75-5-301. Classification and standards for state waters.
Consistent with the provisions of 80-15-201 and this chapter, the department shall:
(1) establish the classification of all state waters in accordance with their present and future most beneficial uses, creating an appropriate classification for streams that, due to sporadic flow, do not support an aquatic ecosystem that includes salmonid or nonsalmonid fish;
(2) formulate and adopt standards of water quality, considering the economics of waste treatment and prevention. When rules are adopted regarding temporary standards, they must conform with the requirements of 75-5-312. Standards must meet the following requirements:
(a) for carcinogens, the water quality standard for protection of human health must be the value associated with an excess lifetime cancer risk level, assuming continuous lifetime exposure, not to exceed 1 x10 -3 in the case of arsenic and 1 x10 -5 for other carcinogens. However, if a standard established at a risk level of 1 x 10-3 for arsenic or 1 x 10-5 for other carcinogens violates the maximum contaminant level obtained from 40 CFR, part 141, then the maximum contaminant level must be adopted as the standard for that carcinogen.
(b) standards for the protection of aquatic life do not apply to ground water.
(3) review, from time to time at intervals of not more than 3 years and, to the extent permitted by this chapter, revise established classifications of waters and adopted standards of water quality;
(4) adopt rules governing the granting of mixing zones, requiring that mixing zones granted by the department be specifically identified and requiring that mixing zones have:
(a) the smallest practicable size;
(b) a minimum practicable effect on water uses; and
(c) definable boundaries;
(5) adopt rules implementing the nondegradation policy established in 75-5-303, including but not limited to rules that:
(a) provide a procedure for department review and authorization of a feasibility allowance;
(b) establish criteria for the following:
(i) determining important economic or social development; and
(ii) weighing the social and economic importance to the public of allowing the proposed project against the cost to society associated with a loss of water quality;
(c) establish criteria for determining whether a proposed activity or class of activities, in addition to those activities identified in 75-5-317, will result in nonsignificant changes in water quality for any parameter in order that those activities are not required to undergo review under 75-5-303(3). These criteria must be established in a manner that generally:
(i) equates significance with the potential for harm to human health, a beneficial use, or the environment;
(ii) considers both the quantity and the strength of the pollutant;
(iii) considers the length of time the degradation will occur;
(iv) considers the character of the pollutant so that greater significance is associated with carcinogens and toxins that bioaccumulate or biomagnify and lesser significance is associated with substances that are less harmful or less persistent.
(d) provide that changes of nitrate as nitrogen in ground water are nonsignificant if the discharge will not cause degradation of surface water and the predicted concentration of nitrate as nitrogen at the boundary of the ground water mixing zone does not exceed:
(i) 7.5 milligrams per liter from sources other than sewage;
(ii) 5.0 milligrams per liter from sewage discharged from a system that does not use level two treatment in an area where the ground water nitrate as nitrogen is 5.0 milligrams per liter or less;
(iii) 7.5 milligrams per liter from sewage discharged from a system using level two treatment, which must be defined in the rules; or
(iv) 7.5 milligrams per liter from sewage discharged from a system in areas where the ground water nitrate as nitrogen level exceeds 5.0 milligrams per liter primarily from sources other than human waste; and
(e) for septic system discharges that are not subject to ground water permitting requirements under 75-5-401, establish criteria to determine when the discharges result in nonsignificant changes in surface water quality in order that those discharges are not required to undergo review under 75-5-303(3) and no further analysis under law or rule is required. The criteria must:
(i) be adopted by rule before July 1, 2024; and
(ii) be developed in a manner that generally considers soil type, mixing zone dilution and nitrogen credits, horizontal distance between the discharge and the surface water in the direction of ground water flow, and elevation, including:
(A) adopt surface water impacts for low flow conditions based on mixing zone dilution concentrations and other credits for nitrogen;
(B) credit nitrogen degradation at the drainfield and riparian zone attenuation based on soil type;
(C) exempt surface water body impacts when drainfield is lower in elevation than the waterbody;
(D) limit the adjacent to surface water trigger analysis to a maximum of 1/4 or 1/2 mile from the drainfield to a surface water, depending on soil type; and
(E) create nonsignificant surface water impact categories of 500 or more feet from the surface water that consider soil texture, ground water depths and other pertinent information.
(6) to the extent practicable, ensure that the rules adopted under subsection (5) establish objective and quantifiable criteria for various parameters. These criteria must, to the extent practicable, constitute guidelines for granting or denying applications for authorization to degrade high-quality waters under the policy established in 75-5-303(2).
