Criteria for allowable advanced conductor programs

69-3-714. Criteria for allowable advanced conductor programs. (1) The commission may approve cost-effectiveness criteria for advanced conductor projects that may be placed into a utility's rate base under this part.

(2) Criteria must be based on established direct current resistance at standard pressure and a temperature of 20 degrees Celsius.

(3) As used in this section, "advanced conductor" means an overhead electricity conductor installed in a transmission or distribution project that has a direct current electrical resistance at least 10% lower than existing conductors of a similar diameter on the system.

(4) In establishing cost-effectiveness criteria, the commission may consider decreased electrical losses and any other relevant consumer, environmental, and system benefits provided by advanced conductors.