71-3-1001. Definitions.
As used in this part, the following definitions apply:
(1) "Furnish" means sell or rent.
(2) "Material" means material, fuel, machinery, equipment, appliances, buildings, structures, tools, bits, or supplies but does not include drilling rigs or hoists or their integral component parts except wire lines.
(3) "Owner" includes a person holding any interest in the legal or equitable title, or both, and purchasers under executory contract.
71-3-1002. Lien for labor and materials furnished for use on leasehold for oil and gas purposes or pipelines -- exceptions.
(1) Any person, corporation, or partnership that under expressed or implied contract with the owner of any leasehold for oil and gas purposes or the owner of any gas pipe or oil pipeline or with the trustee or agent of the owner performs labor or furnishes material or services used in the digging, drilling, torpedoing, completing, operating, or repairing of any oil or gas well or oil or gas pipeline or who furnishes any material or services or performs any labor in constructing or putting together any of the machinery used in digging, drilling, torpedoing, operating, completing, or repairing any oil or gas well or oil or gas pipeline, whether or not the material is incorporated into or becomes a part of the oil or gas well or oil or gas pipeline, may have a lien for the amount due, including associated transportation and mileage charges and interest from the date the amount was due, upon:
(a) the whole of the leasehold or oil or gas pipeline;
(b) the appurtenances on the leasehold or oil or gas pipeline;
(c) all material owned by the owner of the leasehold or oil or gas pipeline and used in the digging, drilling, torpedoing, completing, operating, or repairing of the oil or gas well or oil or gas pipeline;
(d) all oil or gas wells located on the leasehold; and
(e) all oil or gas produced from the leasehold, subject to the provisions of Title 71, chapter 3, part 16.
(2) If labor is performed for, or materials or services are furnished to, the owner of the working interest in only a portion of the acreage covered by a lease, the lien granted under subsection (1) must be restricted to the portion of the acreage that is covered by the lease.
(3) A lien granted under subsection (1) does not extend to any royalty interests, overriding royalty interests, or oil payments created prior to the date the first item of material or services are furnished or the date the first labor is performed.
71-3-1003. Lien for labor or supplies furnished for contractor.
Any person, partnership, or corporation that furnishes materials or services as a subcontractor or to a contractor or a subcontractor or any person who performs labor under a subcontractor with a contractor or who, as an artisan or day laborer in the employ of such contractor or subcontractor, performs any such labor has a lien upon all the property upon which the lien of an original contractor may attach to the same extent as an original contractor, and the lien provided for in this section attaches to all materials and fixtures owned by such original contractor or subcontractor for whom the labor is performed or materials or services furnished and used or employed or furnished to be used or employed in the drilling or operating of such oil and gas wells or in the construction of such pipeline.
71-3-1004. How lien perfected.
A person, corporation, or partnership claiming a lien under this part shall file with the county clerk of the county in which the land, leasehold, or pipeline or some part of the land, leasehold, or pipeline is situated a statement verified by affidavit setting forth the amount claimed and the items of the claim, the dates on which labor was performed or material or services furnished, the name of the owner of the leasehold or pipeline, if known, the name of the claimant and the claimant's mailing address, a description of the leasehold or pipeline, and if the claimant is a claimant under 71-3-1003, the name of the person for whom the labor was immediately performed or the material or services were immediately furnished. The statement must be filed within 6 months after the date upon which the material or services were last furnished or labor was last performed under contract.
71-3-1005. Enforcement of liens -- duty of county clerks.
The liens herein created shall be enforced in the same manner and the duty of county clerks with respect to the filing and abstracting of liens shall be the same as now provided by the laws for materialmen's and construction liens.
71-3-1006. Date lien arises.
The lien provided for in this part arises on the date of the furnishing of the first item of material or services or the date of performance of the first labor.
71-3-1007. Priority.
(1) Upon compliance with the provisions of 71-3-1004, such lien shall be preferred to all other titles, charges, liens, or encumbrances which may attach to or upon any of the property upon which a lien is given by this part subsequent to the date the lien herein provided for arises.
