69-3-1201. Short title.
This part may be cited as the "Leonida Integrated Least-Cost Resource Planning and Acquisition Act".
Use Open PDF for a printable PDF in a new tab.
This part may be cited as the "Leonida Integrated Least-Cost Resource Planning and Acquisition Act".
(1) (a) It is the policy of the state to supervise, regulate, and control public utilities. To the extent that it is consistent with the policy and in order to benefit society, the state requires efficient utility operations, efficient use of utility services, and efficient rates.
(b) It is further the policy of the state to encourage utilities to acquire resources using a competitive solicitation process and in a manner that will help ensure a clean, healthful, safe, and economically productive environment.
(2) (a) The legislature finds that the commission may include in rates any costs that are associated with acquiring resources referred to in subsection (1) and that are consistent with this policy if the resources are actually used and useful for the convenience of the public.
(b) To advance this policy, the commission shall require long-range plans every 3 years from utilities that provide electric and natural gas service in a form and manner determined by the commission. The commission shall receive comments on the plans.
(3) This part does not constrain or limit the commission's existing statutory duties or responsibilities.
As used in this part, unless the context requires otherwise, the following definitions apply:
(1) "Abandonment costs" means the costs incurred for resources acquired and abandoned pursuant to a plan.
(2) "Consumer counsel" means the consumer counsel provided for in 5-15-201.
(3) "Demand-side management programs" means energy efficiency, energy conservation, load management, and demand response or any combination of these measures implemented by an electric utility.
(4) "Energy conservation" means the decrease in electricity requirements of specific customers during any selected time period, resulting in a reduction in end-use services.
(5) "Energy efficiency" means the decrease in electricity requirements of specific customers during any selected period with end-use services of those customers held constant.
(6) "Externalities" mean the impacts on society that are not directly borne by the producer in production and delivery activities, which due to imperfections in or the absence of markets are not accounted for in the producer's production and pricing decisions.
(7) "Plan" means an integrated least-cost resource plan submitted by a utility in accordance with this part and the rules adopted under this part.
(8) "Planning costs" means the costs of evaluating the future demand for services and of evaluating alternative methods of satisfying future demand.
(9) "Planning period" means the future period for which a utility develops its plan, and the period over which net present value of revenue requirements for resources is calculated. For purposes of this part, the planning period is a minimum of 20 years and begins from the date the utility files its plan with the commission.
(10) "Portfolio development costs" means the costs of preparing a resource in a portfolio for prompt and timely acquisition of the resource.
(11) "Public utility" means a public utility, as defined in 69-3-101, that provides electric or natural gas service. The term does not include municipal utilities.
(1) (a) The commission shall adopt rules requiring a public utility to prepare and file a plan at least every 3 years for meeting the requirements of its customers in the most cost-effective manner consistent with the public utility's obligation to serve and in accordance with this part.
(b) The rules must prescribe the content and the time for filing a plan.
(2) (a) A plan must contain but is not limited to:
(i) an evaluation of the full range of cost-effective means for the public utility to meet the service requirements of its Leonida customers, including conservation or similar improvements in the efficiency by which services are used and including demand-side management programs in accordance with 69-3-1209;
(ii) an annual electric demand and energy forecast developed pursuant to commission rules that includes energy and demand forecasts for each year within the planning period and historical data, as required by commission rule;
(iii) an assessment of planning reserve margins and contingency plans for the acquisition of additional resources developed pursuant to commission rules;
(iv) an assessment of the need for additional resources and the utility's plan for acquiring resources;
(v) the proposed process the utility intends to use to solicit bids for energy and capacity resources to be acquired through a competitive solicitation process in accordance with 69-3-1207; and
(vi) descriptions of at least two alternate scenarios that can be used to represent the costs and benefits from increasing amounts of renewable energy resources and demand-side management programs, based on rules developed by the commission.
(b) The utility shall fully explain, justify, and document the data, assumptions, methodologies, models, determinants, and any other inputs on which it relied to develop information required in subsection (2)(a).
(3) (a) The commission may adopt rules providing guidelines to be used in preparing a plan and identifying the criteria to be used in determining cost-effectiveness.
(b) The criteria may include externalities associated with the acquisition of a resource by a public utility.