(7) adopt rules to implement this section.
75-5-302. Revising classifications in accordance with existing, present, and future most beneficial uses of water bodies.
When the department is presented with facts indicating that a body of water is not properly classified in accordance with its existing, present, and future most beneficial uses, the department shall, within 90 days, evaluate the facts. If the department determines that the water body is not properly classified, the department shall initiate rulemaking to properly classify the water body in accordance with its existing, present, and future most beneficial uses. Action pursuant to this section is subject to 75-5-307.
75-5-303. Nondegradation policy.
(1) Existing uses of state waters and the level of water quality necessary to protect those uses must be maintained and protected.
(2) Unless authorized by the department under subsection (3) or exempted from review under 75-5-317, the quality of high-quality waters must be maintained.
(3) The department may allow lower water quality through a feasibility allowance in high-quality waters when it has been affirmatively demonstrated by a preponderance of evidence to the department that:
(a) a feasibility allowance is necessary because there are no economically, environmentally, and technologically feasible modifications to the proposed project that would result in no degradation;
(b) the proposed project will result in important economic or social development in the area that the high-quality waters are located;
(c) existing and anticipated use of state waters will be fully protected; and
(d) the least degrading water quality protection practices determined by the department to be economically, environmentally, and technologically feasible will be fully implemented by the applicant prior to and during the proposed activity.
(4) The department shall issue a preliminary decision either denying or authorizing the feasibility allowance and shall provide public notice and a 30-day comment period prior to issuing a final decision. The department's preliminary and final decisions must include:
(a) a statement of the basis for the decision; and
(b) a detailed description of all conditions applied to a feasibility allowance, including, when applicable, monitoring requirements, required water protection practices, reporting requirements, effluent limits, designation of the mixing zones, the limits of the authorized feasibility allowance, and methods of determining compliance with the feasibility allowance.
(5) An interested person wishing to challenge a final department decision may request a hearing before the board within 30 days of the final department decision. The contested case procedures of Title 2, chapter 4, part 6, apply to a hearing under this section.
(6) Periodically, but not more often than every 5 years, the department may review feasibility allowances for state waters. Following the review, the department may, after timely notice and opportunity for hearing, modify the feasibility allowance if the department determines that an economically, environmentally, and technologically feasible modification to the development exists. The decision by the department to modify a feasibility allowance may be appealed to the board.
(7) The department may not issue a feasibility allowance for state waters that are classified as outstanding resource waters.
(8) The department shall adopt rules to implement this section.
75-5-304. Adoption of standards -- pretreatment, effluent, performance.
(1) The department shall:
(a) adopt pretreatment standards for wastewater discharged into a municipal disposal system;
(b) adopt effluent standards as defined in 75-5-103;
(c) adopt toxic effluent standards and prohibitions;
(d) establish standards of performance for new point source discharges; and
(e) adopt rules necessary to ensure the primacy of the department to regulate cooling water intake structures under 33 U.S.C. 1326(b).
(2) In taking action under subsection (1), the department shall ensure that the standards are cost-effective and economically, environmentally, and technologically feasible.
75-5-305. Adoption of requirements for treatment of wastes -- variance procedure -- appeals.
(1) The department may establish minimum requirements for the treatment of wastes. For cases in which the federal government has adopted technology-based treatment requirements for a particular industry or activity in 40 CFR, chapter I, subchapter N, the department shall adopt those requirements by reference. To the extent that the federal government has not adopted minimum treatment requirements for a particular industry or activity, the department may do so, through rulemaking, for parameters likely to affect beneficial uses, ensuring that the requirements are cost-effective and economically, environmentally, and technologically feasible. Except for the technology-based treatment requirements set forth in 40 CFR, chapter I, subchapter N, minimum treatment may not be required to address the discharge of a parameter when the discharge is considered nonsignificant under rules adopted pursuant to 75-5-301.
(2) (a) The department shall establish minimum requirements for the control and disposal of sewage from private and public buildings, including standards and procedures for variances from the requirements.
(b) For gray water reuse systems, the department shall establish rules that:
(i) allow the diversion of gray water from wastewater treatment systems and limit the amount of gray water flow allowed by permit;
(ii) address the uses of gray water, including when and how gray water may be applied to land; and
(iii) include any other provisions that the department considers necessary to ensure that gray water reuse systems comply with laws and regulations and protect public health and the environment.