(2) All liens affixed by virtue of this part upon the same property shall be of equal standing.
(3) The lien herein provided for shall have no priority over other liens, encumbrances, or mortgages which are filed or recorded prior to the date of the furnishing of the first item of material or services or the date of performance of the first labor.
71-3-1008. Lien for running account as single contract.
All labor performed or materials or services furnished by any person entitled to a lien under this part upon the same leasehold for oil and gas purposes or the same pipeline shall for the purposes of this part be considered as having been performed or furnished under a single contract regardless of whether or not the same was performed or furnished at different times or on separate orders, provided that no more than 6 months shall have elapsed between the date of performance of such labor or the date of furnishing such material or services and the date on which labor is next performed or materials or services are next furnished.
71-3-1009. Liability fixed.
This part may not be construed to fix a greater liability against the owner of the land or leasehold interest in the land than the price or sum stipulated by the owner to be paid for the materials or services furnished or labor performed. However, the risk of all payments made to the original contractor must be upon the owner if the payments are made after written notice from a person other than an original contractor is received by the owner at the owner's residence or principal place of business. The notice must set forth the name and address of the claimant and the amount and nature of the claim. Payment by the owner to the original contractor of all or any part of the contract price prior to the receipt of the notice must operate to discharge and satisfy all liens attaching to the property of the owner by virtue of this part to the extent of the payment. The owner does not have the right to offset obligations of the original contractor unless the obligations arise out of the original contract.
71-3-1010. Removal of property covered by lien prohibited -- effect of wrongful removal.
(1) When any lien provided for by this part shall have attached to the property covered thereby, it shall be unlawful for any person to remove such property or any part thereof or cause the same to be removed from the land or premises where located at the time such lien attached or otherwise dispose of the same without the written consent of the holder of such lien.
(2) In the event such property or some part thereof is about to be removed or disposed of in violation of this section, the district court for the county where such property or any part thereof is located may, upon the verified application of the holder of such lien, enjoin all persons alleged in such application to be about to remove or dispose of such property or some part thereof from removing or disposing of the same.
(3) In the event such property or any part thereof shall have been removed or disposed of in violation of this section, the holder of such lien shall be entitled in any action to foreclose the same to the appointment of a receiver to take possession of such removed or disposed of property wherever the same may be located within this state.
(4) This section shall not preclude the appointment of a receiver in actions brought to foreclose liens given by this part upon any equitable grounds warranting such appointment.
71-3-1011. Notice to purchaser of oil and gas.
(1) Any lien claimed under this part that extends to oil or gas or the proceeds of the sale of oil or gas is subject to the provisions of Title 71, chapter 3, part 16, and must meet the requirements of subsection (2) before taking effect.
(2) (a) Written notice of a claim must be delivered to a purchaser at the purchaser's residence or principal place of business. A notice must state the name of the claimant, the claimant's address, the amount for which the lien is claimed, and a description of the interest upon which the lien is claimed. The notice must be delivered personally to the purchaser or by certified letter deposited in the United States mail.
(b) Until the notice is delivered as provided in subsection (2)(a), a purchaser is not liable to the claimant for any oil or gas produced upon which the lien is claimed or money from the sale of proceeds of the oil or gas upon which the lien is claimed. A purchaser shall withhold payments for oil or gas to the extent of the lien amount being claimed until delivery of notice in writing that the claim has been paid.
71-3-1012. Effect on interest which is less than fee interest.
If a lien provided for in this part attaches to an estate less than the fee, forfeiture of such estate shall not impair any lien as to material, appurtenances, and fixtures located thereon and to which said lien has attached prior to forfeiture. If a lien provided for in this part attaches to an equitable interest or to a legal interest contingent upon the happening of a condition subsequent, failure of such interest to ripen into legal title or such condition subsequent to be fulfilled shall not impair any lien as to material, appurtenances, and fixtures located thereon and to which said lien attached prior to such failure.