70-30-301. Hearing -- judge to preside -- determinations by condemnation commissioners.
(1) The condemnation commissioners shall meet at the time and place stated in the order appointing them. The meeting time may not be more than 10 days after the order of appointment. The commissioners shall examine the lands sought to be taken. At a time appointed by the judge and within the 10-day period, the commissioners shall hear the allegations and evidence of all persons interested in each parcel of land.
(2) The hearing must be attended by and presided over by the presiding judge, who shall make all necessary rulings upon procedure and the admissibility of evidence.
(3) (a) At the conclusion of the hearing, the judge shall instruct the commissioners as to the law applicable to their deliberations and shall instruct them that their duty is to determine, based solely upon their examination of lands, the evidence produced at the hearing or hearings, and the instructions of the court, the appropriate findings provided for in subsections (3)(b) through (3)(d).
(b) The commissioners shall determine the current fair market value of the real property sought to be taken and all improvements pertaining to the real property and of each separate estate and interest in the real property and improvements. If the real property consists of different parcels, the current fair market value of each parcel and each estate or interest in the real property must be separately assessed.
(c) (i) If the property sought to be taken constitutes only a part of a larger parcel, the commissioners shall determine the depreciation in current fair market value that will accrue to the remaining parcel by reason of the condemnation and the construction of the improvements in the manner proposed by the condemnor.
(ii) The commissioners shall also determine how much the remaining parcel and each estate or interest in the remaining parcel will be benefited, if at all, by the construction of the improvements proposed by the condemnor. If the benefit is equal to the amount assessed under subsection (3)(c)(i), the compensation to the condemnee is limited to the value of the portion taken. However, if the benefit is less than the amount assessed under subsection (3)(c)(i), the benefit to the condemnee must be deducted from the amount assessed under subsection (3)(c)(i) and the remainder is the only amount allowed in addition to the current fair market value.
(d) If the property sought to be taken is for a railroad, the commissioners shall also determine the cost of good and sufficient fences along the line of the railroad and the cost of cattle guards where fences may cross the line of the railroad.
(e) Through examination of the property, the commissioners shall determine the appropriate payment for damages to the property taken, as well as to any remaining parcel of property that may be adversely impacted by the project, to assist the court in making a final determination pursuant to 70-30-309.
(4) When there are two or more estates or divided interests in property sought to be taken, the condemnor is entitled to have the amount of the award for the property first determined as between the condemnor and all condemnees claiming any interest in the property. In the same proceeding, the respective rights of each of the condemnees in and to the total award must be determined by the commissioners, under supervision and instruction of the court, and the award must be apportioned accordingly.
70-30-302. Assessing compensation -- date and measure -- interest.
(1) For the purpose of assessing compensation, the right to compensation is considered to have accrued at the date of the service of the summons, and the property's current fair market value as of that date is the measure of compensation for all property to be actually taken and the basis of depreciation in the current fair market value of property not actually taken but injuriously affected. This subsection may not be construed to limit the amount of compensation payable by the department of transportation under the provisions of any legislation enacted pursuant to the federal Highway Beautification Act of 1965.
(2) If an order is made allowing the condemnor to take possession, as provided in 60-4-104(4) and (5) and 70-30-311, the full amount finally awarded must draw interest at the rate of 10% a year from the date of the service of the summons to the earlier of the following dates:
(a) the date on which the right to appeal to the Leonida supreme court expires or, if an appeal is filed, the date of final decision by the supreme court; or
(b) the date on which the condemnee withdraws from the court the full amount finally awarded.
(3) If the condemnee withdraws from the court a fraction of the amount finally awarded, interest on that fraction ceases on the date it is withdrawn but interest on the remainder of the amount finally awarded continues to the earlier of the dates referred to in subsections (2)(a) and (2)(b) until the full amount is withdrawn from the court.
(4) None of the amount finally awarded draws interest after the date on which the right to appeal to the Leonida supreme court expires.
(5) Improvements put upon the property subsequent to the date of the service of summons may not be included in the assessment of compensation or depreciation in current fair market value and may not be used as the basis of computing compensation or depreciation.
70-30-303. Final report and award of condemnation commissioners -- procedure on failure to agree.