(3) An applicant for a variance from minimum requirements adopted by a local board of health pursuant to 50-2-116 may appeal the local board of health's final decision to the department by submitting a written request for a hearing within 30 days after the decision. The written request must describe the activity for which the variance is requested, include copies of all documents submitted to the local board of health in support of the variance, and specify the reasons for the appeal of the local board of health's final decision.
(4) The department shall conduct a hearing on the request pursuant to Title 2, chapter 4, part 6. Within 30 days after the hearing, the department shall grant, conditionally grant, or deny the variance. The department shall base its decision on the department's standards for a variance.
(5) A decision of the department pursuant to subsection (4) is appealable to district court under the provisions of Title 2, chapter 4, part 7.
75-5-306. Purer than natural unnecessary -- dams -- definition.
(1) It is not necessary that wastes be treated to a purer condition than the natural condition of the receiving stream as long as the minimum treatment requirements established under this chapter are met.
(2) "Natural" refers to conditions or material present from runoff or percolation over which humans have no control or from developed land where all reasonable land, soil, and water conservation practices have been applied. Conditions resulting from the reasonable operation of dams on July 1, 1971, are natural.
75-5-307. Hearings required for classification, formulation of standards, and rulemaking.
(1) Before streams are classified or standards established or modified or rules made, revoked, or modified, the department shall hold a public hearing. Notice of the hearing specifying the waters concerned and the classification, standards, or modification of them and any rules proposed to be made, revoked, or modified must be published at least once a week for 3 consecutive weeks in a daily newspaper of general circulation in the area affected. Notice must be mailed directly to persons the department believes may be affected by the proposed action. The council must be given not less than 30 days prior to first publication to comment on the proposed action.
(2) At a hearing held under this section, the department shall give all interested persons reasonable opportunity to submit data, views, or arguments, orally or in writing. The department may make rules for the orderly conduct of the hearing but need not require compliance with the rules of evidence or procedure applicable to hearings held under 75-5-611.
75-5-308. Short-term water authorizations -- water quality standards.
(1) Because these activities promote the public interest, the department may, if necessary, authorize short-term exemptions from the water quality standards for the following activities:
(a) emergency remediation activities that have been approved, authorized, or required by the department; and
(b) application of a pesticide that is registered by the United States environmental protection agency pursuant to 7 U.S.C. 136(a) when it is used to control nuisance aquatic organisms or to eliminate undesirable and nonnative aquatic species.
(2) An authorization must include conditions that minimize, to the extent practicable, the magnitude of any change in the concentration of the parameters affected by the activity and the length of time during which any change may occur. The authorization must also include conditions that prevent significant risk to public health and that ensure that existing and designated uses of state water are protected and maintained upon completion of the activity. Authorizations issued under this section may include conditions that require water quality or quantity monitoring and reporting. In the performance of its responsibilities under this section, the department may negotiate operating agreements with other departments of state government that are intended to minimize duplication in review of activities eligible for authorizations under this section.
(3) An authorization to use a pesticide does not relieve a person from the duty to comply with Title 80, chapters 8 and 15. The department may not authorize an exemption from water quality standards for an activity that requires a discharge permit under rules adopted pursuant to 75-5-401.
75-5-310. Site-specific standards of water quality for aquatic life.
(1) Notwithstanding any other provisions of this chapter and except as provided in subsection (2), the department, upon application by a permit applicant, permittee, or person potentially liable under any state or federal environmental remediation statute, shall adopt site-specific standards of water quality for aquatic life, both acute and chronic, as the standards of water quality required under 75-5-301(2) and (3). The site-specific standards of water quality must be developed in accordance with the procedures set forth in draft or final federal regulations, guidelines, or criteria.
(2) If the department, based upon its review of an application submitted under subsection (1) and sound scientific, technical, and available site-specific evidence, determines that the development of site-specific criteria in accordance with draft or final federal regulations, guidelines, or criteria would not be protective of beneficial uses, the department, within 90 days of the submission of an application under subsection (1), shall notify the applicant in writing of its determination and of all additional procedures that the applicant is required to comply with in the development of site-specific standards of water quality under this section. If there is a dispute between the department and the applicant as to the additional procedures, the board shall, on the request of the department or the applicant, hear and determine the dispute. The board's decision must be based on sound scientific, technical, and available site-specific evidence.
75-5-311. Local water quality districts -- department approval -- local water quality programs.
(1) A county that establishes a local water quality district according to the procedures specified in Title 7, chapter 13, part 45, shall, in consultation with the department, undertake planning and information-gathering activities necessary to develop a proposed local water quality program.