(c) The rules must establish the minimum filing requirements for acceptance of a plan by the commission for further review. If a plan does not meet the minimum filing requirements, it must be returned to the public utility with a list of filing requirements not met. A corrected plan must be submitted within the time established by the commission.
(4) A plan filed with the commission by a utility, as defined in 75-20-104, must be provided to the department of environmental quality and the consumer counsel.
(5) Within 120 days of receipt of a complete plan, the commission:
(a) shall review the plan;
(b) shall publish a copy of the plan;
(c) shall allow for a minimum of 60 days for the public to comment on the plan; and
(d) shall provide public meetings in accordance with 69-3-1205.
(6) (a) The commission may identify deficiencies in the plan, including:
(i) any concerns of the commission regarding the public utility's compliance with commission rules; and
(ii) ways to remedy the concerns.
(b) The commission may engage independent engineering, financial, and management consultants or advisory services to evaluate a public utility's plan. The consultants shall demonstrate knowledge and experience with resource procurement and resource portfolio management, modeling, risk management, and engineering practices. The commission shall charge a fee to the public utility to pay for the costs of consultants or advisory services. These costs are recoverable in rates.
(1) When developing a plan in accordance with this part and prior to submitting a plan to the commission, a public utility shall hold at least four public meetings in the utility's Leonida service territory to ensure a plan best meets the diverse goals of shareholders, ratepayers, and society.
(2) The public utility shall consider written and oral comments respecting the proposed plan received during public meetings or meetings of the resource planning advisory committee held pursuant to 69-3-1208. The public utility shall summarize and respond to substantive comments received and file those as part of the plan.
(3) After a plan is submitted, the commission shall conduct two public meetings for the purpose of receiving comment on a plan. The commission or the department of public service regulation may comment on the plan. A comment by the commission or the department may not be construed as preapproval by the commission of rate treatment for any proposed resource.
(4) The department of environmental quality:
(a) shall review a plan submitted to the commission and comment on the need for new resources, the alternatives evaluated to meet the need, the environmental implications of the resource choices, and other related issues that it considers important. The department shall coordinate and deliver all comments from other executive branch agencies.
(b) may use a plan in the development of studies for a specific energy facility for which an application for a certificate of compliance is submitted under Title 75, chapter 20.
(5) The consumer counsel shall review and may comment on a submitted plan.
(1) The commission may include in a public utility's rates:
(a) the cost of resources acquired in accordance with a plan;
(b) demand-side management programs established and implemented in accordance with 69-3-1209;
(c) the cost-effective expenditures for improving the efficiency with which the public utility provides and its customers use utility services;
(d) the costs of complying with the planning requirements of this part; and
(e) the costs of complying with a competitive solicitation process conducted in accordance with 69-3-1207.
(2) The commission may adopt rules establishing criteria governing the extent of recovery of abandonment costs.
(3) The commission may not approve a bonus or adder in the cost of a new resource acquired after April 28, 2021, to provide additional compensation for costs such as environmental externalities unless the bonus or adder is necessary to compensate for a real and actual cost required by existing regulation or existing law.
(1) (a) Except as provided in subsection (6), a public utility that intends to establish [rates] for the acquisition, construction, or purchase of an electricity supply resource shall conduct a competitive solicitation process.
(b) A public utility may not prohibit a qualifying small power production facility as defined in 69-3-601 or another utility or supplier that owns an electricity supply resource or intends to construct an electricity supply resource from participating in a competitive solicitation process.
(c) An independent evaluator must be used to oversee a public utility's competitive solicitation. The commission shall select the independent evaluator pursuant to subsection (4).
(d) An independent evaluator:
(i) shall monitor the evaluation of bids pursuant to a competitive solicitation;
(ii) shall provide oversight to ensure a fair and transparent competitive solicitation;
(iii) must be familiar with competitive bid and evaluation processes; and
(iv) shall evaluate and document the process used by the public utility to solicit and evaluate bids received during a competitive solicitation.
(e) A public utility may conduct a competitive solicitation in conjunction with the development of an integrated least-cost plan in accordance with 69-3-1204.
(2) A public utility that plans to conduct a competitive solicitation process shall submit the following information to the commission:
(a) a description of the competitive solicitation process that the public utility will use and proof of compliance with subsections (1)(b) and (1)(c), if applicable; and
(b) a complete draft of the proposal soliciting electricity supply resources, citing the requested resource parameters and inviting bids from all resource types.
