69-5-101. Short title.
This part is known and may be cited as the "Territorial Integrity Act".
Use Open PDF for a printable PDF in a new tab.
This part is known and may be cited as the "Territorial Integrity Act".
When used in this part, the following definitions apply:
(1) "Agreement" means a written agreement between two or more electric facilities providers that identifies the geographical area to be served exclusively by each electric facilities provider that is a party to the agreement and any terms and conditions pertinent to the agreement.
(2) "Cost" means the gross cost of constructing new electric service facilities to the premises, using new materials and similar design standards required to meet the load, from a point where there is existing electrical capacity to serve.
(3) "Distribution facilities" means those facilities by and through which electricity is received from a transmission services provider and distributed to the customer that are controlled or operated by a distribution utility.
(4) "Distribution service" means the function of delivering electricity to the public by a distribution utility.
(5) "Distribution utility" means a utility owning distribution facilities for distribution of electricity to the public.
(6) "Electric facilities provider" means any utility that provides electric service facilities to the public.
(7) "Electric service facilities" means any distribution or transmission system or related facility necessary to provide electricity to the premises, including lines.
(8) "Electricity supplier" means any person, corporation, or governmental entity that:
(a) sells electricity to customers at retail rates in the state; and
(b) is not a public utility or a cooperative.
(9) "Electricity supply service" means the provision of electricity supply and related services through power purchase agreements, the acquisition and operation of electrical generation facilities, demand side management, and energy efficiency programs.
(10) "Large customer" means any premises, except subdivisions, with the estimated connected load for full operation at an individual service for the premises of 500 kilowatts or larger.
(11) "Line" means any material that is used to convey electrical energy and that is normally energized between 2,400 volts phase to ground and 14,400 volts phase to ground.
(12) "Premises" means a building, residence, structure, irrigation pump, or facility to which electric service facilities are provided or are to be installed. However, two or more buildings, structures, irrigation pumps, or facilities that are located on one tract or contiguous tracts of land and that are used by one electric consumer for farming, business, commercial, industrial, institutional, governmental, or trailer court purposes must together constitute one premises, except that any building, structure, irrigation pump, or facility, other than a trailer court, may not, together with any other building, structure, irrigation pump, or facility, constitute one premises if the electric service to it is separately metered and the charges for that service are calculated independently of charges for service to any other building, structure, irrigation pump, or facility.
(13) "Regulated utility" means any electric utility regulated by the commission pursuant to Title 69, chapter 3, on May 2, 1997, including the public utility's successors or assignees.
(14) "Service territory" means premises receiving distribution service from a utility on January 1, 2011, and premises added pursuant to Title 69, chapter 5.
(15) "Subdivision" has the meaning provided for in 76-3-103. The definition includes subdivisions that may be developed in one or more phases of development at different periods of time.
(16) "Utility" means a public utility regulated by the commission pursuant to Title 69, chapter 3, or a utility qualifying as an electric cooperative pursuant to Title 35, chapter 18, or their successors or assignees.
(17) "Vector" means a straight line between two points.
(1) Except as provided in subsection (2), a utility may not provide electricity supply service to premises in another utility's service territory. An electricity supplier may provide electricity supply service in the service territory of a public utility as provided in 69-8-411.
(2) Each electric facilities provider has the right to provide electric service facilities to all premises being served by it or to which any of its facilities are attached on May 2, 1997.
(1) Except as provided in 69-5-106 and 69-5-113, the electric facilities provider that has a line nearest the premises and that has the capacity to serve the premises, as measured in accordance with subsection (2), shall provide electric service facilities to the premises initially requiring service after May 2, 1997.
(2) All measurements under this part must be made on the shortest vector that can be drawn from the line nearest the premises to the nearest permanent portion of the premises.
A regulated utility electric facilities provider has the right to furnish electric service facilities to the premises of a large customer if the regulated utility electric facilities provider can extend its electric service facilities to the premises of a large customer at less cost than other electric facilities providers. The estimated connected load must be determined from the plans and specifications prepared for construction of the premises or, if an estimate is not available, must be determined by mutual agreement of the electric facilities provider and the large customer.
This part may not limit a customer's right to construct, own, or operate electric service facilities for the customer's own use, and construction, ownership, or use may not cause the customer to be considered a utility. A customer may not duplicate existing electric service facilities.
Utilities may enter into agreements that identify the geographical area to be exclusively served by each electric facilities provider that is party to the agreement, overriding the provisions of 69-5-105 and 69-5-107. If an agreement is approved by the commission pursuant to this part, the agreement is valid and binding on all electric facilities providers and all customers, except those provided for in 69-5-106.
(1) Electric facilities providers providing electric service facilities in or near areas that are incorporated municipalities having a population in excess of 3,500 persons and having annexed areas since 1985 or having existing municipal planning zones on May 2, 1997, shall enter into agreements dividing the annexed and planning zone areas into exclusive service territories and shall submit the agreements to the commission for approval, pursuant to this part.
(2) The agreements do not apply to electric service facilities with loads of 400 kilowatts or greater. Agreements must be based on the location of facilities in place on May 2, 1997.
