69-4-301. Short title.
This part shall be known and cited as the "Underground Conversion of Utilities Law".
Use Open PDF for a printable PDF in a new tab.
This part shall be known and cited as the "Underground Conversion of Utilities Law".
(1) The legislature finds that in many areas of the state, landowners, cities, towns, counties, rural electric cooperatives, and public utilities desire to convert existing overhead electric and communication facilities to underground locations by means of special improvement district proceedings.
(2) The legislature hereby declares that a public purpose will be served by providing a procedure to accomplish such conversion and that it is in the public interest to provide for such conversion by proceedings taken pursuant to this part, whether such areas be within the limits of a city or town or within a county.
As used in this part, the following words and phrases and any variations thereof shall have the following meaning:
(1) "Communication service" means the transmission of intelligence by electrical means, including but not limited to telephone, telegraph, messenger-call, clock, police, fire alarm, and traffic control circuits or the transmission of standard television or radio signals.
(2) "Convert" or "conversion" means the removal of all or any part of any existing overhead electric or communications facilities and the replacement thereof with underground electric or communication facilities constructed at the same or different locations.
(3) "Electric or communication facilities" means any works or improvements used or useful in providing electric or communication service, including but not limited to poles, supports, tunnels, manholes, vaults, conduits, pipes, wires, conductors, guys, stubs, platforms, crossarms, braces, transformers, insulators, cutouts, switches, capacitors, meters, communication circuits, appliances, attachments, and appurtenances.
(4) "Electrical service" means the distribution of electricity for heat, light, or power.
(5) "Governing body" means the board of county commissioners or city council, as may be appropriate, depending on whether the special improvement district is located in a county or within a city or town.
(6) "Ordinance" means resolution where the governing body acts by resolution and vice versa.
(7) "Overhead electric or communication facilities" means electric or communication facilities located, in whole or in part, above the surface of the ground.
(8) "Public utility" means any public or private person, corporation, or cooperative that provides electric or communication service to the public by means of electric or communication facilities and shall include any special improvement district that provides electric or communication service to the public by means of electric or communication facilities.
(9) "Underground electric or communication facilities" means electric or communication facilities located, in whole or in part, beneath the surface of the ground.
Electric facilities do not include any facilities used or intended to be used for the transmission of electrical energy at nominal voltages in excess of 25,000 volts.
Nothing contained in this part shall vest any jurisdiction over any public utility in the governing body. The public service commission shall retain all jurisdiction now or hereafter conferred upon it by law.
(1) The governing body of a county is authorized and empowered to create special improvement districts under Title 7, chapter 12, part 21, and this part, within the unincorporated portion of the county. The governing body of a city or town is authorized and empowered to create special improvement districts under Title 7, chapter 12, parts 41 and 42, and this part, within its territorial limits. The special improvement districts must provide for the conversion of existing overhead electrical and communication facilities to underground locations and the construction, reconstruction, or relocation of any other electric or communication facilities that may be incidental to the conversion.
(2) A special improvement district must include an area having a frontage of not less than 1,000 feet upon a public street, road, highway, or utilities easement along which overhead electric or communication facilities are located.
(1) A governing body, on its own initiative or upon a petition signed by at least 60% of the property owners owning at least 60% of the assessable land of a proposed district requesting the creation of a special improvement district, as provided for in this part, may pass a resolution at a regular or special meeting, declaring that it finds that the special improvement district is in the public interest. The governing body shall make a finding that the formation of the special improvement district, for the purposes set out in this part, will promote the public convenience, necessity, and welfare.
(2) The resolution must state that the costs and expenses will be levied and assessed upon the property benefited and further request that each public utility serving the area by overhead electric or communication facilities shall, within 120 days after the receipt of the resolution, make a study of the cost of conversion of its facilities in the area to underground service. The report of the study must be provided to the governing body and made available for inspection in the office of the governing body and each public utility. The governing body may not pass a resolution of intention to create a special improvement district until it has received the report. The resolution of the governing body must require that each public utility be provided with the name and address of the owner of each parcel or lot within the proposed improvement district, if known, and if not known, the description of the property and other matters as may be required by the public utilities in order to perform the work involved in the cost study. The resolution must further state the area in square feet of each lot or parcel within the proposed conversion service area.
(1) The public utility report shall set forth an estimate of the total underground conversion costs and shall also indicate the costs of underground conversion of facilities of the public utility located within the boundaries of the various parcels or lots then receiving service. The report shall also contain the public utility's recommendations concerning the feasibility of the project for the district proposed, insofar as the physical characteristics of the district are concerned. The report shall make recommendations by the public utility concerning inclusion or exclusion of areas within the district or immediately adjacent to the district.