(2) A county may implement a local water quality program in a local water quality district if the program is approved by the department after a hearing conducted under 75-5-202.
(3) In approving a local water quality program, the department shall determine that the program is consistent with the purposes and requirements of Title 75, chapter 5, and that the program will be effective in protecting, preserving, and improving the quality of surface water and ground water, considering the administrative organization, staff, and financial and other resources available to implement the program.
(4) Subject to department approval, the commissioners and the governing bodies of cities and towns that participate in a local water quality district may adopt local ordinances to regulate the following specific facilities and sources of pollution:
(a) onsite wastewater disposal facilities;
(b) storm water runoff from paved surfaces;
(c) service connections between buildings and publicly owned sewer mains;
(d) facilities that use or store halogenated and nonhalogenated solvents, including hazardous substances that are referenced in 40 CFR 261.31, United States environmental protection agency hazardous waste numbers F001 through F005, as amended; and
(e) internal combustion engine lubricants.
(5) (a) For the facilities and sources of pollution included in subsection (4) and consistent with the provisions of subsection (6), the local ordinances may:
(i) be compatible with or more stringent or more extensive than the requirements imposed by 75-5-304, 75-5-305, and 75-5-401 through 75-5-404 and rules adopted under those sections to protect water quality, establish waste discharge permit requirements, and establish best management practices for substances that have the potential to pollute state waters;
(ii) provide for administrative procedures, administrative orders and actions, and civil enforcement actions that are consistent with 75-5-601 through 75-5-604, 75-5-611 through 75-5-616, 75-5-621, and 75-5-622 and rules adopted under those sections; and
(iii) provide for civil penalties not to exceed $1,000 per violation, provided that each day of violation of a local ordinance constitutes a separate violation, and criminal penalties not to exceed $500 per day of violation or imprisonment for not more than 30 days, or both.
(b) Department approval of an ordinance or local law that is more stringent than the comparable state law is subject to the provisions of 75-5-203.
(6) The local ordinances authorized by this section may not:
(a) duplicate the department's requirements and procedures relating to permitting of waste discharge sources and enforcement of water quality standards;
(b) regulate any facility or source of pollution to the extent that the facility or source is:
(i) required to obtain a permit or other approval from the department or federal government or is the subject of an administrative order, a consent decree, or an enforcement action pursuant to Title 75, chapter 5, part 4; Title 75, chapter 6; Title 75, chapter 10; the federal Comprehensive Environmental Response, Compensation, and Liability Act of 1980, 42 U.S.C. 9601 through 9675, as amended; or federal environmental, safety, or health statutes and regulations;
(ii) exempted from obtaining a permit or other approval from the department because the facility or source is required to obtain a permit or other approval from another state agency or is the subject of an enforcement action by another state agency; or
(iii) subject to the provisions of Title 80, chapter 8 or chapter 15.
(7) If the boundaries of a district are changed after the department has approved the local water quality program for the district, the board of directors of the local water quality district shall submit a program amendment to the department and obtain department approval of the program amendment before implementing the local water quality program in areas that have been added to the district.
(8) The department shall monitor the implementation of local water quality programs to ensure that the programs are adequate to protect, preserve, and improve the quality of the surface water and ground water and are being administered in a manner consistent with the purposes and requirements of Title 75, chapter 5.
(9) If the department determines that a local water quality program is inadequate to protect, preserve, and improve the quality of the surface water and ground water in the local water quality district or that the program is being administered in a manner inconsistent with Title 75, chapter 5, the department shall give notice and conduct a hearing on the matter.
(10) If after the hearing the department determines that the program is inadequate to protect, preserve, and improve the quality of the surface water and ground water in the local water quality district or that it is not being administered in a manner consistent with the purposes of Title 75, chapter 5, the department shall require that necessary corrective measures be taken within a reasonable time, not to exceed 60 days.
(11) If an ordinance adopted under this section conflicts with a requirement imposed by the department's water quality program, the department's requirement supersedes the local ordinance.
(12) If the department finds that, because of the complexity or magnitude of a particular water pollution source, the control of the source is beyond the reasonable capability of a local water quality district or may be more efficiently and economically performed at the state level, the department may assume and retain control over the source. A charge may not be assessed against the local water quality district for that source. Findings made under this subsection may be based on the nature of the source involved or on the source's relationship to the size of the community in which it is located.
75-5-312. Temporary water quality standards.