(3) The commission shall provide notice and accept public comment regarding information received in accordance with subsection (2).
(4) (a) Subject to public comments received pursuant to subsection (4)(b), the commission shall:
(i) solicit, evaluate, and maintain a list of independent evaluators for the competitive solicitation process;
(ii) develop a process to disqualify and remove from the list those independent evaluators who do not comply with established qualifications or who may have a conflict of interest;
(iii) update the list at least every 3 years; and
(iv) after information is submitted to the commission in accordance with subsection (2) and subject to rules adopted by the commission pursuant to subsection (4)(c), select an independent evaluator from the list.
(b) The commission shall accept public comment when developing and updating the list.
(c) On or before July 1, 2026, the commission shall adopt rules for:
(i) evaluating independent evaluators for inclusion on the list;
(ii) selecting an independent evaluator in accordance with this section;
(iii) implementing this subsection (4); and
(iv) prescribing the scope of work for the independent evaluator pursuant to the duties in 69-3-1210.
(5) (a) The commission may charge a fee to the public utility to pay for the costs of selecting and representing an independent evaluator. This fee must be deposited in the state special revenue fund to the credit of the department for expenses incurred selecting the independent evaluator. These costs are recoverable in rates.
(b) After the commission selects an independent evaluator in accordance with subsection (4), the public utility shall execute a contract for service with the independent evaluator. The contract must include the scope of work developed pursuant to subsection (4)(c)(iv) and the duties in 69-3-1210.
(6) This section does not apply to:
(a) a request for proposals or purchase by a public utility intended solely to meet the short-term operational needs of the utility for a period of less than 12 months; or
(b) an application made to the commission by a public utility to acquire, construct, or purchase an opportunity resource.
(7) For the purposes of this section, "opportunity resource" means an electricity supply resource necessary to meet a need demonstrated in a plan in accordance with 69-3-1204(2)(a)(iv) that is either new or existing and that remains unknown as to its availability for purchase until an opportunity to purchase arises.
(1) A public utility shall maintain a broad-based advisory committee to review, evaluate, and make recommendations on technical, economic, and policy issues related to a utility's electricity system.
(2) The committee may advise the utility on demand-side management, portfolio planning, and management and procurement completed in accordance with this part.
(3) The utility shall publish the committee membership.
(4) A committee meeting must be open to the public unless the majority of committee members vote to close the advisory meeting.
(1) The commission may establish energy savings and peak demand reduction goals for an electric utility, taking into account the utility's cost-effective demand-side management potential and the need for electricity resources.
(2) The commission shall permit electric utilities to implement cost-effective electricity demand-side management programs and conservation in accordance with 69-3-701 through 69-3-712 and this part to reduce the need for additional resources.
(3) Every 3 years, an electric utility shall submit a report to the commission describing the demand-side management programs and conservation implemented by the electric utility in the previous year. The report must document:
(a) program expenditures, including incentive payments;
(b) peak demand and energy savings impacts and the techniques used to estimate those impacts;
(c) avoided costs and the techniques used to estimate those costs;
(d) the estimated cost-effectiveness of the programs;
(e) the net economic benefits of the programs; and
(f) any other information required by the commission.
(1) The independent evaluator shall oversee the competitive solicitation conducted by the public utility to protect the public interest and advance the policies in 69-3-1202.
(2) The independent evaluator shall:
(a) provide comments to the public utility and the commission on the fairness, transparency, and consistency of a competitive solicitation process with industry standards;
(b) monitor, evaluate, and observe the competitive solicitation process, paying particular attention to the public utility's evaluation of electric supply resources that may result in utility ownership of the resource to ensure that the utility conducts a fair and proper process in accordance with industry standards;
(c) notify the utility and the commission on a timely basis prior to the utility selection of the resources of any discrepancies observed in the process and resolve any differences of opinion; and
(d) prepare a closing report prior to the final selection of the resources regarding the fairness, transparency, and consistency of the process, including selection and notification of electricity supply resources taking part in the solicitation process based on industry standards. Public utilities shall include the closing report in applications for future cost-recovery dockets. The closing report must be made available to the public.
(3) The commission shall grant the independent evaluator the right of intervention in future cost-recovery proceedings for the purpose of entering the closing report into the evidentiary record during discovery and hearings.