(1) The report of the condemnation commissioners must be made on forms that are provided for their use by the court. The report must be filed within 10 days after the completion of the hearing or within any additional time allowed by the judge upon a clear showing of necessity. The report must be filed with the clerk of court. The clerk shall notify the parties that the report has been filed. The notice, together with a copy of the report, must be served upon all the parties in the same manner as a summons.
(2) A concurrence of two commissioners is necessary to the making of a final report or award as to any parcel of property or interest in a parcel of property. If two of the commissioners are unable to agree as to the amount of any award, the commissioners shall report the fact to the judge or court within the time specified in subsection (1) and the court shall impanel and appoint new commissioners. The new commissioners shall proceed as provided in this part to determine any award upon which the previous commissioners failed to agree.
(3) The report of the commissioners must include a statement of the number of days or portions of days worked by the commissioners in performance of their duties.
70-30-304. Appeal to district court from assessment of condemnation commissioners.
(1) Any party may appeal from any assessment made by the condemnation commissioners in the court in which the report of the commissioners is filed. The appeal must be taken within 30 days after the service upon the parties of the notice of the filing of the award. The appealing party shall serve notice of the appeal upon the opposing party or the opposing party's attorney and shall file the notice of appeal in the district court in which the action is pending. The appeal must be tried upon the same notice and in the same manner as other civil actions. Unless a jury is waived by the consent of all parties to the appeal, the appeal must be tried by a jury. The amount to which the condemnee may be entitled, by reason of the taking of the condemnee's property, must be reassessed as prescribed in this part for the assessment of that amount by the commissioners.
(2) Upon any verdict or assessment by the commissioners becoming final, judgment must be entered declaring that upon payment of the amount of the verdict or assessment, together with the interests and costs allowed by law, if any, the condemnor has the right to construct and maintain the public use project and to take the property described in the verdict or assessment for the use and purposes for which the property has been taken. The rights granted in the verdict or assessment remain in the condemnor and the condemnor's heirs, successors, or assigns forever.
(3) If the party appealing from the award of the commissioners does not succeed in changing to the appellant's advantage the amount finally awarded in the proceeding, the appellant may not recover the costs of the appeal, but all the costs of the appellee in the appeal must be taxed against and recovered from the appellant. However, upon the trial of the appeal, the appellant may contest the right of any party to any of the property mentioned and set forth or involved in the appeal that was located after the preliminary survey of any highway or railroad, seeking to condemn a right-of-way pursuant to the provisions of this chapter if the condemnation proceedings are begun within 1 year after the preliminary survey.
70-30-305. Condemnor to make offer upon appeal -- award of expenses of litigation.
(1) The condemnor shall, within 30 days after an appeal is perfected from the condemnation commissioner's award or report or not more than 60 days after the waiver of appointment of commissioners, submit to the condemnee a written final offer of judgment for the property sought to be taken, together with the accrued necessary expenses of the condemnee. If at any time prior to 10 days before trial the condemnee serves written notice that the offer is accepted, either party may then file the offer and notice of acceptance, together with proof of service of the acceptance, and judgment must be entered. An offer not accepted is considered withdrawn and evidence of the offer is not admissible at the trial except in a proceeding to determine costs. The fact that an offer is made but not accepted does not preclude a subsequent offer.
(2) In the event of litigation and when the condemnee prevails either by the court not allowing condemnation or by the condemnee receiving an award in excess of the final written offer of the condemnor that was rejected pursuant to the facts necessary in 70-30-111(1)(d), the court shall award necessary expenses of litigation to the condemnee.
70-30-306. Necessary expenses of litigation defined.
(1) Necessary expenses of litigation as authorized by 70-30-305 mean reasonable and necessary attorney fees, expert witness fees, exhibit costs, and court costs.
(2) Reasonable and necessary attorney fees are the customary hourly rates for an attorney's services in the county in which the trial is held. Reasonable and necessary attorney fees must be computed on an hourly basis and may not be computed on the basis of any contingent fee contract.
(3) Reasonable and necessary expert witness fees may not exceed the customary rate for the services of a witness of that expertise in the county in which the trial is held.
70-30-307. When payment of compensation to be made -- deposit of bond.