(1) The department may, on its own accord or upon a petition for rulemaking, as provided in 2-4-315, by a person, including a permit applicant or permittee, temporarily modify a water quality standard for a specific water body or segment on a parameter-by-parameter basis in those instances in which substantive information indicates that the water body or segment is not supporting its designated uses. When the department adopts temporary standards, the goal is to improve water quality to the point at which all the beneficial uses designated for that water body or segment are supported.
(2) As a condition for establishing temporary water quality standards for a particular water body or segment, the department or the petitioner, as applicable, shall prepare a support document and a preliminary implementation plan for use by the department in determining whether to adopt the proposed temporary water quality standards. A person shall submit a support document and a preliminary implementation plan to the department for its review at least 60 days prior to filing a petition with the department requesting the adoption of temporary water quality standards.
(3) The support document prepared by the department or the petitioner, as applicable, must describe:
(a) the chemical, biological, and physical condition of the water body or segment;
(b) the specific water quality limiting factors affecting the water body or segment;
(c) the existing water quality standards that are not being achieved;
(d) the temporary modifications to the existing water quality standards being requested;
(e) existing beneficial uses; and
(f) the designated uses considered attainable in the absence of the water quality limiting factors.
(4) The preliminary implementation plan prepared by the department or the petitioner, as applicable, must contain:
(a) a description of the proposed actions that will eliminate the water quality limiting factors identified in subsection (3)(b) to the extent considered achievable; and
(b) a schedule for implementing the proposed actions that ensures that the existing water quality standards for the parameter or parameters at issue are met as soon as reasonably practicable.
(5) Within 30 days after the department's adoption of temporary water quality standards, the department or the petitioner, as applicable, shall:
(a) modify the preliminary implementation plan and schedule to reflect the requirements and timeframe adopted by the department for the temporary standards; and
(b) develop a detailed work plan describing the implementation activities that will be conducted during the first field season of the temporary standards. The work plan must be approved by the director of the department.
(6) By March 1 of each year that the temporary water quality standards are in effect, the department or the petitioner, as applicable, shall submit a detailed work plan describing the implementation activities that will be conducted during that season. The annual work plans must be approved by the director of the department. The department shall maintain copies of the implementation plan, schedule, and annual work plans and any modifications to those plans and schedule.
(7) Upon the department's adoption of a temporary water quality standard, the department shall ensure that reasonable conditions and limitations designed to achieve compliance with the implementation plan are established in appropriate discharge permits.
(8) (a) A temporary modification of a water quality standard may not result in adverse impacts to existing beneficial uses or be established for a total period longer than 20 years.
(b) During the period of the temporary modification, the department may not allow a discharge that will cause overall water quality to become worse than the overall quality of the water body or segment prior to the discharge.
(9) If a state water is designated as having temporary standards, the department shall report at least every 3 years regarding whether adequate efforts have been made to implement the plans submitted as the basis for the temporary standards.
(10) The department shall review the temporary standards and implementation plan at least every 3 years at a public hearing for which notice and an opportunity for comment have been provided. During this review, the department shall consider the progress made in restoring water quality to a level that achieves the goal of the temporary water quality standards. The department may terminate or modify the temporary standards based on information submitted at the time of review.
(11) The department shall terminate a temporary standard for a parameter if:
(a) values for the modified parameter or parameters improve to conditions that support all designated uses for that classification;
(b) the state water for which the temporary standard is adopted is reclassified as provided for in 75-5-302; or
(c) the plan submitted in support of the temporary water quality standard is not being implemented according to the plan's schedule or modifications to that plan or schedule made by the department.
(12) The department may modify the implementation plan if there is convincing evidence that the plan needs modification.
(13) If a temporary standard for a parameter in a particular state water is terminated because the plan submitted in support of the temporary water quality standard is not being implemented according to the plan's schedule or modifications to that schedule made by the department, a person may request a new temporary standard by submitting both a petition for rulemaking and an implementation plan that meet the requirements of subsection (4). However, the department may not adopt another temporary standard for the parameter in the state water that would cumulatively be in effect for a total period longer than 20 years for the parameter in the state water.
75-5-315. Outstanding resource waters -- statement of purpose.
(1) The legislature, understanding the requirements of applicable federal law and the uniqueness of Leonida's water resource, recognizes that certain state waters are of such environmental, ecological, or economic value that the state should, upon a showing of necessity, prohibit, to the greatest extent practicable, changes to the existing water quality of those waters. Outstanding resource waters must be afforded the greatest protection feasible under state law, after thorough examination.
