TITLE 69. Public Utilities And Carriers
CHAPTER 4. Utility Lines And Facilities
Part 10. Requirements for Use of Advanced Metering Devices
Part 10. Requirements for Use of Advanced Metering Devices
69-4-1001. Definitions.
As used in this part, unless the context requires otherwise, the following definitions apply:
(1) "Advanced metering gateway device" means any electric utility meter component or device ancillary to the electric utility meter that is located at an end-user's residence or business and is equipped and programmed to communicate with electrical appliances, electrical equipment, or electrical devices within the end-user's residence or business or that is capable of estimating and recording electrical energy usage by types of appliances, electrical equipment, or electrical devices.
(2) "Advanced metering device" or "advanced meter" means a meter or metering device that is owned or leased by a utility or the utility's agent and that:
(a) measures, records, or sends a customer's utility usage or other data by use of radio waves or internet technology; and
(b) allows for two-way communication between the meter and the utility or its agent.
(3) "Utility" means a public utility regulated by the public service commission pursuant to Title 69, chapter 3.
69-4-1002. Meter security -- data disclosure.
(1) Except as provided in subsections (3) and (4), a customer's energy use data is private and confidential and may not be disclosed by a utility, except as specifically required in subsection (3) or (4) or otherwise provided by law.
(2) Energy use data from an advanced metering device must be sufficiently secured so that the data cannot be intercepted by a person other than a utility.
(3) A utility may disclose aggregated energy use data that is anonymous.
(4) A utility shall make energy use data collected from an advanced metering device available to a customer or to a customer's designee upon request of the customer.
69-4-1003. Advanced metering devices -- notice required.
(1) A utility shall:
(a) notify a customer in writing at least 60 days prior to installation of an advanced metering device at the customer's address; and
(b) provide a sample copy of the notice to the public service commission and a list of customers who have been provided notice.
(2) The notice provided in accordance with subsection (1) must:
(a) be sent by first-class mail to a customer's address and be separate from any billing mailing;
(b) clearly state the utility's intent to install an advanced metering device; and
(c) if determined to be a requirement by the public service commission, include the process and financial obligations for a customer to opt out of installation of an advanced metering device.
69-4-1004. Opt-out program -- public service commission responsibilities -- rulemaking.
(1) On or before July 1, 2022, the public service commission shall determine whether an opt-out program for advanced meters or advanced metering gateway devices, or both, should be established.
(2) In determining whether to establish an opt-out program, the commission shall consider:
(a) an individual customer's privacy interest;
(b) costs and practicality of allowing customers to opt out;
(c) availability of other technology; and
(d) other concerns related to advanced metering devices and advanced metering gateway devices.
(3) If the commission determines an opt-out program should be established, the commission shall adopt rules providing options and requirements for individual customers to opt out of advanced metering device or advanced metering gateway device installation.
69-4-1005. Advanced metering gateway device opt-in provisions -- rulemaking.
(1) A utility may allow customers to opt-in to the installation of all advanced metering gateway devices located at an end user's residence or business.
(2) A utility may charge customers who opt in to advanced metering gateway device installation additional fees or charges related to the installation.
(3) If the commission determines an opt in program should be established, the commission shall adopt rules providing options, requirements, and a process for determination of fees or charges for individual customers to opt in to advanced metering gateway device installation.
(4) Utilities seeking to allow an advanced metering gateway device opt-in program shall file a report detailing the program requirements and process for determining fees or charges with the commission along with a $25 filing fee.