reconstruct, operate, or otherwise maintain the state-owned project to accommodate the hydroelectric facility except as negotiated under subsection (3).