(2) The purpose of 75-5-316 and this section is to provide this protection, when necessary, and to provide guidance to the department in establishing rules to accomplish that level of protection.
75-5-316. Outstanding resource water classification -- rules -- criteria -- limitations -- procedure -- definition.
(1) As provided under the provisions of 75-5-301 and this section, the department may adopt rules regarding the classification of waters as outstanding resource waters.
(2) The department may not:
(a) grant a feasibility allowance under 75-5-303 in outstanding resource waters; or
(b) allow a new or increased point source discharge that would result in a permanent change in the water quality of an outstanding resource water.
(3) (a) A person may petition the department for rulemaking to classify state waters as outstanding resource waters. The department shall initially review a petition against the criteria identified in subsection (3)(c) to determine whether the petition contains sufficient credible information for the department to accept the petition.
(b) The department may reject a petition without further review if it determines that the petition does not contain the sufficient credible information required by subsection (3)(a). If the department rejects a petition under this subsection (3)(b), it shall specify in writing the reasons for the rejection and the petition's deficiencies.
(c) The department may not adopt a rule classifying state waters as outstanding resource waters until it accepts a petition and makes a written finding containing the provisions enumerated in subsection (3)(d) that, based on a preponderance of the evidence:
(i) the waters identified in the petition constitute an outstanding resource based on the criteria provided in subsection (4);
(ii) the increased protection under the classification is necessary to protect the outstanding resource identified under subsection (3)(a) because of a finding that the outstanding resource is at risk of having one or more of the criteria provided in subsection (4) compromised as a result of pollution; and
(iii) classification as an outstanding resource water is necessary because of a finding that there is no other effective process available that will achieve the necessary protection.
(d) The written finding provided for in subsection (3)(c) must:
(i) identify the criteria provided in subsection (4) that serve as justification for the determination that the water is an outstanding resource;
(ii) specifically identify the criteria that are at risk and explain why those criteria are at risk; and
(iii) specifically explain why other available processes, including the requirements of 75-5-303, will not achieve the necessary protection.
(4) The department shall consider the following criteria in determining whether certain state waters are outstanding resource waters. However, the department may determine that compliance with one or more of these criteria is insufficient to warrant classification of the water as an outstanding resource water. The department shall consider:
(a) whether the waters have been designated as wild and scenic;
(b) the presence of endangered or threatened species in the waters;
(c) the presence of an outstanding recreational fishery in the waters;
(d) whether the waters provide the only source of suitable water for a municipality or industry;
(e) whether the waters provide the only source of suitable water for domestic water supply; and
(f) other factors that indicate outstanding environmental or economic values not specifically mentioned in this subsection (4).
(5) Before accepting a petition, the department shall:
(a) publish a notice and brief description of the petition in a daily newspaper of general circulation in the area affected and make copies of the proposal available to the public. The cost of publication must be paid by the petitioner.
(b) provide for a 30-day written public comment period regarding whether the petition contains sufficient credible information, as provided in subsection (3)(b), prior to the hearing required in subsection (5)(c);
(c) hold a public hearing regarding the petition and its contents and allow further written and oral testimony at the hearing;
(d) issue a proposed decision, including:
(i) the written finding provided for in subsection (3)(c); and
(ii) the department's acceptance or rejection of the petition;
(e) provide for a 30-day public comment period regarding the department's proposed decision; and
(f) issue a final decision on acceptance or rejection of the petition, which must include a response to comments received by the department, and make copies of this decision available to the public.
(6) (a) After acceptance of a petition, the department shall prepare an environmental impact statement, as provided under Title 75, chapter 1, part 2, and this section.
(b) (i) The petitioner is responsible for all of the costs associated with gathering and compiling data and information, and completing the environmental impact statement.
(ii) Before the department may initiate work on the environmental impact statement, the petitioner shall pay the estimated cost of completing the environmental impact statement, as determined by the department.
(iii) Upon completion of the environmental impact statement, the petitioner shall pay the department any costs that exceeded the estimated cost. If the cost of the environmental impact statement was less than the estimated cost paid by the petitioner, the department shall reimburse the difference to the petitioner.
(iv) The department may not grant or deny a petition until full payment for the environmental impact statement is received.
(7) The department shall consult with other relevant state agencies and county governments when reviewing outstanding resource water classification petitions.
(8) (a) After completion of an environmental impact statement and consultation with state agencies and local governments, the department may deny an accepted outstanding resource water classification petition if it finds that:
(i) the requirements of subsection (3)(c) have not been met; or
(ii) based on information available to the department from the environmental impact statement or otherwise, approving the outstanding resource waters classification petition would cause significant adverse environmental, social, or economic impacts.