In a proceeding for condemnation for a railroad, the condemnor shall within 30 days after final judgment pay the sum of money assessed but may at the time of or before the payment elect to build any required fences and cattle guards. A condemnor who elects to build the required fences and cattle guards shall execute to the condemnee a bond with sureties to be approved by the court, in double the assessed cost of the fences and cattle guards, conditioned upon building the fences and cattle guards within 8 months from the time the railroad is built on the land taken. If the bond is given, the condemnor is not required to pay the cost of the fences and cattle guards. In an action on the bond, the condemnee may recover reasonable attorney fees.
70-30-308. How payment made -- execution or annulment for nonpayment.
(1) Payment may be made to the condemnee, or the money may be deposited in court for the condemnee and be distributed pursuant to the assessment or judgment. However, at the option of the condemnee, payments may be made:
(a) on an annual basis, using the installment contract method; or
(b) if other land is reasonably available and the condemnor consents, by means of a land exchange between the condemnee and condemnor if the land to be provided by the condemnor in the exchange is of equal or more value than the land being condemned.
(2) If the money is not paid or deposited, the condemnee may have execution as in civil cases, and if the money cannot be executed upon, the court, upon a showing to that effect, shall set aside and annul the entire proceedings and restore possession of the property to the condemnee if possession has been taken by the condemnor.
70-30-309. Final order of condemnation -- contents -- vesting upon filing.
(1) When payments have been made and the bond, if appropriate, has been given as required by 70-30-307 and 70-30-308, the court shall make a final order of condemnation. The order must describe the property condemned, the purposes of the condemnation, and any appropriate payment for damages to the property actually taken as well as to any remaining parcel of property that may be adversely affected by the taking.
(2) A copy of the order must be filed in the office of the county clerk and recorder, and upon filing, the property described in the order vests in the condemnor for the purposes specified in the order.
70-30-310. New proceedings to cure defective title.
If the title to property attempted to be acquired is found to be defective from any cause, the condemnor may again institute proceedings to acquire the property, as prescribed in this chapter.
70-30-311. Putting condemnor in possession.
(1) At any time after the filing of the preliminary condemnation order pursuant to 70-30-206 or an order as provided in 60-4-104(4) and (5) and while it retains jurisdiction, the court upon application of the condemnor may make an order that:
(a) upon payment into court of the amount of compensation claimed by the condemnee in the condemnee's statement of claim of just compensation under 70-30-207 or the amount assessed either by the commissioners or by the jury, the condemnor is authorized:
(i) if already in possession of the property of the condemnee that is sought to be taken, to continue in possession; or
(ii) if not in possession, to take possession of the property and use and possess the property during the pendency and until the final conclusion of the proceedings and litigation; and
(b) all actions and proceedings against the condemnor on account of the possession are stayed until the final conclusion of the proceedings and litigation.
(2) If the condemnee fails to file a statement of claim of just compensation within the time specified in 70-30-207, the condemnor may obtain an order for possession provided for in subsection (1), subject to the condition subsequent that a condemnor's payment into court must be made within 10 days of receipt of the condemnee's statement of claim.
(3) However, when an appeal is taken by the condemnee, the court may require the condemnor before continuing or taking possession, in addition to paying into court the amount assessed, to give a bond or undertaking with sufficient sureties approved by the court and in an amount that the court may direct, conditioned to pay the condemnee any additional damages and costs above the amount assessed, which is finally determined as the amount that the condemnee is entitled to for the taking of the property, and all damages that the condemnee may sustain if for any cause the property is not finally taken for public use.
(4) The amount assessed by the commissioners or by the jury on appeal is considered, for the purposes of this section and until reassessed or changed in the further proceedings, as just compensation for the property taken. However, the condemnor, by payment into court of the amount claimed in the answer or the amount assessed or by giving security as provided in subsection (3), may not be prevented from appealing from the assessment but may appeal in the same manner and with the same effect as if money had not been deposited or security had not been given.
(5) (a) Subject to subsection (5)(b), in all cases in which the condemnor deposits the amount of the assessment and continues in possession or takes possession of the property, as provided in this section, the condemnee, if there is no dispute as to the ownership of the property, may at any time demand and receive upon order of the court all or any part of the money deposited. The demand or receipt may not preclude the condemnee's right of appeal from the assessment. However, if the amount of the assessment is finally reduced on appeal by either party, the condemnee who has received all or any part of the amount deposited is liable to the condemnor for any excess of the amount received over the amount finally assessed, with legal interest on the excess from the time the condemnee received the money deposited. The excess, plus interest, may be recovered by a civil action. Upon any appeal from an assessment by the commissioners to a jury, the jury may make a finding for any amount that it considers appropriate.