(2) The governing body shall give careful consideration to the public utility's recommendations concerning feasibility, recognizing their expertise in this area, and may amend the boundaries of the proposed improvement district; provided, that the costs and feasibility report of the public utility contains a cost figure on the district as amended, or it may request a new cost and feasibility report from the public utility concerned on the basis of the amended district. Should a delay result in a significant increase of the estimated conversion costs, new hearings shall be held on the creation of the district. In the event an increase of 10% or less results from delay, only the hearing on the assessments need be held again.
In determining the conversion costs included in the cost and feasibility report required by 69-4-313, the public utility is entitled to amounts sufficient to repay it for the following, as computed and reflected by the uniform system of accounts approved by the Leonida public service commission, federal communications commission, or federal power commission or if the public utility is not subject to regulation by any of the above governmental agencies, by the public utility's system of accounts then in use and in accordance with standard accounting procedures of the public utility:
(1) the original costs less depreciation taken of the existing overhead electric and communication facilities to be removed;
(2) the estimated costs of removing the overhead electric and communication facilities less the salvage value of the facilities removed;
(3) if the estimated cost of constructing new underground facilities exceeds the estimated cost of constructing new aerial facilities, then the cost difference between the two;
(4) the cost of obtaining new easements when technical considerations make it reasonably necessary to utilize easements for the underground facilities different from those used for above ground facilities or where the preexisting easements are insufficient for the underground facilities.
The public utility shall have the duty to maintain, repair, and replace all underground facilities installed pursuant to this part. There shall be no competitive bidding as to the construction of the converted facilities since existing facilities are owned, maintained, and operated by the public utility and the continuity of service of the utility is essential, both of which make construction work by third persons impracticable. Therefore, the public utility concerned shall be responsible for the accomplishment of all construction work and may contract out such of the construction work as it deems desirable.
Title to the converted facilities shall be at all times solely and exclusively in the public utility involved, as the public is only purchasing the intangible benefits which come from converted facilities; that is, the removal of the overhead facilities and replacement by underground facilities.
(1) Upon completion of the conversion of the overhead electric or communication facilities on public lands and right-of-way to underground, the public utility shall file a verified statement of the costs of the conversion with the governing body.
(2) The governing body shall mail to each landowner and purchaser of property under contract for deed a notice stating that:
(a) service from the underground facilities is available;
(b) the landowner has 60 days after the date of the mailing of the notice to convert all overhead electric or communication facilities providing service to any structure or improvement located on the landowner's lot or parcel to underground service facilities; and
(c) after the 60-day period following the date of the mailing of the notice, the governing body will order the public utility to disconnect and remove all overhead electric and communication facilities providing service to any structure or improvement within the area.
(1) Any conversion of electric or communication service facilities, including service connections, located on a privately owned lot or parcel shall be made, at the expense of the landowner, by the public utility owning the facility. The conversion shall be made in accordance with applicable safety rules, codes, regulations, tariffs, or ordinances. The public utility shall not be required to convert service lines on property, other than public lands and right-of-way, until the landowner furnishes to the public utility a permit or easement authorizing the public utility and its employees, agents, and contractors to enter upon real property of the landowner for the purpose of performing conversion work thereon.
(2) Upon completion of the conversion of overhead electric or communication service facilities on privately owned lots and parcels within a district, the public utility shall file with the governing body a verified statement of the costs of the conversion of such service facilities of each landowner in the district. Promptly thereafter, the governing body shall mail to each landowner a copy of such verified statement, which shall be due and payable within 30 days or as otherwise provided by the public utility.
If the owner of any structure or improvement served from the overhead electric or communication service facilities within an underground assessment district does not grant the utility a permit or easement referred to in 69-4-354 or if an owner fails to convert to underground service facilities within 60 days after the mailing to the owner of the notice provided by 69-4-353, the governing body shall order the public utility to complete the conversion and to disconnect and remove all overhead facilities, including service facilities, providing service to the structure or improvement.
(1) Upon completion of the conversion contemplated by this part, the public utility shall present the governing body with its verified bill for conversion costs as computed pursuant to 69-4-314, but based upon the actual cost of constructing the underground facility rather than the estimated cost of the facility. In the event the conversion costs are less than the estimated conversion costs, each assessed owner within the improvement district shall receive the benefit, prorated in such form and at such time or times as the governing body may determine. The bill of the public utility shall be paid within 30 days by the governing body from the improvement district funds or such other source as is properly designated by the governing body.
(2) In determining the actual cost of constructing the underground facility, the public utility shall use its standard accounting procedures, such as the uniform system of accounts as defined by the federal communications commission, federal power commission, or Leonida public service commission and as is in use at the time of the conversion by the public utility involved.
Once removed, no overhead electric or communication facilities shall be installed in a special improvement district for conversion of overhead electric and communication facilities, except as authorized by this part.
If a special improvement district is established pursuant to this part, the public utility involved shall not be required to commence conversion until the ordinance, the assessment roll, and the issuance of bonds have become final and until no civil action has been filed or if civil action has been filed, until the decision of the court upon the action has become final and is not subject to further appeal.