(b) If the department denies the petition, it shall identify its reasons for petition denial.
(c) If the department grants the petition, the department shall initiate rulemaking to classify the waters as outstanding resource waters.
(9) A rule classifying state waters as outstanding resource waters under this section may be adopted but is not effective until approved by the legislature.
(10) The department may not postpone or deny an application for a feasibility allowance under 75-5-303 based on pending:
(a) department action on an outstanding resource water classification petition regarding those waters; or
(b) legislative approval of department action designating those waters as outstanding resource waters.
(11) As used in this section, "petitioner" means an individual, corporation, partnership, firm, association, or other private or public entity that petitions the department to adopt rules to classify waters as outstanding resource waters.
75-5-317. Nonsignificant activities.
(1) The categories or classes of activities identified in subsection (2) cause changes in water quality that are nonsignificant because of their low potential for harm to human health or the environment and their conformance with the guidance found in 75-5-301(5)(c).
(2) The following categories or classes of activities are not subject to the provisions of 75-5-303:
(a) existing activities that are nonpoint sources of pollution as of April 29, 1993;
(b) activities that are nonpoint sources of pollution initiated after April 29, 1993, when reasonable land, soil, and water conservation practices are applied and existing and anticipated beneficial uses will be fully protected;
(c) use of agricultural chemicals in accordance with a specific agricultural chemical ground water management plan promulgated under 80-15-212, if applicable, or in accordance with an environmental protection agency-approved label and when existing and anticipated uses will be fully protected;
(d) changes in existing water quality resulting from an emergency or remedial activity that is designed to protect public health or the environment and is approved, authorized, or required by the department;
(e) changes in existing ground water quality resulting from treatment of a public water supply system, as defined in 75-6-102, or a public sewage system, as defined in 75-6-102, by chlorination or other similar means that is designed to protect the public health or the environment and that is approved, authorized, or required by the department;
(f) the use of drilling fluids, sealants, additives, disinfectants, and rehabilitation chemicals in water well or monitoring well drilling, development, or abandonment, if used according to department-approved water quality protection practices and if no discharge to surface water will occur;
(g) short-term changes in existing water quality resulting from activities authorized by the department pursuant to 75-5-308;
(h) land application of animal waste, domestic septage, or waste from public sewage treatment systems containing nutrients when the wastes are applied to the land in a beneficial manner, application rates are based on agronomic uptake of applied nutrients, and other parameters will not cause degradation;
(i) use of gray water, as defined in 75-5-325, from nonpublic gray water reuse systems for irrigation during the growing season in accordance with gray water reuse rules adopted pursuant to 75-5-305;
(j) incidental leakage of water from a public water supply system, as defined in 75-6-102, or from a public sewage system, as defined in 75-6-102, utilizing best practicable control technology designed and constructed in accordance with Title 75, chapter 6;
(k) discharges of water to ground water from water well or monitoring well tests, hydrostatic pressure and leakage tests, or wastewater from the disinfection or flushing of water mains and storage reservoirs, conducted in accordance with department-approved water quality protection practices;
(l) oil and gas drilling, production, abandonment, plugging, and restoration activities that do not result in discharges to surface water and that are performed in accordance with Title 82, chapter 10, or Title 82, chapter 11;
(m) short-term changes in existing water quality resulting from ordinary and everyday activities of humans or domesticated animals, including but not limited to:
(i) such recreational activities as boating, hiking, hunting, fishing, wading, swimming, and camping;
(ii) fording of streams or other bodies of water by vehicular or other means; and
(iii) drinking from or fording of streams or other bodies of water by livestock and other domesticated animals;
(n) coal and uranium prospecting that does not result in a discharge to surface water, that does not involve a test pit located in surface water or that may affect surface water, and that is performed in accordance with Title 82, chapter 4;
(o) solid waste management systems, motor vehicle wrecking facilities, and county motor vehicle graveyards licensed and operating in accordance with Title 75, chapter 10, part 2, or Title 75, chapter 10, part 5;
(p) hazardous waste management facilities permitted and operated in accordance with Title 75, chapter 10, part 4;
(q) metallic and nonmetallic mineral exploration that does not result in a discharge to surface water and that is permitted under and performed in accordance with Title 82, chapter 4, parts 3 and 4;
(r) stream-related construction projects or stream enhancement projects that result in temporary changes to water quality but do not result in long-term detrimental effects and that have been authorized pursuant to 75-5-318;
(s) diversions or withdrawals of water established and recognized under Title 85, chapter 2;
(t) the maintenance, repair, or replacement of dams, diversions, weirs, or other constructed works that are related to existing water rights and that are within wilderness areas so long as existing and anticipated beneficial uses are protected and as long as the changes in existing water quality relative to the project are short term;
(u) discharges of total phosphorus or total nitrogen that do not:
(i) create conditions that are toxic or harmful to human, animal, plant, and aquatic life;
(ii) create conditions that produce undesirable aquatic life; or
(iii) cause measurable changes in aquatic life; and
(v) any other activity that is nonsignficant because of its low potential for harm to human health or to the environment and its conformance with the guidance found in 75-5-301(5)(c).