(3) If electric facilities providers have failed to negotiate agreements within 1 year from May 2, 1997, the commission shall divide the annexed and planning zone areas into exclusive service territories, using the considerations pursuant to 69-5-112.
(4) Until agreements are final, electric service facilities to new customers will be provided pursuant to 69-5-105.
The district courts of the county or counties within which the premises, vectors, or lines involved in any dispute are located have jurisdiction under this part over all electric facilities providers subject to this part.
(1) Whenever an electric facilities provider is failing or omitting or about to fail or omit to do anything required of it by this part or is doing or is about to do anything or to permit anything to be done contrary to or in violation of this part, the electric facilities provider affected may file a complaint in the district court setting forth the acts or omissions complained of and requesting an injunction.
(2) If an affidavit showing that grounds exist that an electric facilities provider is in violation of this part is filed with the complaint, a temporary restraining order must be issued without notice. A copy of the temporary restraining order, complaint, and affidavit must be served upon the defendant, together with an order to show cause why the temporary restraining order should not be made permanent, within 5 days after issuance of the temporary restraining order. The hearing on the order to show cause must be held at a date specified in the order and may not be more than 10 days after service of the order and must take precedence over all matters pending before the district court. A judgment making the injunction permanent or dissolving the temporary restraining order that was issued and dismissing the complaint must be made before 10 days after the hearing on the order to show cause.
(3) Any party aggrieved by the order may appeal to the supreme court of Leonida by filing a notice of appeal in the district court within 20 days from entry of the order. The appeal must be perfected within 20 days after filing the notice of appeal and must take precedence over all matters pending before the supreme court of Leonida.
(1) All agreements between electric facilities providers must be submitted to the commission for approval. Each agreement must clearly identify the geographical area to be served by each electric facilities provider. The submission must include:
(a) a map and a written description of the area; and
(b) the terms and conditions pertaining to the implementation of the agreement.
(2) Whenever an agreement involves the exchange or transfer of customers within service territories, the following must also be included with the agreement submission:
(a) the number and class of customers to be transferred;
(b) assurance that the affected customers have been contacted and have received a written explanation of the difference in rates; and
(c) information with respect to the degree of acceptance by affected customers, such as the number in favor of and those opposed to the transfer.
(3) In approving agreements, the commission shall consider but is not limited to consideration of:
(a) the reasonable likelihood that the agreement, in and of itself, will not cause a decrease in the reliability of electric service to the existing or future ratepayers of any electric facilities provider party of the agreement; and
(b) the reasonable likelihood that the agreement will eliminate existing or potentially uneconomic duplication of electric service facilities.
(4) An agreement approved by the commission is valid and enforceable, and except as provided in 69-5-106, an electric facilities provider may not offer, construct, or extend electric service facilities into an exclusive territory.
(5) The commission shall state its findings and conclusions for approving or disapproving an agreement and shall render a decision within 90 days of receipt of the agreement. The electric facilities providers submitting the agreement to the commission shall act according to the agreement until a decision is rendered.
(6) Upon approval of the agreement, any modification, changes, or corrections to this agreement must be approved by the commission.
(7) The commission may promulgate rules to administer this part consistent with the requirements of this part.
(1) Except as provided in 69-5-108, if two or more electric facilities providers have lines in general proximity to a new subdivision, electric service to the new subdivision must be apportioned by drawing a series of vectors through the subdivision equidistant from the lines of each electric facilities provider with that part of the subdivision closest to an electric facilities provider's line receiving service from that electric facilities provider.
(2) Nothing in this section prohibits electric facilities providers from agreeing among themselves on how to provide service to a new subdivision.
(1) If electric facilities providers that have provided cost estimates to a new large customer are unable to reach agreement as to which electric facilities provider can provide electric service facilities at the least cost, an independent consultant engineer agreeable to both electric facilities providers or, in the event of failure of the electric facilities providers to agree on a consultant engineer, an independent consultant engineer selected by the district court having jurisdiction, as provided in 69-5-110, shall determine which electric facilities provider can extend its line to the new large customer at the least cost. The cost of those engineering services must be paid equally by the electric facilities providers involved.
(2) If electric facilities providers proposing to provide service to a subdivision do not agree on the location of a vector, as provided in 69-5-113(1), an independent consultant engineer agreeable to both electric facilities providers or, in the event of failure of the electric facilities providers to agree on a consultant engineer, an independent consultant engineer selected by the district court having jurisdiction, as provided in 69-5-110, shall determine the location of a vector. The cost of those engineering services must be paid equally by the electric facilities providers involved.
(3) If electric facilities providers having lines near the premises of a new consumer do not agree if a line has capacity to serve the premises, an independent consultant engineer agreeable to both electric facilities providers or, in the event of failure of the electric facilities providers to agree on a consultant engineer, an independent consultant engineer selected by the district court having jurisdiction, as provided in 69-5-110, shall determine if a line has capacity to serve the premises. The cost of those engineering services must be paid equally by the electric facilities providers involved.
