If no time is specified for the performance of an act required to be performed, a reasonable time is allowed. If the act is in its nature capable of being done instantly (for example, if it consists in the payment of money only), it must be performed immediately upon the thing to be done being exactly ascertained.
28-3-602. When time considered of the essence.
Time is never considered as of the essence of a contract unless by its terms expressly so provided.
28-3-603. Postponement of performance date which falls on holiday.
Whenever any act of a secular nature other than a work of necessity or mercy is appointed by contract to be performed upon a particular day which day falls upon a holiday, such act may be performed upon the next business day with the same effect as if it had been performed upon the day appointed.