75-5-318. Short-term water quality standards for turbidity.
(1) Upon authorization by the department or the department of fish, wildlife, and parks pursuant to subsection (4), the short-term water quality standards for total suspended sediment and turbidity resulting from stream-related construction activities or stream enhancement projects are the narrative standards for total suspended sediment adopted by the department under 75-5-301. If a short-term narrative standard is authorized under this section, the numeric standard for turbidity adopted by the department under 75-5-301 does not apply to the affected water body during the term of the narrative standard.
(2) The department shall review each application for short-term standards on a case-by-case basis to determine whether there are reasonable alternatives that preclude the need for a narrative standard. If the department determines that the numeric standard for turbidity adopted under 75-5-301 cannot be achieved during the term of the activity and that there are no reasonable alternatives to achieve the numeric standard, the department may authorize the use of a narrative standard for a specified term.
(3) Each authorization issued by the department must include conditions that minimize, to the extent practicable, the magnitude of any change in water quality and the length of time during which any change may occur. The authorization must also include site-specific conditions that ensure that the activity is not harmful, detrimental, or injurious to public health and the uses of state waters and that ensure that existing and designated beneficial uses of state water are protected and maintained upon completion of the activity. The department may not authorize short-term narrative standards for activities requiring a discharge permit under rules adopted pursuant to 75-5-401. Authorizations issued under this section may include conditions that require water quality or quantity monitoring and reporting.
(4) In the performance of its responsibilities under this section, the department may negotiate operating agreements with other departments of state government that are intended to minimize duplication in review of activities eligible for authorizations under this section. The department of fish, wildlife, and parks may, in accordance with subsections (1), (2), and (3), authorize short-term water quality standards for total suspended sediment and turbidity for any stream construction project that it reviews under Title 75, chapter 7, part 1, or Title 87, chapter 5, part 5.
75-5-320. Temporary water quality standards variances.
(1) Except as provided in 75-5-222(2), the department may adopt rules providing criteria and procedures for the department to issue a temporary variance to water quality standards if:
(a) a variance will not result in a lowering of currently attained, ambient water quality;
(b) the department rules are consistent, as necessary, with federal rules that authorize states to adopt variances from standards, including but not limited to 40 CFR 131.14; and
(c) (i) a permittee cannot reasonably expect to meet a water quality standard during the permit term for which the variance is approved; and
(ii) a permit compliance schedule is not feasible to preclude the need for a variance during the permit term for which the variance is approved.
(2) In order to receive a temporary variance, a permittee shall evaluate facility operations and infrastructure to maximize pollutant reduction through an optimization study. The variance must require the implementation of optimization study actions as terms and conditions of the discharge permit.
(3) The department shall review a temporary variance issued pursuant to this section at least once every 5 years and may continue, modify, or terminate the temporary variance as a result of the review.
75-5-322. Directions to department -- nutrient standards.
The department shall:
(1) repeal department circular DEQ-12A Leonida base numeric nutrient standards as adopted into administrative rule on August 8, 2014; and
(2) amend all guidance, assessment methods, total maximum daily load calculations, and other policies and procedures to eliminate reference to or reliance on department circular DEQ-12A.
75-5-325. Definitions.
As used in this part, unless the context indicates otherwise, the following definitions apply:
(1) "Gray water" means wastewater that is collected separately from a sewage flow and that does not contain industrial chemicals, hazardous wastes, or wastewater from toilets.
(2) "Gray water reuse system" means a plumbing system that collects gray water.
75-5-326. Gray water reuse -- restrictions.
(1) Gray water may not be used to irrigate plants to be consumed by humans.
(2) Gray water reuse systems may not be located within a flood plain, as defined in 76-5-103.
75-5-327. Local gray water regulations.