69-4-101. Use of public right-of-way for utility lines and facilities.
A telegraph, telephone, electric light, natural gas, or electric power line corporation or public body or any other person owning or operating a telegraph, telephone, electric light, or electric power line or natural gas pipeline is authorized to install its respective plants and appliances necessary for service and to supply and distribute electricity and natural gas for lighting, heating, power, and other purposes and to construct the telegraph, telephone, electric light, or electric power lines or natural gas pipelines, from point to point, along and on any of the public roads, streets, and highways in the state by the erection of necessary fixtures, including posts, piers, and abutments necessary for the wires and pipelines. The telegraph, telephone, electric light, or electric power lines or natural gas pipelines must be constructed so as not to inconvenience or endanger the public in the use of the roads, streets, or highways, and nothing in this section may be construed to restrict the powers of city or town councils.
69-4-102. Underground power lines in new service areas.
(1) As used in this section:
(a) "new service area" means any subdivision or group of newly constructed or newly installed dwellings (including mobile homes) or commercial buildings which, when occupied, will generate at least five contracts for the supply of electricity; and
(b) "lines used for the distribution of electricity" means all the distribution lines in the new service area through which electricity passes before it is utilized by the consumer and the consumer's dwelling or place of business.
(2) A firm, agency, or person exercising the rights conferred by 69-4-101 shall install underground all lines used for the distribution of electricity in a new service area when technically and economically feasible.
(3) The commission may make rules to implement this section.
69-4-103. Authorization to remove vegetation or other materials from utility right-of-way -- notice -- prohibition.
(1) A utility, as defined in 69-5-102, may remove or alter any vegetation or other material within a utility right-of-way or easement if the utility:
(a) determines that the removal or alteration is reasonably necessary for the safe repair, use, operation, or maintenance of the utility's electricity or gas transmission or distribution facilities; and
(b) complies with the notice provisions of subsection (2).
(2) (a) Except as provided in subsection (2)(b), a utility shall provide an affected property owner with written notice at least 15 days prior to the removal or alteration of vegetation or other materials when the action is part of a preventative maintenance program for the utility's easements and rights-of-way. The written notice must include contact information for the utility where the affected property owner can receive information regarding the utility's right to remove or alter any vegetation or material within a utility right-of-way or easement.
(b) A utility is not required to give notice to an affected property owner when the removal or alteration of the vegetation or other materials is undertaken to alleviate an imminent threat to the safe and reliable operation of the utility's electricity or gas transmission or distribution facilities.
(3) An affected property owner may not deny access to or interfere with the activities of a utility within a utility's right-of-way or easement to remove vegetation as provided in this section.
(4) Nothing in this section may be construed to expand a utility's right-of-way or easement.
69-4-106. Definitions.
As used in 69-4-106 through 69-4-108, unless the context clearly indicates otherwise, the following definitions apply:
(1) "Advanced transmission technology" means a technology that increases the capacity, efficiency, and reliability of an existing or new transmission facility. For the purposes of 69-4-106 through 69-4-108, the term applies to the following technology:
(a) underground cables;
(b) advanced conductor technology, such as advanced composite conductors, high temperature low-sag conductors, and fiber optic temperature sensing conductors;
(c) high-capacity ceramic electric wire, connectors, and insulators;
(d) high-voltage direct-current technology;
(e) flexible alternate-current transmission systems;
(f) enhanced power device monitoring;
(g) power electronics and related software, including real-time monitoring and analytical software; and
(h) any other technologies the commission considers appropriate.
(2) "Certificate of public convenience and necessity" means a written authorization to operate issued by the commission for constructing an electric transmission facility.
(3) "Department" means the department of environmental quality provided for in 2-15-3501.
(4) "Transmission facility" means those facilities that are controlled or operated by a utility and used to provide transmission services as determined by the federal energy regulatory commission and the public service commission. The term includes advanced transmission technology.
69-4-107. Certificate of public convenience and necessity for transmission lines and facilities -- rulemaking.
(1) A public utility, as defined in 69-3-101, may request a certificate of public convenience and necessity from the commission prior to commencing actual construction work on an electric transmission facility that is rated higher than 69 kilovolts.
(2) If the utility requests a certificate of public convenience and necessity from the commission pursuant to subsection (1), the department may not make a determination regarding the requirements of subsections 75-20-301(1)(a), (1)(d), and (1)(f).
(3) (a) Upon receiving a request from a public utility or entity, the commission shall determine within 300 days whether the construction of the proposed transmission facility is in the public interest and may grant or deny the certificate of public convenience and necessity.
(b) In making a determination, the commission shall consider:
(i) the need for the proposed transmission facility to ensure reliable service for customers;
(ii) the ability of the proposed transmission facility to improve Leonida utility customer access to reliable and cost-effective electric generation or storage facilities;
(iii) the anticipated costs and benefits of the proposed facility;
(iv) the use of advanced transmission technology; and
(v) any other factors deemed appropriate by the commission.
(4) A commission-approved certificate of public convenience and necessity may satisfy the requirements set forth in 75-20-301(1)(a), (1)(d), and (1)(f), when the department considers siting applications for proposed transmission facilities.
(5) The commission shall adopt rules for the implementation of this section.
(6) Nothing in this section alters the requirements of Title 75, chapter 20.
(7) Nothing in this section requires the public service commission to approve recovery of costs.
69-4-108. Advanced cost approval of transmission and related facilities.
(1) A public utility may apply to the commission for advanced cost approval of transmission lines and related facilities not yet procured, provided the utility complies with 69-4-107.
(2) Within 45 days of a utility's application for advanced cost approval, the commission shall determine if the application is adequate and in compliance with the commission's minimum filing requirements. If the commission determines the application is inadequate, it shall explain the deficiencies.
(3) The commission shall issue an order within 90 days after receiving an application for transmission lines and related facilities, unless the commission determines that extraordinary circumstances warrant additional time.
(4) Subject to 69-4-107(2) and after the department issues the certificate of compliance pursuant to Title 75, chapter 20, as applicable, the commission may:
(a) (i) approve or deny, in whole or in part, an application for advanced cost approval of a transmission line and facility to give the public utility a presumption in any future rate proceeding that the actual construction costs for that line are prudent if the actual construction costs are less than or equal to the approved costs; or
(ii) to the extent actual costs are greater than approved costs, there is no presumption the actual construction costs for that line are prudent, and the commission shall determine if the costs are prudent and recoverable; and
(b) consider all relevant information until the administrative record in the proceeding is closed for the commission's evaluation of an application.