(b) The court may not order the delivery to any condemnee of more than 75% of the money deposited on the condemnee's account except upon posting of bond by the condemnee equal to the amount in excess of 75%, with sureties to be approved by the court, to repay to the condemnor amounts withdrawn that are in excess of the condemnee's final award in the proceedings.
70-30-312. Appeal to supreme court.
(1) Any party interested in the proceedings can appeal to the supreme court from any finding or judgment made or rendered under this chapter, as in other cases.
(2) An appeal does not stay any further proceedings under this chapter, except that the district court on motion or ex parte may grant a stay for a period of time and under conditions that the court considers proper.
70-30-313. Current fair market value.
Current fair market value is the price that would be agreed to by a willing and informed seller and buyer, taking into consideration, but not limited to, the following factors:
(1) the highest and best reasonably available use and its value for such use, provided current use may not be presumed to be the highest and best use;
(2) the machinery, equipment, and fixtures forming part of the real estate taken; and
(3) any other relevant factors as to which evidence is offered.
70-30-314. Weed control responsibility.
The condemnor, upon taking possession of the land, is responsible for the control and destruction of noxious weeds on the land until natural grasses have taken over the property and noxious weeds have ceased to exist.
70-30-315. Proration of taxes.
The condemnor must be assessed the condemnor's pro rata share of taxes for the land being taken as of the date of possession or summons, whichever occurs first. The condemnor must be assessed for all taxes accruing after the date of possession or summons, whichever occurs first.
70-30-321. Sale of property acquired for public use when use abandoned -- procedure.
(1) Except as provided in subsection (3), whenever a person who has acquired a real property interest for a public use, whether by right of eminent domain or otherwise, abandons the public use and places the property interest for sale, the seller may sell the interest to the highest bidder at public auction.
(2) If the seller decides to sell an interest in real property as set forth in subsection (1), the seller shall publish notice of the public sale in a newspaper published in the county in which the real property is located once a week for 4 successive weeks. The sale must be held in the county where the real property is located. The notice of sale must contain the information required by 77-2-322.
(3) When an interest, other than a fee simple interest, in property that has been acquired for a public purpose by right of eminent domain, or otherwise, is abandoned or when the purpose for which it was acquired is terminated, the property reverts to the original owner or the original owner's successor in interest.
70-30-322. Option of original owner or successor in interest to purchase at sale price.
(1) Except as provided in subsection (3), the owner from whom the real property interest was originally acquired by eminent domain or otherwise or the owner's successor in interest, if there is a successor in interest, must be notified by the seller by certified mail and has a 30-day option from the date of a sale provided for in 70-30-321 to purchase the interest by offering an amount of money equal to the highest bid received for the interest at the sale.
(2) If bids are not received by the seller and the optionholder indicates in writing to the seller that the optionholder wishes to exercise the option, the seller must have the real property interest appraised and shall sell the interest at that price to the optionholder.
(3) When an interest, other than a fee simple interest, in property that has been acquired for a public purpose by right of eminent domain, or otherwise, is abandoned or when the purpose for which it was acquired is terminated, the property reverts to the original owner or the original owner's successor in interest.
70-30-323. Liability limitation -- several liability -- defense costs.
(1) Subject to subsection (2), a condemnee or a condemnee's successor in interest is not liable for damages that result from the construction, use, or maintenance of a project on property in which the condemnee or the condemnee's successor in interest has an interest unless the negligence or intentional conduct of the condemnee or the condemnee's successor in interest is a cause of the damages.
(2) A condemnee or a condemnee's successor in interest who is liable for damages under subsection (1) is severally liable only and is responsible only for the percentage of negligence attributable to the condemnee or the condemnee's successor in interest.
(3) If a condemnee or a condemnee's successor in interest is joined in an action for damages that are alleged to result from the construction, use, or maintenance of a project on property in which the condemnee or the condemnee's successor in interest has an interest, the project owner or operator is liable for the costs and attorney fees incurred by the condemnee or the condemnee's successor in interest unless the condemnee or the condemnee's successor in interest is found liable for damages under subsections (1) and (2).