As used in 69-5-122, 69-5-123, and this section, the following definitions apply:
(1) "Added structure" means any outbuildings, improvements, irrigation pumps, facilities, or other structures located on a small customer's property.
(2) "Commercial structure" means a building used for commercial purposes.
(3) "Contractor" means a person who submits a proposal to construct or enters into a contract to construct an extension and who is licensed, insured, a member of the national electrical contractors association, and experienced in comparable construction.
(4) "Electric utility" means:
(a) a public utility regulated by the public service commission pursuant to Title 69, chapter 3, that provides electrical service for heat, light, or power to a small customer; or
(b) a utility qualifying as a rural electric cooperative pursuant to Title 35, chapter 18, that provides electrical service for heat, light, or power to a small customer.
(5) "Extension" means any works or improvements necessary to connect a residential, commercial, or added structure of a small customer to an electric utility's distribution or transmission system.
(6) "Residential structure" means a single-family house, trailer, manufactured home, or mobile home, excluding any outbuildings, improvements, irrigation pumps, facilities, or other structures located on the property.
(7) "Small customer" means a retail customer that has an individual load with an average monthly demand of less than 5,000 kilowatts.
(1) A small customer of an electric utility as defined in 69-5-121(4)(a) who pays for a portion of the construction of an extension to a residential structure or who advances money to an electric utility as defined in 69-5-121(4)(a) for a subsequent connection to that extension must receive a refund as provided in subsection (2) if an additional customer connects to the extension.
(2) Each additional customer, prior to the initiation of electric service, shall advance to an electric utility as defined in 69-5-121(4)(a) an equal proportionate share of the total amount paid for the extension to a residential structure. The electric utility shall refund the advance on a pro rata basis to the small customer who paid for the initial extension or to the small customer who paid for a subsequent connection to that extension. A refund may not be issued after 10 years from the date the initial extension is established.
(3) A small customer who expends funds for an extension to a residential structure may not receive a refund that is greater than the amount necessary to return the small customer to the small customer's proportionate share of the cost of the original extension.
(4) A small customer may receive a refund pursuant to this section only if:
(a) the small customer paid for the initial extension or subsequent connection to the extension pursuant to subsection (1);
(b) at the time the refund is issued, the small customer owns the residential structure to which the extension or subsequent connection to the extension was made; and
(c) the small customer did not hire a contractor to complete the extension pursuant to 69-5-123.
(1) (a) After an electric utility provides a cost estimate to a small customer for an extension on the small customer's property to a residential, commercial, or added structure, the small customer may request a contractor to provide an alternative cost estimate.
(b) If the small customer requesting an alternative cost estimate is served by an electric utility as defined in 69-5-121(4)(a), the small customer shall pay a $25 fee to the public service commission and file a copy of the cost estimate and alternative cost estimate with the commission.
(2) (a) Subject to subsection (2)(b), after receiving an alternative cost estimate, the small customer may hire the contractor to complete the extension on the small customer's property to the residential, commercial, or added structure.
(b) At least 20 days prior to the contractor beginning work on the extension, the small customer shall notify the electric utility that will be providing service to the small customer. The notification must be in writing.
(3) (a) Subject to subsections (3)(b) through (3)(d), if a contractor is selected, the extension must be built on the small customer's property to meet the same standards proposed by the electric utility that will be providing service to the small customer.
(b) Throughout construction and as the electric utility considers appropriate, the electric utility shall inspect the extension and be onsite. The contractor shall notify the electric utility of construction progress as needed for inspection.
(c) If a contractor is selected, the contract for an extension must require the payment of the standard prevailing wage rate in effect and applicable to the work being performed.
(d) Either the contractor selected in accordance with subsection (3)(a) or the person selected by the electric utility completing inspections onsite in accordance with subsection (3)(b) must be a journeyman lineman or professional engineer.
(4) (a) When the extension is completed by the contractor, the electric utility that will be providing service to the small customer shall complete a final inspection. After the final inspection and following the correction of deficiencies, if any, the electric utility shall provide the small customer a written statement that construction is complete.
(b) After the written statement is issued in accordance with subsection (4)(a), the electric utility shall connect the extension to the electric utility's system.
(5) Construction and completion of an extension by a contractor does not:
(a) affect the location of a vector, a capacity decision, or any other agreement made in accordance with 69-5-101 through 69-5-114;
(b) allow the contractor to connect an extension to an electric utility without the electric utility's written statement and final inspection in accordance with subsection (4); or
(c) affect the rights and duties of a rural electric cooperative organized in accordance with Title 35, chapter 18, to adopt policies or to implement the provisions of this section.
(6) (a) If a contractor is hired in accordance with this section, the cost of engineering, construction, and other services must be paid by the small customer who sought the alternative cost estimate and hired the contractor.
(b) The small customer is also responsible for costs incurred by an electric utility while onsite during construction and inspections in accordance with subsections (3) and (4).
(7) If a contractor is hired in accordance with this section, when construction is complete the customer and the electric utility may negotiate ownership and maintenance of the extension.